Carrier Has Duty to Defend Claim for Active Malfunction of Product
October 19, 2020 —
Tred R. Eyerly - Insurance Law HawaiiRejecting that the underlying claim was based solely on faulty workmanship, the Third Circuit held the insurer had a duty to defend allegations of a malfunctioning product. Nautilus Ins. Co. v. 200 Christina Street Partners LLC, 2020 U.S. App. LEXIS 22118 (3d Cir. July 16, 2020).
The insureds were sued by homeowners in two separate suits alleging defects in the construction of their homes. Nautilus defended under a reservation of rights. Nautilus filed suit in District Court and moved for judgment on the pleadings. The District Court denied the motion, finding Nautilus had a duty to defend because the underlying claims sufficiently alleged product--related tort clams that could fall within the scope of coverage under the relevant policies.
The Third Circuit affirmed. There was a distinction between a claim of faulty workmanship, for which the insurer did not have a duty to defend, and a claim of "active malfunction" of a product, for which an insurer did have such a duty. An active malfunction was sufficiently fortuitous as to constitute an "occurrence."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Contract Construction Smarts: Helpful Provisions for Dispute Resolution
June 03, 2019 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday, Musings welcomes back Doug Reiser (@douglasreiser), though from new digs. Doug is a construction attorney, LEED AP and the principal at Reiser Legal LLC in Seattle, WA. His office provides effective construction counsel for businesses in the construction industry. He also runs the Builders Counsel Blog, a blog focused on progressive issues in Washington construction law. Doug is a former partner/member at Wolfe Law Group LLC and former owner and director of Express Lien Inc.
There are many types of attorneys out there, but there are certainly two styles: ones looking for the fight and ones trying to prevent the fight. I take the preventative approach. Client funds do not grow on trees. That old saying “an ounce of prevention is worth a pound of cure” should say a “ton of cure.” It’s that valuable.
Sometimes the problem for prevention attorneys is trying to relay that message to a construction business. The cost of smart prevention is mainly thought of as just that – a cost. But when it buys you a cure for pennies on the dollar, it’s worth it. You will know it’s worth it when you finally become engaged in a costly three year long legal proceeding over a construction dispute.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Tejon Ranch Co. Announces Settlement of Litigation Related to the Tejon Ranch Conservation and Land Use Agreement
December 05, 2022 —
Tejon Ranch Co.TEJON RANCH, Calif., Nov. 30, 2022 (GLOBE NEWSWIRE) -- Tejon Ranch Co. is pleased to announce the resolution of a legal dispute involving the Tejon Ranch Conservancy and the signatories to the 2008 Tejon Ranch Conservation and Land Use Agreement (Agreement), namely, Audubon California, Endangered Habitats League, Natural Resources Defense Council, Planning and Conservation League, and the Sierra Club. The dispute stemmed from the signatories' participation in the Antelope Valley Regional Conservation Strategy (AVRCIS), which was subsequently used by the Center for Biological Diversity (CBD) and the California Native Plant Society (CNPS) to oppose Tejon Ranch Co.'s Centennial development.
The 2008 Tejon Ranch Conservation and Land Use Agreement has been widely hailed as a historic conservation achievement in preserving one of California's great natural and working landscapes. Tejon Ranch Co.'s agreement to conserve 90 percent of its landholdings pursuant to the Agreement is a monumental contribution to conservation in California. Tejon Ranch Co. continues to be a leader in balancing the stewardship of the ranch as a natural treasure for California and achieving economic opportunities for its shareholders. The Company demonstrated that leadership with the actions it took to enforce the terms of the Agreement, which led to this legal dispute.
As part of a settlement agreement, the Conservancy and the signatories dismissed with prejudice the lawsuit they filed. They also acknowledge that the AVRCIS does not contain the "best available scientific data" regarding Tejon Ranch Co.'s landholdings, and further, that they will not use, or support the use of, the AVRCIS or any other similar endeavors, to challenge Tejon Ranch Co.'s development projects and/or any Ranch uses consistent with the Agreement.
In turn, Tejon Ranch Co. released from escrow 50% of the advance payments it withheld under the terms of the Agreement. The remaining funds will be released over a three-year period as matching funds to monies raised by the Conservancy as well as others who participate in Conservancy capital raising programs, after which the remaining funds with be released to the Conservancy to further its mission. These funds are the final fulfilment of Tejon Ranch Co.'s full funding obligations under the Agreement, totaling $11,760,000 over the past 14 years, again demonstrating Tejon Ranch Co.'s commitment to fulfilling the implementation of the 2008 Tejon Ranch Conservation and Land Use Agreement.
All parties are glad to put this dispute behind them and move forward in a cooperative manner to achieve the goals envisioned in the historic 2008 Agreement.
About Tejon Ranch Co.
Tejon Ranch Co. (NYSE: TRC) is a diversified real estate development and agribusiness company, whose principal asset is its 270,000-acre land holding located approximately 60 miles north of Los Angeles and 30 miles south of Bakersfield. More information about Tejon Ranch Co. can be found on the Company's website at www.tejonranch.com.
