Not in My Kitchen – California Supreme Court Decertifies Golden State Boring Case
November 26, 2014 —
Roger Hughes – California Construction Law BlogOn November 11, 2014, the California Supreme Court rejected the recent California Court of Appeals decision Golden State Boring & Pipe Jacking, Inc. v Eastern Municipal Water District, 228 Cal.App.4th 273 (2014) which we wrote about earlier by “decertifying” it (meaning that lawyers cannot cite to the case as legal precedent) The decertification removed a decision that added substantially to the confusion as to when an action on a payment bond is timely filed. Even though the decision was determined in accordance with pre-2014 statutes, the case was relevant precedent for construction attorneys when determining time deadlines for filing a claim on a bond.
Background
In July of this year, the California Court of Appeals for the Fourth Appellate District upheld a trial court’s granting of summary judgment against a project subcontractor Golden State Boring & Pipe Jacking, Inc. (GSB) who sued Safeco Insurance Company (Safeco) for unpaid contract amounts on a project payment bond issued by Safeco. Both at the trial level and on appeal Safeco successfully argued that GSB’s action on its payment bond claim was time barred by former California Civil Code Sections 3249 (now Section 9558), because it was filed more than six month after the period in which stop notices may be filed as provided by California’s Civil Code Section 3184 (now Section 9558).
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Owners Bound by Arbitration Clause on Roofing Shingles Packaging
December 04, 2018 —
David Adelstein - Florida Construction Legal UpdatesIn today’s age, you are probably familiar with terms such as a shrinkwrap contract (terms and conditions), which is a boilerplate contract included with a retained product, or a clickwrap contract (terms and conditions), which is generally a boilerplate contract that is digitally accepted when purchasing software or an electronic product. These are are boilerplate terms from manufacturers or vendors of products or software. Arbitration provisions in these types of agreements have generally found to be enforceable.
In the recent ruling by the Eleventh Circuit Court of Appeals in Dye v. Tamko Building Products, Inc., 2018 WL 5729085 (11th Cir. 2018), the court held that an arbitration provision included in a product-purchase limited warranty agreement on the package of every roofing shingles binds a homeowner to arbitrating disputes over the opened and retained product with the manufacturer, irrespective of whether the shingles were purchased by an owner’s roofer. The shingles do not have to be purchased and opened by the owner for the arbitration provision to apply. If the roofer uses or retained the shingles for purposes of the owner’s home, such knowledge of the product-purchase limited warranty agreement on the packaging of the shingles is imputed to the owner (end-user of the shingles).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Results are in, CEO/Founding Partner Nicole Whyte is Elected to OCBA’s 2024 Board of Directors!
October 09, 2023 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is excited to share that CEO/Founding Partner Nicole Whyte has been elected to the Orange County Bar Associations (“OCBA”) slate of four open Board of Directors for a three-year term beginning January 2024, alongside Casey Johnson (Aitken Aitken Cohn LLP), William O’Neill (Ross, Wolcott, Teinert & Prout LLP), and Lesley Young (Orange County District Attorney’s Office).
“It is one of the greatest honors of my career to have been elected to the OCBA board of directors. Thank you to all those who supported me; I will work tirelessly as your representative to serve our bar and community. I am especially excited to work alongside President Elect Christina Zabat-Fran and the other esteemed members of the board. I look forward to applying my skills and knowledge to serve our legal community as we work to promote excellence, integrity and honor in our profession, and to improve the practice for all.” – Nicole Whyte
Nicole is honored to have the opportunity to continue her support with the OC legal community. For over two decades, she has served on various OCBA legal committees and boards. Nicole currently serves on the board of OCBA Master’s Division and is the 2023 Board President of the Public Law Center, the largest pro-bono law firm in Orange County. She is also a current board member of the Sonenshine Pro Bono Committee. Nicole is a founding fellow of the OC Bar Foundation and served as secretary for the Robert Banyard Inn of Court for eight years. Nicole plans to call upon her experience serving on various boards, and her many years of law practice and management experience, to help identify and support the needs of the OCBA and its thriving and diverse OC legal community.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Broker for Homeowners Policy Has No Duty to Advise Insureds on Excess Flood Coverage
November 02, 2017 —
Tred R. Eyerly - Insurance Law HawaiiA broker who assisted the insureds in procuring a homeowners policy had no duty to advise the insureds to secure additional flood coverage. Ring v. Meeker Sharkey Assocs., LLC, 2017 N.J. Super. Unpub. LEXIS 3458 (N.J. Super Ct. App. Div. Sept.26, 2017).
