Ivo G. Daniele – Newmeyer & Dillion LLP News AlertIt is paramount that a contractor diligently maintains its license prior to and during the performance of any contract work. Failure to do so could result in barring a contractor from receiving payment and/or disgorgement of profits received under the construction contract.
California Business and Professions Code section 7031 is part of the Contractors State License Law (Business & Prof. section 700 et seq.), and is both feared and loathed by all contractors performing work in the state of California. This draconian statute is known as the “Shield” and was enacted over 70 years ago for the singular purpose to bar all actions by contractors seeking compensation for unlicensed contract work – even precluding a contractor from enforcing his or her mechanic’s lien rights. However, a contractor could potentially avoid the harshness of B&P 7031 by establishing that he or she had substantially complied with the appropriate licensing requirements.
SUBSTANTIAL COMPLIANCE WITH LICENSE REQUIREMENTS PRIOR TO 2017 AMENDMENT
The substantial compliance exception is found in section B&P 7031(e), which authorizes the court to determine that there has been substantial compliance with licensure requirements, if the contractor has shown at an evidentiary hearing that he or she engaged in the unlicensed work had:
- Been duly licensed as a contractor in this state prior to the performance of the act or contract;
- Acted reasonably and in good faith to maintain the license;
- Did not know or reasonably should not have known that he or she was not licensed when he or she performed the work; and
- Acted promptly and in good faith to reinstate the license once it learned the license had lapsed.
Although not impossible, satisfying all four requirements of the exception was challenging for the contractor, specifically, requirement # (3) – the lack of knowledge that he or she was unlicensed during performance of work.
SUBSTANTIAL COMPLIANCE POST 2017
Fortunately, Governor Brown heard the collective cry for relief and signed Assembly Bill 1793 (“AB 1793”) into law. The new bill revises the criteria for the court to determine if a contractor is in substantial compliance with the licensing requirements by deleting requirement # (3) in its entirety and modestly amending requirement # (4) to require the contractor to act promptly and in good faith to remedy the failure to comply with the licensure requirements upon learning of the failure.
As a result, the substantial compliance exception under B&P 7031(e) reads as follows:
(e) The judicial doctrine of substantial compliance shall not apply under this section where the person who engaged in the business or acted in the capacity of a contractor has never been a duly licensed contractor in this state. However, notwithstanding subdivision (b) of Section 143, the court may determine that there has been substantial compliance with licensure requirements under this section if it is shown at an evidentiary hearing that the person who engaged in the business or acted in the capacity of a contractor
(1) had been duly licensed as a contractor in this state prior to the performance of the act or contract, (2) acted reasonably and in good faith to maintain proper licensure, and (3) acted promptly and in good faith to remedy the failure to comply with the licensure requirements upon learning of the failure.
This new legislation has tempered the burden of proof born by the contractor in establishing substantial compliance, although be it minor in its modification, the fact of the matter remains the same – be diligent in maintaining your license during all phases of contract work.
Ivo Daniele is a seasoned associate in the Walnut Creek office focusing his practice on commercial transactions and business and construction litigation. For questions regarding California Business and Professions Code section 7031, please feel free to contact Ivo Daniele at (925) 988-3222 or ivo.daniele@ndlf.com.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Bidders Shortlisted as Oroville Dam Work Schedule is Set
April 13, 2017 —
JT Long - Engineering News-RecordIn a race to fix the damaged Oroville Dam’s main spillway by November, the California Dept. of Water Resources, the operator of the country’s tallest dam, is going to bid with a 65%-complete design that breaks recovery efforts into three parts, with an ultimate goal of doubling the main spillway’s release capacity to 270,000 cu ft per second.
Read the court decisionRead the full story...Reprinted courtesy of
JT Long, ENRENR may be contacted at
ENR.com@bnpmedia.com
Supreme Court of Kentucky Holds Plaintiff Can Recover for Stigma Damages in Addition to Repair Costs Resulting From Property Damage
August 15, 2018 —
Gus Sara - The Subrogation StrategistIn Muncie v. Wiesemann, 2018 K.Y. LEXIS 257, the Supreme Court of Kentucky considered whether stigma damages[1] in a property casualty case are recoverable in addition to the costs incurred to remediate the actual damage. The court held that stigma damages are recoverable in addition to repair costs, but the total of the stigma damages and repair costs cannot exceed the diminution in the fair market value of the property. The court’s decision establishes that if the repair costs are insufficient to make the plaintiff whole, a recovery for stigma damages up to the amount of the diminution in the market value of the home is appropriate.