Forward Looking Statements
This press release contains forward-looking statements, including without limitation statements regarding commitments of the parties under the settlement agreement and the achievement of certain goals related to Tejon Ranch Co.'s landholdings. These forward-looking statements are not a guarantee of future results, performance, or achievements, are subject to assumptions and involve known and unknown risks, uncertainties and other important factors that could cause the actual results, performance, or achievements to differ materially from those implied by such forward-looking statements. These risks, uncertainties and important factors include, but are not limited to, the ability and willingness of the parties to the Settlement Agreement to take the actions (or refrain from taking the actions) specified in the Settlement Agreement, and the risks described in the section entitled "Risk Factors" in our annual and quarterly reports filed with the SEC.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contracts Need Amending Post COVID-19 Shutdowns
October 19, 2020 —
Richard P. Higgins - Construction ExecutiveNo one could have expected the coronavirus pandemic in the beginning of 2020. True, there were rumblings about a sickness in China that was highly contagious and infecting many people. Death tolls began rising as the world watched in disbelieve. After all, this is 2020. This is not supposed to happen. We should have been able to control the spread of the virus, but we could not. COVID-19 quickly spread throughout the world causing havoc and economic despair.
While some sectors of the construction industry are not as impacted as others, contractors industry-wide need to consider how COVID-19 will impact their contractual obligations. Depending on what happens and what the government decides to do to stop the spread of the coronavirus, project delays, supply chain distributions, lost productivity and work stoppages may continue for months. All of this will impact the contracts that contractors have with owners. Contractors may not be able to preform according to the terms of the contract through no fault of their own. Owners may no longer qualify for the financing needed to pay for the project.
FORCE MAJEURE
According to Investopedia, “force majeure refers to a clause that is included in contracts to remove liability for natural and unavoidable catastrophes that interrupt the expected course of events and prevent participants from fulfilling obligations.”
Reprinted courtesy of
Richard P. Higgins, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Higgins may be contacted at
Richard.Higgins@MCC-CPAs.com
Construction Litigation Roundup: “Ursinus is Cleared!”
March 11, 2024 —
Daniel Lund III - LexologyUrsinus University in Pennsylvania – a “private, nonprofit liberal arts college” – funded a construction project for a new building utilizing monies loaned by the Montgomery County Health and Higher Education Authority, a public economic development authority “formed by the Board of County Commissioners… authorized to issue bonds relative to projects for eligible educational institution such as Ursinus.”
Loans up to the amount of $23,000,000 became available to the University, and construction proceeded using the loans as construction funds. At issue: whether a project was to be considered publicly funded project such that prevailing wage rates were required to be paid. IBEW filed a related grievance with the Pennsylvania Department of Labor and Industry’s Bureau of Labor Law Compliance, which was refused by the Bureau, on the basis that because work was “financed completely by loans from the Authority, which Ursinus was required to repay in their entirety, the Project was ultimately funded through private sources and exempt from coverage under the [Pennsylvania Prevailing Wage Act].” A grievance to the Prevailing Wage Appeals Board ensued, and the Board took a different position.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
New Zealand Using Plywood Banned Elsewhere
October 30, 2013 —
CDJ STAFFCopper chromium arsenate helps protect wood against insect damage and fungal growth. Unfortunately, its use leads to arsenic exposure. The safety concerns over CCA for both construction workers and the people who later use the buildings have led to the CCA-treated plywood being banned or restricted in most countries, including the United States, Canada, France, the United Kingdom, and Germany.
New Zealand is not on the list of countries restricting or banning CCA-treated wood. Dr. Merial Watts, a science coordinator for Pesticide Action Network NZ described the product as an “unacceptable public health risk,” and said that “wrapping homes in CCA-treated plywood is a very bad idea.”
One construction official, speaking anonymously, noted that “workers have to handle it with gloves and full body suits,” but those guidelines may not be followed. A foreman on a building site said “I know about the treatment but I don’t take many precautions.”
Read the court decisionRead the full story...Reprinted courtesy of
McDermott International and BP Team Arbitrate $535M LNG Site Dispute
April 02, 2024 —
Mary B. Powers - Engineering News-RecordBP and Kosmos Energy are seeking “maximum recoverable damages” of about $535 million in binding arbitration with contractor McDermott International over a claim that it failed to meet contract obligations on subsea pipeline installation for an estimated $4.8 billion liquefied natural gas project off Africa.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Industry Standard and Sole Negligence Defenses Can’t Fix a Defect
June 14, 2021 —
Lian Skaf - The Subrogation StrategistStrict products liability cases have been the subject of much fluctuation in the Pennsylvania courts over the last few years. Utilizing hope created by the courts in recent strict liability cases, defendants have tried to revive defenses based on meeting industry standards and the plaintiff’s contributory negligence. Recently, the Superior Court of Pennsylvania tempered that hope with limitations of how far strict liability defenses can extend.
In Sullivan v. Werner Co., No. 3086 EDA 2019, 2021 Pa. Super. LEXIS 210, an appellate panel of the Superior Court reviewed the lower court’s decision to exclude evidence of industry standards and of the plaintiff’s negligence in a trial that resulted in a $2.5 million verdict for the plaintiff. Upholding the decision of the lower court, the court found that the proffered evidence was within the discretion of the court to exclude.
In Sullivan, Michael Sullivan (Sullivan) was working as a union carpenter at a renovation project for a local school. He and his apprentice were installing exterior sheathing to the outdoor walls. In order to install the sheathing, Sullivan had to use a scaffold. He put together a new SRS-72 scaffold manufactured by Werner Company (Werner) that his foreman bought at Lowe’s Companies, Inc. (Lowe’s) and used the scaffold during the course of his work. While on the scaffold, Sullivan fell through and crashed to the ground. He suffered permanent injuries as a result of the incident.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com