New Jersey Court Upholds Registration Requirement for Joint Ventures Bidding on Public Works Contracts
December 16, 2023 —
Nicholas J. Zaita & Brian Glicos - Peckar & Abramson, P.C.Introduction
In a matter of “first impression,” on November 30, 2023, the Appellate Division affirmed the New Jersey Superior Court decision in
Ernest Bock & Sons-Dobco Pennsauken Joint Venture v. Township of Pennsauken and Terminal Construction Corp., finding that the New Jersey Public Works Contractor Registration Act, N.J.S.A. 34:11-56.48 to -56.57 (“PWCRA” or the “Act”), applies to a joint venture formed for the sole purpose of bidding on a public works contract. Therefore, the Court held that the PWCRA requires any joint venture bidding on public works projects in New Jersey to be registered under the Act at the time of bid submission. Accordingly, the Township of Pennsauken acted within its authority and properly rejected the bid submission of the Ernest Bock & Sons-Dobco Joint Venture which was not registered under the Act in the name of the joint venture at the time of its bid submission, despite the individual members of the joint venture being registered.
Reprinted courtesy of
Nicholas J. Zaita, Peckar & Abramson, P.C. and
Brian Glicos, Peckar & Abramson, P.C.
Mr. Zaita may be contacted at nzaita@pecklaw.com
Mr. Glicos may be contacted at bglicos@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Appellate Court of Maryland Construes Notice Conditions of A312 Performance Bond in Favor of Surety
January 02, 2024 —
Joel P. Williams - White and Williams LLPThe Appellate Court of Maryland issued a reported opinion in a case construing an American Institute of Architects (“AIA”) A312 performance bond. In Wildewood Operating Company, LLC v. WRV Holdings, LLC, et al. 2023 Md. App. LEXIS 720 (Oct. 30, 2023), the Appellate Court of Maryland held that a performance bond surety was discharged from liability where the owner/obligee failed to give the surety notice of the contractor’s default termination until after a third party had completed the work.
The project concerned the construction of an assisted living facility in St. Mary’s County, Maryland. The owner, Wildewood Operating Company, LLC, entered into an A312-2010 performance bond with Clark Turner Construction, LLC, as contractor, and First Indemnity of America Insurance Company, as surety. When Clark Turner failed to complete certain stormwater management work adjacent to the site, Wildewood, Clark Turner, and other parties entered into a Work Agreement to address completion of the work. The surety was not a party to the Work Agreement.
Read the court decisionRead the full story...Reprinted courtesy of
Joel P. Williams, White and Williams LLPMr. Williams may be contacted at
williamsj@whiteandwilliams.com
When Subcontractors Sue Only the Surety on Payment Bond and Tips for General Contractors
August 13, 2019 —
Ira M. Schulman & Emily D. Anderson - ConsensusDocsPayment bonds have been a staple of public construction projects since 1874, when the U.S. Congress first passed the Heard Act, which required that contractors obtain payment bonds for public projects to ensure that subcontractors and material suppliers have a way to recover their damages if an upstream contractor fails to pay for work performed and materials furnished on the project. The 1874 Heard Act has since been replaced by the 1935 Miller Act, and the concept has been expanded to construction projects funded by the states through state statutes known as “Little Miller Acts.” But the structure remains the same: On most public projects where the project’s cost exceeds $100,000, the prime contractor (the bond principal) is required to obtain a payment bond from a surety equal to the contract price to guarantee to subcontractors and material suppliers (the bond obligees) that the surety will pay for labor and materials under certain statutory or contractual conditions should the contractor fail to make payment.
A surety is jointly and severally liable with the contractor to the subcontractor, which means that the subcontractor may seek recovery against either the contractor or the surety or both, and the contractor and surety will be liable for the damages together. Put another way, in most states and in federal court, an unpaid subcontractor has the right to sue only the surety on the payment bond without joining the contractor because a contract of suretyship is a direct liability of the surety to the subcontractor.1 When the contractor fails to perform, the surety becomes directly responsible at once — it is unnecessary for the subcontractor to establish that the contractor failed to carry out its contract before the obligation of the surety becomes absolute.
Reprinted courtesy of
Ira M. Schulman, Pepper Hamilton LLP and
Emily D. Anderson, Pepper Hamilton LLP
Mr. Schulman may be contacted at schulmani@pepperlaw.com
Ms. Anderson may be contacted at andersone@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Renters Who Bought Cannot Sue for Construction Defects
October 08, 2013 —
CDJ STAFFA Wisconsin couple that leased then bought a home cannot sue the couple that built the home for construction defects. The court rejected the claims made by Niksa and Kelly Ivancevic that the sellers, Ronald and Debra Reagan, had breached contract or that the contract represented a mutual mistake.