Appellants Cindy and Jim Muncie incurred significant property damage to their home as a result of an oil leak originating from a neighboring property owned by the Estate of Martha Magel. In 2011, Auto Owners Insurance Company (Auto Owners), the liability carrier for the Estate’s testatrix, Patricia Weisman, filed an impleader complaint in federal court to discharge its obligation to settle the third-party liability claims on behalf of Ms. Weisman. Auto Owners reached a settlement with the Muncies for $60,000 which represented the remediation costs for the actual damage to the property. The settlement release reserved the Muncies’ right to pursue a claim for stigma damages associated with the oil leak.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com
Appeals Court Explains Punitive Damages Awards For Extreme Reprehensibility Or Unusually Small, Hard-To-Detect Or Hard-To-Measure Compensatory Damages
November 10, 2016 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Nickerson v. Stonebridge Life Ins. Co. (No. B234271A, filed 11/3/16), (“Nickerson II”) a California appeals court outlined the requirements for complying with the single-digit multiplier annunciated as a Constitutional limitation on punitive damages by the United States Supreme Court in State Farm Mut. Automobile Ins. Co. v. Campbell (2003) 538 U.S. 408, for awards of punitive damages against insurers in cases of extreme reprehensibility or unusually small, hard-to-detect or hard-to-measure compensatory damages.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Haight Welcomes Elizabeth Lawley
September 03, 2015 —
Elizabeth W. Lawley – Haight Brown & Bonesteel LLPHaight Brown & Bonesteel LLP welcomes partner Elizabeth W. Lawley. Elizabeth joins Haight’s new Sacramento office in the Construction Law and General Liability Practice Groups. She has extensive experience representing construction companies, contractors, subcontractors, real estate developers and insurers. Among her clients are prestigious national home builders, window manufacturers, roofers, HVAC, tile and masonry contractors. Elizabeth provides exceptional legal services while navigating complex litigation handling and resolution and she adds another layer of top-tier skills to Haight’s existing practice.
Haight Brown & Bonesteel LLP
2485 Natomas Park Drive
Suite 450
Sacramento, CA 95833
www.hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Elizabeth W. Lawley, Haight Brown & Bonesteel LLPMs. Lawley may be contacted at
elawley@hbblaw.com
Margins May Shrink for Home Builders
November 06, 2013 —
CDJ STAFFHome builders are worried that the rising prices of new homes might not rise enough and be caught by the rising costs of building them, cutting into the profit margin. “If builders say the trajectory of margins is beginning to peak, then in a cyclical business, people tend to go from thinking the best to thinking the worst,” Stephen Kim, a Barclays analyst told the Wall Street Journal. As of the end of October, the U.S. Home Construction Index was 21% below its highest point in 2013, set back in May.
Margins are still over those of last year. Meritage Homes saw a gross margin of 22.8% in 2013’s third quarter, when the same quarter in 2012 had a gross margin of 18.6%. Steven Hilton, the firm’s Chairman and CEO, predicted little or no growth and a decline toward 20% or 21%. On the other hand, with margins at 20.6%, Ryland Homes sees itself at a normal point. Larry Nicholson, the President and CEO of Ryland, said “there’s not a lot of room for it to grow.”
Read the court decisionRead the full story...Reprinted courtesy of
Pennsylvania Considers Changes to Construction Code Review
November 06, 2013 —
CDJ STAFFPennsylvania may soon change how it adopts changes to its implementation of the Uniform Construction Code, but it’s not clear which method will be adopted, as the Pennsylvania House and Senate have competing bills. In the Senate bill (SB1023), the only change would be that any changes to the Uniform Building Code made by the International Code Council would automatically become part of the Pennsylvania building code, unless rejected by a two-thirds vote of the Pennsylvania UCC Review and Advisory Council. Under current Pennsylvania law, changes are adopted only with a two-thirds approval of the RAC.
The House bill (HB1209), separates the commercial code from the residential code. Under the House proposal, the RAC would reject changes to the commercial building code on a two-thirds vote, otherwise they would be adopted, but in the residential building code, changes would be rejected unless the RAC approved them by a two-thirds vote.
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Charting Your Contractual Rights With Respect To The Coronavirus
April 06, 2020 —
David Adelstein - Florida Construction Legal UpdatesAs more and more information is being learned, and more and more industries are being impacted, it is likely that the construction industry will follow suit. And, while impacts with the global supply chain may not yet be realized, impacts could begin with labor supply and, frankly, employers’ safety protocols dealing with the coronavirus. One suggestion that should be implemented is a detailed chart, similar to the below, where you are charting rights and obligations under your contracts dealing with force majeure, notice, and project suspensions. This is step one to make sure you are making prudent decisions, preserving rights, and making sure contractual obligations are being met. Be proactive, not reactive.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com