Teaching An Old Dog New Tricks: The Spearin Doctrine and Design-Build Projects
October 30, 2018 —
John Castro - Gordon & Rees Construction Law BlogThe United States District Court for the Southern District of California has now held that the Spearin doctrine applies to design-build subcontractors where the subcontractor is expected to design a portion of their work. The case is United States for the use and benefit of Bonita Pipeline, Inc., et al. v. Balfour Beatty Construction, LLC, et al. (“Bonita Pipeline”) (Case No. 3:16-cv-00983-H-AGS).
In Bonita Pipeline, a subcontractor sued the general contractor and its sureties alleging breach of contract, breach of implied warranty, declaratory relief, and recovery under the Miller Act. The subcontractor then filed a motion for partial summary judgment against the general contractor on its declaratory relief cause of action, seeking a finding that the general contractor could not shift legal responsibility for its defective plans and specifications to the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
John Castro, Gordon & Rees Scully MansukhaniMr. Castro may be contacted at
jcastro@grsm.com
California Mediation Confidentiality May Apply to Third Party “Participants” Retained to Provide Analysis
November 02, 2017 —
Tony Carucci - Snell & Wilmer Real Estate Litigation BlogCalifornia Evidence Code section 1119 governs the general admissibility of oral and written communications generated during the mediation process. Section 1119(a) provides that “[n]o evidence of anything said or any admission made
for the purpose of, in the course of, or pursuant to, a mediation . . . is admissible or subject to discovery, and disclosure of the evidence shall not be compelled, in any . . . civil action . . . .” Cal. Evid. Code § 1119(a) (emphasis added). Similarly, section 1119(b) bars discovery or admission in evidence of any “writing . . . prepared
for the purpose of, in the course of, or pursuant to, a mediation . . . .” Cal. Evid. Code § 1119(b) (emphasis added). Finally, section 1119(c) provides that “[a]ll communications, negotiations, or settlement discussions by and between
participants in the course of a mediation . . . shall remain confidential.” Cal. Evid. Code § 1119(c) (emphasis added).
Read the court decisionRead the full story...Reprinted courtesy of
Tony Carucci, Snell & WilmerMr. Carucci may be contacted at
acarucci@swlaw.com
Cal/OSHA ETS: Newest Version Effective Today
January 17, 2022 —
Amy R. Patton, Matthew C. Lewis & Rana Ayazi - Payne & FearsThe newest version of the Cal/OSHA ETS goes into effect today, Jan. 14, 2022, and will expire on April 15, 2022. A redline of the recently expired Cal/OSHA ETS and the newest Cal/OSHA ETS is available HERE. The newest Cal/OSHA ETS, which was drafted prior to Dec. 16, 2021, is already partially out-of-date based on the California Department of Public Heath’s Guidance For the Use of Masks (released Jan. 5, 2022) and the CDPH’s Guidance for Local Health Jurisdictions on Isolation and Quarantine of the General Public (released Jan. 8, 2022); these changes have been addressed in the Cal/OSHA ETS FAQs.
With all of these changes occurring (not to mention all of the litigation surrounding the now-stayed federal OSHA ETS), California employers are asking: How do I comply with the current Cal/OSHA ETS and the updated CDPH Guidance? Here are the key points to ensure you are in compliance:
- New Shorter Isolation and Quarantine Periods
Isolation: When an employee has COVID-19 (even without symptoms).
- Day 0: First day of symptoms or the day a positive test specimen was collected. Begin isolation.
- Day 1: First full day after symptoms developed or positive test specimen was collected.
- Day 5: Recommended day to take COVID-19 test.
Reprinted courtesy of
Amy R. Patton, Payne & Fears,
Matthew C. Lewis, Payne & Fears and
Rana Ayazi, Payne & Fears
Ms. Patton may be contacted at arp@paynefears.com
Mr. Lewis may be contacted at mcl@paynefears.com
Ms. Ayazi may be contacted at ra@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
The Washington Supreme Court Rules that a Holder of a Certificate of Insurance Is Entitled to Coverage
March 09, 2020 —
Sally Kim & Kyle Silk-Eglit - Gordon & Rees Insurance Coverage Law BlogThe Washington courts have historically found that the purpose of a certificate of insurance is to advise others as to the existence of insurance, but that a certificate is not the equivalent of an insurance policy. However, the Washington State Supreme Court recently held that, under certain circumstances, an insurer may be bound by the representations that its insurance agent makes in a certificate of insurance as to the additional insured (“AI”) status of a third party. Specifically, in T-Mobile USA, Inc. v. Selective Ins. Co. of America, the Supreme Court found that where an insurance agent had erroneously indicated in a certificate of insurance that an entity was an AI under a liability policy, that entity would be considered as an AI based upon the agent’s apparent authority, despite boilerplate disclaimer language contained in the certificate. T-Mobile USA, Inc. v. Selective Ins. Co. of America, Slip. Op. No. 96500-5, 2019 WL 5076647 (Wash. Oct. 10, 2019).
In this case, Selective Insurance Company of America (“Selective”) issued a liability policy to a contractor who had been retained by T-Mobile Northeast (“T-Mobile NE”) to construct a cell tower. The policy conferred AI status to a third party if the insured-contractor had agreed in a written contract to add the third party as an AI to the policy. Under the terms of the subject construction contract, the contractor was required to name T-Mobile NE as an AI under the policy. T-Mobile NE was therefore properly considered as an AI because the contractor was required to provide AI coverage to T-Mobile NE under the terms of their contract.
