Make Your Business Great Again: Steven Cvitanovic Authors Construction Today Article
April 20, 2017 —
Steven M. Cvitanovic - Haight Brown & Bonesteel LLPThere is a lot of uncertainty regarding how President Trump’s immigration and trade policies will affect the construction industry. In his Construction Today article, Partner Steven Cvitanovic discusses how businesses can remain competitive and profitable during this period of uncertainty, including updating contract documents, recruiting and retaining employees, and increasing cybersecurity efforts.
“If you do not know when your contract documents were last updated, it’s probably been too long,” writes Cvitanovic. “Unlike wine, contract documents only get worse with age.” Cvitanovic advises teams to sit down together and review contracts to see if they still meet the firm’s needs.
Read the court decisionRead the full story...Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLPMr. Cvitanovic may be contacted at
scvitanovic@hbblaw.com
Housing in U.S. Cools as Rate Rise Hits Sales: Mortgages
April 28, 2014 —
John Gittelsohn and Prashant Gopal – BloombergAfter a roller-coaster decade of boom-bust-boom, the U.S. housing market is going downhill just when many economists thought annual sales would be heading up.
Sales of previously owned properties in March tumbled 7.5 percent from a year earlier to the slowest pace in 20 months, while purchases of new houses sank 14.5 percent from February, according to reports this week. Mortgage applications to buy homes plunged 19 percent from a year earlier, indicating slowing demand during what is typically the busiest season for deals.
The housing market’s underlying fragility is emerging as outside influences that fueled a two-year rebound are receding. Mortgage interest rates are rising from record lows as the central bank withdraws its stimulus, and investors, who had helped drive national prices up more than 20 percent as they went on a buying spree, are now retreating.
Mr. Gittelsohn may be contacted at johngitt@bloomberg.net; Mr. Gopal may be contacted at pgopal2@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn and Prashant Gopal, Bloomberg
Google’s Biggest Moonshot Is Its Search for a Carbon-Free Future
November 15, 2021 —
Mark Bergen - BloombergGoogle Bay View, the company’s newest campus, consists of three squat buildings nestled near the San Francisco Bay shoreline a few miles east of its headquarters in Mountain View, Calif. The first things visitors notice are the roofs.
They curve down gently from pinched peaks, like circus tents, sloping almost to the ground. Each roof is blanketed with overlapping solar panels that glisten with a brushed metal sheen on the edges. Google calls this design Dragonscale, and indeed it looks as if a mystical beast is curled up by the water in Silicon Valley.
Google envisions its latest campus as the embodiment of a grander ambition to run its operations entirely free of carbon. The company plans to open Bay View in January to “a limited number” of employees, depending on the pandemic. Beneath the buildings, thousands of concrete pillars plunged into the ground will serve as a sort of geothermal battery, storing heat to warm the building and water supply without natural gas. The roof panels were constructed with a unique textured glass to prevent glare and with canopies that emit a soft, glowing light into the spacious atria inside. “We call this the Cathedral of Work,” says Asim Tahir, who oversees energy decisions in Google’s real estate division. He stands by the southern entrance in a hard hat, mask, and safety vest.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Bergen, Bloomberg
Study May Come Too Late for Construction Defect Bill
February 14, 2013 —
CDJ STAFFColorado State Senator Mark Scheffel removed his bill, Senate Bill 13-052, from the calendar of the Senate Judiciary Committee in anticipation of a study which he feels would be pertinent to the discussion. The bill would stop communities from suing developers over noise and vibration issues associated with transit facilities, and would also provide for developers fixing construction defects before being sued. Senator Scheffel said that the intent of his bill was to spur development near transit facilities.
The study, commissioned by the Denver Regional Council of Governments, would focus on the effects of the state’s construction defects law on housing. It might not come soon enough for the senator’s bill. The Denver Business Journal reports that the study, which will take four months to complete, doesn’t yet have a contract. The Legislature must adjourn by May 8, so it is not possible for the study to be concluded before the end of this legislative session.
Read the court decisionRead the full story...Reprinted courtesy of
Serving Notice of Nonpayment Under Miller Act
January 20, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnder the federal Miller Act, if a claimant is NOT in privity with the prime contractor, it needs to serve a “notice of nonpayment” within 90 days of its final furnishing. In this manner, 40 U.S.C. 3133 (b)(2) states:
A person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made. The action must state with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. The notice shall be served–
(A) by any means that provides written, third-party verification of delivery to the contractor at any place the contractor maintains an office or conducts business or at the contractor’s residence; or
(B) in any manner in which the United States marshal of the district in which the public improvement is situated by law may serve summons.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Still Going, After All This Time: the Sacketts, EPA and the Clean Water Act
September 13, 2021 —
Anthony B. Cavender - Gravel2GavelOn August 16, 2021, the U.S. Court of Appeals for the Ninth Circuit affirmed the lower court’s ruling that the Idaho property of Michael and Chantell Sackett was a regulated wetlands under the then-controlling 1977 EPA rules defining “waters of the United States,” and that the Sacketts dredging and filling of their property was subject to regulation by the U.S. Army Corps of Engineers or EPA. EPA’s case, as it has been for many years, was based on 2008 EPA and Corps inspection reports and Justice Kennedy’s “significant nexus” test as the controlling opinion in the 2006 Supreme Court case, Rapanos v. United States. The Sacketts’ argument was that the text of the Clean Water Act, as interpreted by Justice Scalia and three other Justices, was controlling, but for several years, the Ninth Circuit has relied on Justice Kennedy’s opinion in these CWA controversies. The court’s opinion expressed considerable sympathy for the Sacketts as they negotiated the thicket of EPA’s regulatory processes, but it could not disregard circuit precedent. A few years ago, the Supreme Court ruled, in a unanimous decision, that EPA’s then extant administrative compliance orders were arbitrary and capricious. (See Sackett v. US, 566 US 120 (2015).) After that decision, the case was remanded to the federal district court, where it lingered for several more years.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Architect Named Grand Custom Home Winner for Triangular Design
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFRobert Gurney, architect, created a triangular shaped home design to deal with restricted space on a corner lot that has "stumped developers for years," according to Custom Home.
"Using the wedge-shaped lot’s height limit and property line setbacks to define a structure, Gurney designed a striking triangle-plan house that not only answers its owners’ program requirements, but also makes a handsome and respectful addition to the existing streetscape," according to Custom Home.
Gurney told Custom Home that the clients--two graphic designers--helped make it successful. “They’re design-oriented,” he said, “so they were pretty much on board with whatever we came up with. And, fortunately, they didn’t need a lot of space; they’re empty-nesters.”
Read the court decisionRead the full story...Reprinted courtesy of
Differing Site Conditions Produce Differing Challenges
February 18, 2019 —
Sarah E. Carson - Smith CurrieThe saying “The best laid plans of mice and men often go awry” can too often apply in the construction industry. A contractor may receive a description of site conditions that is ultimately found flawed or misleading. The costs associated with addressing these surprise conditions often fall on the contractor to pay. The following article details proactive steps to avoid costly obstacles that may cause a project’s success to go awry.
What are Differing Site Conditions?
There are generally two recognized types of differing site conditions. The first, often referred to as a “Type I Changed Condition,” exists when a specification in the conditions indicated in the contract documents varies from what is represented. The second category, generally referred to as a “Type II Changed Condition,” is a variance so unusual in its nature that it materially differs from conditions ordinarily encountered in performing the type of work called for in the geographic area where the project is located.
Read the court decisionRead the full story...Reprinted courtesy of