Yes, Indeedy. Competitive Bidding Not Required for School District Lease-Leasebacks
October 01, 2014 —
Garret Murai – California Construction Law BlogRemember when you discovered that the tooth fairy wasn’t real?
It was kind of a bummer on one hand learning that it wasn’t a fairy that magically appeared to swap your tooth for cold hard cash, but rather your mom or, visual horrors, dad.
At the same time, it was, to your nearly-halfway-to-a-decade-on-this-planet-wizened-six-year-old mind, confirmation of what you had a sneaking suspicion was the case in any event.
And, so it is with the next case.
Lease-Leasebacks
In California, most public school construction projects are built using the traditional design-bid-build project delivery method in which a design professional designs the project, the project is put out for competitive bid and the selected contractor builds the project.
But not all school construction projects are built this way.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at
gmurai@kmtg.com
Texas Supreme Court: Breach of Contract Not Required to Prevail on Statutory Bad Faith Claim
June 06, 2018 —
Bethany L. Barrese - Saxe Doernberger & Vita, P.C.In USAA Texas Lloyds Company v. Menchaca, the Supreme Court of Texas clarified long-standing confusion regarding whether damages for bad faith are recoverable in the absence of a breach of contract under Texas law. The Menchaca case takes an in-depth dive into decades’ worth of Texas precedent and concludes that, under certain circumstances, an insured can recover policy benefits as damages for bad faith without finding that the insurer was in breach of contract.
The story of this case begins with Hurricane Ike in September 2008. Homeowner Gail Menchaca contacted her homeowner’s insurance company, USAA Texas Llloyds Company (“USAA”) to report that the storm had damaged her home. USAA sent an adjuster to investigate the claim, and USAA determined that although the policy covered some of the damage, no benefits would be paid under the policy because the repair estimate did not exceed the policy deductible. Five months later, at Ms. Menchaca’s request, another USAA adjuster inspected the property and reached the same conclusion.
Read the court decisionRead the full story...Reprinted courtesy of
Bethany L. Barrese, Saxe Doernberger & Vita, P.C.Ms. Barrese may be contacted at
blb@sdvlaw.com
Georgia Supreme Court Rules Construction Defects Can Constitute an Occurrence in CGL Policies
April 05, 2011 —
Beverley BevenFlorez CDJ STAFFRecently, the Supreme Court of Georgia reversed the decision in American Empire Surplus Lines Insurance Company v Hathaway Development Company, Inc. stating that because Whisnant’s faulty workmanship caused damage to the surrounding properties, the construction defects constituted “occurrences” under the Commercial General Liability (CGL) policy. Unlike the South Carolina Supreme court ruling in the case of Crossman Communities v Harleysville Mutual, the Georgia Supreme Court stated that an accident can happen intentionally if the effect is not the intended result.
Interestingly, the only dissenting judge, J. Melton, disagreed with his colleagues on the basis that “although the term ‘accident’ is not specifically defined in the policy, it is axiomatic that an ‘accident’ cannot result from ‘intentional’ behavior.” It is clear that what constitutes an occurrence in CGL policies is still being hotly debated.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
How BIM Can Serve Building Owners
September 17, 2018 —
Aarni Heiskanen - AEC BusinessBuilding Information Models typically end their active life after the construction phase. An experimental project was initiated to find out whether and how they can serve owners throughout the life cycle of a building.
Gradia, the Jyväskylä Educational Consortium, provides education to students of all ages in central Finland. It has around 25,000 students, a staff of 1,100, and buildings with a total floor area of 150,000 square meters. Gradia and a team from Gravicon and XRM Finland carried out a government-supported KIRA-digi experimentation project in 2017 on the use of BIMs for building maintenance and repairs.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Don’t Get Caught Holding the Bag: Hold the State Liable When General Contractor Fails to Pay on a Public Project.
January 31, 2018 —
Sean Minahan – Construction Contract AdvisorAccording to a quick Google search the term
“holding the bag” comes from the mid eighteenth century and means be left with the onus of what was originally another’s responsibility. Nobody wants to be left holding the bag. But that is the situation our client (subcontractor) found themselves in when upon completion of a public project the general contractor went out of business before paying the remaining amount due and owing to our client.
Under Nebraska law, liens are not allowed against public projects. Instead the subcontractor is to make a claim on the payment and performance bond secured by the general contractor at the start of the project. In our case, the general contractor never secured a bond on which to make a claim; consequently, leaving our client holding the bag.