However, over the course of approximately seven years, Selective’s own insurance agent issued a series of certificates of insurance that erroneously identified a different company, “T-Mobile USA”, as an AI under the policy. This was in error because there was no contractual requirement that T-Mobile USA be added as an AI. Nonetheless, the certificates stated that T-Mobile USA was an AI, and they were signed by the agent as Selective’s “authorized representative.”
Reprinted courtesy of
Sally S. Kim, Gordon & Rees and
Kyle J. Silk-Eglit, Gordon & Rees
Ms. Kim may be contacted at sallykim@grsm.com
Mr. Silk-Eglit may be contacted at ksilkeglit@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
Arbitration—No Opportunity for Appeal
October 22, 2014 —
Craig Martin – Construction Contractor AdvisorLast week I presented to the Great Plains Chapter of the American Society of Professional Estimators on arbitration and litigation. Some of the questions related to the difficulty of appealing an arbitrator’s decision. A Florida appellate court recently confirmed this difficulty.
In Village at Dolphin Commerce Center, LLC v. Construction Service Solutions, LLC, a contractor filed an arbitration claim against the owner to get paid for its work. The owner claimed that the contractor could not maintain the claim to get paid because the contractor was not licensed. Apparently, there is a law in Florida that a contractor unlicensed at the time of the contract cannot maintain an action in Florida for unpaid work.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Certain Private Projects Now Fall Under Prevailing Wage Laws. Is Yours One of Them?
November 21, 2022 —
Nancy Cox - Construction ExecutiveFor the last few years, New York State Labor Law has required that all contractors overseeing public development projects pay their workers the prevailing wage rate, which includes a regulated hourly rate for wage and benefits. Fast forward to 2022, the requirements of Section 224-A are extending to private projects costing more than $5 million where 30% or more of the financing for the construction costs was obtained from public sources like state or local funding.
There are a number of forms of financing that qualify as public funding, and its important for developers to understand exactly how these are defined under the new law. Public funding includes any indirect or direct payment from government authorities, savings from fees, tax credits or payments in lieu of taxes, loans from public entities and more.
In order to provide further clarity, the law also clearly defined certain project exemptions to the new rule. First, affordable housing projects will not be affected, along with historic rehabilitation projects or small renewable energy projects. Also, projects for established non-profit companies receive an exemption as long as the company reports gross annual revenues less than $5 million. Other exemptions include projects for schools under 60,000 square feet and those funded by the Urban Development Corporation’s Restore New York's Communities Initiative.
Reprinted courtesy of
Nancy Cox, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Supreme Court Limits the Powers of the Nation’s Bankruptcy Courts
June 11, 2014 —
Earl Forte – White and Williams LLPOn June 9, 2014, the Supreme Court of the United States issued its much-awaited decision in Executive Benefits Insurance Agency v. Arkison, Chapter 7 Trustee of Estate of Bellingham Insurance Agency, Inc., Case No. 12-1200, in which the court confirmed that the power of the nation’s bankruptcy courts to hear and decide cases involving state-created private rights in which the bankruptcy proof of claim process has not been directly invoked, is severely limited by Article III of the Constitution of the United States.
The decision in Executive Benefits, while providing some clarity to practitioners and the public following the Court’s June 2011 decision in Stern v. Marshall, 131 S. Ct. 2594 (2011), nevertheless will make a substantial portion of bankruptcy litigation matters more cumbersome and potentially more expensive to guide through the bankruptcy system. Clients and practitioners are best advised to hire knowledgeable counsel to help navigate the more complex procedural waters created by this decision.
Although the Court in Executive Benefits did resolve a pending procedural question that had dogged practitioners since Stern was decided in 2011, the Court’s decision in Executive Benefits now makes it abundantly clear that many disputes that were previously heard and decided in the nation’s bankruptcy courts can no longer be decided there and must be submitted to the district courts for full de novo review and entry of a final judgment or order. It is difficult to see how this decision will not make bankruptcy litigation more cumbersome and expensive by adding an additional layer of judicial involvement to many matters, notably to fraudulent transfer and other avoidance “claw back” actions that historically have been decided in the bankruptcy courts and used famously in Madoff and other cases as an efficient device for creating value for creditors.
Read the court decisionRead the full story...Reprinted courtesy of
Earl Forte, White and Williams LLPMr. Forte may be contacted at
fortee@whiteandwilliams.com
Out of the Black
May 30, 2022 —
John Drentlaw - Construction ExecutiveEven if you previously weren’t familiar with the term “black swan event,” you’ve likely become intimately familiar with what one looks like over the past two years. Coined by author Nassim Taleb in his book The Black Swan: The Impact of the Highly Improbable, the term refers to a rare, unpredictable event—perhaps, say, a pandemic—that has an extreme impact.
“Extreme” certainly seems to be an accurate description of the impact that the COVID-19 pandemic has had on the construction industry, at nearly every level. The Commercial Construction Index (CCI) fell from 74 to 56 during Q2 2020 and remained statistically unchanged through Q3 of that year. Recovery has been slow, with the CCI remaining eight points below pre-pandemic levels through the end of 2021. Prices for raw materials such as lumber and steel have been extremely volatile, reaching historic highs and dramatic lows. March and April of 2020 alone saw 1.1 million jobs disappear from the industry—roughly half as many jobs as were lost throughout the entire Great Recession (although many of these jobs have since returned).
While the industry has persevered through what should be the worst of these effects, many contractors and project owners are now wondering: How can we predict the next black swan event?
Reprinted courtesy of
John Drentlaw, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of