The Ivancevics initially leased the home, with an agreement that said the house would be “delivered in clean condition and good repair, free of mold and toxic substances, suitable for habitation in compliance with all laws.” Before the purchase, no defects were found. After the purchase, the Ivancevics had problems with the air conditioning, leading to water leaks on the second floor.
The court found that the actual sales contract did not guarantee a defect-free residence. Therefore the Ivancevic’s claim of a mutual mistake, in which “both parties of a contact are unaware of the existence of a past or present fact material to their agreement” did not apply, since the presence of construction defects was not “material to their agreement.”
Read the court decisionRead the full story...Reprinted courtesy of
CGL Coverage for Liquidated Damages and the Contractual Liability Exclusion
October 09, 2023 —
Stu Richeson - The Dispute ResolverLiquidated delay damages are common in construction contracts and are generally imposed when a contractor fails to achieve substantial completion within the time required by the contract. While contracts like the AIA A201-2017 have provisions for extending the time to achieve substantial completion when delays are caused by circumstances beyond the contractor’s control, delays can result from factors other than improper management or planning and the like, for which the owner is not required to give the contractor additional time. Courts are split on whether there is ever coverage under a CGL policy for contractually agreed upon liquidated delay damages.
Liquidated delay damages are often excluded under the contractual liability exclusion of most CGL policies. The contractual liability exclusion excludes coverage for “liability for which the Insured is obligated to pay damages by reason of the assumption of liability in a contract or agreement.” Courts often find the contractual liability exclusion in a CGL policy precludes coverage for liquidated delay damages, because such damages are contractual in nature and are triggered by the failure to bring the contract to substantial completion by a fixed deadline, regardless of the cause of the delay. However, some courts will look to the cause of the delay and find that there is coverage under a CGL policy for liquidated delay damages that are the result of property damage caused by an accident or occurrence.
In Clark Const. Grp., Inc. v. Eagle Amalgamated Serv., Inc., 01-2478-DV, 2005 WL 2092998, at *1 (W.D. Tenn. Aug. 24, 2005) a general contractor entered a contract for the renovation of the convention center in Memphis. Part of the project included the demolition of a structure attached to the convention center. The demolition work was improperly performed by a subcontractor and resulted in damage to the convention center.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
The Jersey Shore gets Beach Prisms Designed to Reduce Erosion
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFThirty-five beach prisms manufactured by Smith-Midland Corporation have been installed along the Jersey shore in Ocean Gate, New Jersey. According to the Wall Street Journal, “The prisms protect homes, prevent erosion, and reduce impacts from natural disasters like Hurricane Sandy.” They “are made with a built-in parabolic curve that scatters waves away as spray instead of allowing them to crash up onto the vulnerable shoreline.”
Ocean Gate’s Mayor Paul J. Kennedy stated, "We've been losing beach year after year with the Nor'easters we get. So we came up with an idea that hopefully will work,” The Wall Street Journal reported.
Read the court decisionRead the full story...Reprinted courtesy of
Last Call: Tokyo Iconic Okura Hotel Meets the Wrecking Ball
August 26, 2015 —
Komaki Ito & Andreea Papuc – BloombergTokyo’s iconic nod to Japanese Modernism, the Hotel Okura, will bid farewell to its last guests next week and face the wrecking ball, despite petitions from around the world to save it.
The 1960s-era hotel, which has welcomed international dignitaries and inspired a throng of admirers eager for preservation, will close its doors Aug. 31 to make way for a gleaming new hotel rebuilt in time for the 2020 Olympics, at a cost of about 100 billion yen ($836 million).
“What’s odd about the Okura is that it’s a perfect embodiment of ‘60s Modernism, and it represents that very first wave of new development in the region,” Tyler Brule, editor in chief of Monocle magazine, who spearheaded a campaign that included a petition with almost 9,000 signatures, said in an e-mailed response to questions. “For this reason alone, it deserves to be preserved.”
Reprinted courtesy of
Komaki Ito, Bloomberg and
Andreea Papuc, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Repairs Commencing on Defect-Ridden House from Failed State Supreme Court Case
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFIn the Windmill Harbour area of Hilton Head Island, South Carolina, Danielle Smith is repairing her home after “spending almost $25,000 on unsuccessful legal battles and two years to secure a loan,” according to the Beaufort Gazette. The contractor who custom built the home was unlicensed, and “[t]he synthetic stucco used to build the house was faulty, causing water damage throughout that will cost $500,000 and six months to repair.”
Back in 2008, Smith’s case reached the state Supreme Court. The court ruled against her, reasoning “that the former owner, who had hired subcontractors to build the house, could not be held liable for the damage because he built it as a private home and had originally intended to never sell it.”
Read the court decisionRead the full story...Reprinted courtesy of