Read the court decisionRead the full story...Reprinted courtesy of
Sean Minaham, Lamson, Dugan and Murrary, LLPMr. Minahan may be contacted at
sminahan@ldmlaw.com
Digital Twins for a Safer Built Environment
November 24, 2019 —
Cristina Savian - AEC BusinessAs a native of Turin Italy, I was horrified at the Ponte Morandi bridge collapse last year. As a child and as an adult I have travelled over that bridge more times than I can imagine and have often pondered the what-if scenarios. What if it had happened when I or my loved ones were travelling on that bridge? As a chartered construction professional, I ask myself, what could have been done, what should have been done and what can we do to prevent this from happening in the future?
Having access to a digital twin with an integrated understanding of the way the bridge was designed, built and performed over the last 50 years and being able to run “what if” scenarios would have allowed us to have a much greater understanding of the structure and its limitations in its context. This is where I believe a digital twin of any built asset is a step in the right direction.
The digital twin has been proclaimed by many as a milestone innovation in the construction industry, with huge benefits to constructors and owners of assets through efficiencies in manufacturing and operation but also to attracting users of the spaces they replicate. However, digital replicas can take a broad range of forms depending on its purpose, use and application sparking debates among professionals on what they actually are and what represents a ‘true’ twin.
Read the court decisionRead the full story...Reprinted courtesy of
Cristina Savian, AEC Business
Revel Closing Shows Gambling Is No Sure Thing for Renewal
September 03, 2014 —
Christopher Palmeri – BloombergThe Revel Casino Hotel was envisioned as a playground for Wall Streeters who hated flying to Las Vegas. Instead, it’s become a money pit for the banks and money managers who spearheaded the New Jersey project, and the losses will keep coming even after closing today.
The Atlantic City resort, built at a cost of $2.4 billion, ceased operations after two bankruptcies and a 10-month search for a buyer. Barring a sale, the new owners may be Wells Fargo & Co. and JPMorgan Chase & Co., which provided $125 million in court-approved funding. Previous backers also included Capital Group Cos., the third-largest manager of U.S. mutual funds, and Morgan Stanley, the original investor.
The resort fell prey to poor timing, bad design and a misreading of the local market. The Revel saga shows what can go wrong when bankers stray from what they know, according to Charles Geisst, a professor of finance at Manhattan College in New York and author of the book “Wall Street: A History.”
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Palmeri, BloombergMr. Palmeri may be contacted at
cpalmeri1@bloomberg.net
Contractor’s Claim for Interest on Subcontractor’s Defective Work Claim Gains Mixed Results
April 27, 2020 —
John J. Gazzola, Associate, Pepper Hamilton LLP - ConsensusDocsThis case concerns calculation of a damages award to a general contractor, Skanska USA Building, Inc., on its claim for breach of contract against its masonry subcontractor, J.D. Long Masonry, Inc., arising from Long’s faulty construction of a masonry façade at a medical research facility in Baltimore. When the façade collapsed and Long failed to repair it, Skanska hired a replacement subcontractor, C.A. Lindman, to remediate Long’s defective work and filed suit against Long to recover the resulting damages. After the court granted Skanska’s motion for summary judgment as to liability, Skanska moved for summary judgment on the issue of damages, relying on the indemnification provision of the subcontract to seek compensatory damages, pre- and post-judgment interest, and litigation fees. In the subcontract, Long agreed to indemnify and hold Skanska harmless from all claims, losses, costs and expenses, including attorneys’ fees, arising before or after completion of Long’s work, caused by, arising out of, resulting from, or occurring in connection with Long’s performance of the work or breach of the subcontract.
The court first applied the terms of this provision to award Skanska compensatory damages, holding that Skanska was, as a matter of law, entitled to recover the amount of the Lindman subcontract and general conditions incurred to supervise remediation of Long’s work. The court, however, denied Skanska’s claim for pre-judgment interest on the entirety of these damages. Skanska asserted that it was entitled to pre-judgment interest on the full award, calculated from the date on which it first paid Lindman. The court disagreed, explaining that, under Maryland law, a claimant is entitled to an award of pre-judgment interest as of right only when the amount due is certain, definite and liquidated by a specific date prior to judgment. The court reasoned that, because much of the Lindman subcontract value was composed of later-executed change orders, an award of pre-judgment interest could not be uniformly calculated back to the date of Skanska’s first payment to Lindman. And moreover, because Skanska continued to withhold sums due to Lindman pending resolution of certain issues, awarding Skanska pre-judgment interest on amounts it had not yet paid would result in a “windfall” to Skanska because there was no “use of income” loss to be compensated.
Read the court decisionRead the full story...Reprinted courtesy of
John J. Gazzola, Pepper Hamilton LLPMr. Gazzola may be contacted at