The insureds owned two beachfront properties that were located in a designated flood zone. They secured homeowners and flood insurance through Meeker's predecessor. Subsequently, Meeker became the insureds' homeowners insurance broker while Willis, N.A. was their flood insurance broker.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Senior Living Facility Makes Construction Defect Claims
November 13, 2013 —
CDJ STAFFMidland Meadows Senior Living, LLC has filed a petition for declaratory judgment in the U.S. District Court in West Virginia, claiming that the contractor who built the facility, Arcon Group Incl, made a variety of errors, leading to mold and lack of water in the dining room, but also that floors were improperly constructed, sump pumps were not installed, and that the company failed to properly insulate the buildings.
The lawsuit also names Arcon Group’s insurer, First Mercury Insurance Company.
Read the court decisionRead the full story...Reprinted courtesy of
Be Careful With Construction Fraud Allegations
April 06, 2016 —
Christopher G. Hill – Construction Law MusingsHere at Construction Law Musings we have discussed the intersection of contracts, construction and fraud on several occasions. We’ve even discussed how such fraud can bleed over from the civil to the criminal.
Recently, the Virginia Supreme Court weighed in again on the question of construction fraud and criminal allegations. In O’Connor v. Tice, the Court discussed a malicious prosecution action brought by a contractor against owners of a commercial building. In O’Connor, the owners and the contractor got into a disagreement over alleged damage to the roof of the owners’ building and who was responsible. In response to this disagreement, the owners contacted the local sheriff’s office, accusing the contractor of construction fraud, and then wrote a “15 day letter” to the contractor outlining the criminal consequences should he fail to pay the damages sought in the owners civil lawsuit. Subsequently, a criminal warrant was issued against the contractor based solely upon the word of the owners. This last occurred at the insistence of the owners (who did not inform the sheriff’s deputy or the Commonwealth Attorney that they’d had this conversation or that the contractor had partially performed) after they discussed the matter with the contractor’s attorney and were informed that any claim that they may have had was civil in nature.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Construction Law MusingsMr. Hill may be contacted at
chrisghill@constructionlawva.com
A Word to the Wise: The AIA Revised Contract Documents Could Lead to New and Unanticipated Risks - Part II
October 16, 2018 —
George Talarico - Construction ExecutivePart I addressed general conditions, revised insurance terms, revisions that affect owner’s required insurance and revisions that affect contractor’s required insurance.
REVISIONS THAT AFFECT DISPUTE RESOLUTION
A seemingly minor but noteworthy change is to the definition of “Claim.” Under Section 15.1 a “Claim” is defined to:
- include a request for a modification of contract time; and
- exclude any requirement that an owner must file a claim to impose liquidated damages.
Notably, any request relating to contract time must be brought within the specified time period for Notice of Claim and in the prescribed manner. There are at least two traps for the unwary. First, even though email is regularly used for communications among the parties, the revised contract documents do not recognize email as an acceptable form of delivery of a Notice of Claim. Second, an unwary contractor may wrongly assume that an owner’s failure to assert a claim for LDs means that LDs will not be imposed. This may lull the contractor into failing to timely assert its own claim for a time extension and thereby waiving its ability to do so.
Reprinted courtesy of
George Talarico, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Talarico may be contacted at
gtalarico@sillscummis.com
Miller Act Statute of Limitations and Equitable Tolling
July 11, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to a Miller Act payment bond claim, there is a one-year statute of limitations—“The Miller Act contains a statute of limitations provision that requires actions to ‘be brought no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the claim.’” U.S. f/u/b/o Techniquex Specialty Flooring, Inc., v. Philadelphia Indemnity Ins. Co., 2022 WL 169070, *3 (M.D.Penn. 2022) (citing the Miller Act).
There is an argument, albeit a difficult one, to support an equitable tolling of the one-year statute of limitations. This would be an argument filed when the one-year statute of limitations expires, but there is reason for missing the statute of limitations caused typically by the overt misleading of the defendant (surety/bond-principal):
“Equitable tolling functions to stop the statute of limitations from running where the claim’s accrual date has passed.” “Equitable tolling is appropriate in three situations: (1) when the defendant has actively misled the plaintiff respecting the facts which comprise the plaintiff’s cause of action; (2) when the plaintiff in some extraordinary way has been prevented from asserting his rights; and (3) when the plaintiff has timely asserted his rights in the wrong forum.” The first ground for equitable tolling“appears to be the same, in all important respects” to equitable estoppel, which “excuses late filing where such tardiness results from active deception on the part of the defendant” and “what courts describe as ‘equitable tolling’ is encompassed by the latter two parts of our Circuit’s doctrine.” The extraordinary circumstances standard may be met “where the defendant misleads the plaintiff, allowing the statutory period to lapse; or when the plaintiff has no reasonable way of discovering the wrong perpetrated against her …”
Tehniquex, supra, at *5 (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com