Request for Stay Denied in Dispute Over Coverage for Volcano Damage
August 10, 2020 —
Tred R. Eyerly - Insurance Law HawaiiAlthough there were concurrent state and federal proceedings regarding the insureds' claims for damage caused by Kilauea Volcano, the federal district court refused to dismiss or stay the federal action. Aqulina v Certain Underwriters at Lloyd's Syndicate #2003, 2020 U.S. District Ct. LEXIS 101832 (D. Haw. June 10, 2020).
Plaintiffs held homeowner's policies from Lloyd's that were brokered and underwritten by various defendants. Coverage from the May 2018 eruption of Kilauea Volcano was denied based upon an exclusion precluding coverage for lava-related damage.
Plaintiffs sued Lloyds and various brokers in federal court, alleging that defendants had engaged in a deceptive scheme to defraud plaintiffs and deprive them of meaningful coverage. Lawsuits were also filed in state court, with plaintiffs arguing their losses were covered by their policies and that defendants wrongfully relied solely on the lava exclusion to deny claims.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
South Carolina “Your Work” Exclusion, “Get To” Costs
July 30, 2014 —
Scott Patterson - CD CoverageIn Precision Walls, Inc. v. Liberty Mutual Fire Insurance Co., No. 2013-000787 (S.C. Ct. App. July 23, 2014), SYS was the general contractor for a project. SYS contracted with Precision for the supply and installation of exterior insulation board, to include the taping of all joints. After Precision completed its work, another subcontractor began construction of the brick veneer wall over the insulation board. During construction of the brick wall, some of the joint sealing tape installed by Precision began to come loose. To correct the problem, the existing portion of the brick veneer wall had to be torn down, all of the joint sealing tape removed and replaced, and the brick veneer wall rebuilt. SYS deducted the cost of tearing down and rebuilding the brick veneer wall from Precision’s contract. Precision sought reimbursement for this amount from its CGL policy issued by Liberty Mutual.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Patterson, CD Coverage
Update: Lawyers Can Be Bound to Confidentiality Provision in Settlement Agreement
January 13, 2020 —
Danielle Ward, Esq. - Balestreri Potocki & HolmesIn July 2019, the California Supreme Court ruled that an attorney’s signature under the often-used phrase “approved as to form and content” does not preclude a finding that the attorney could be bound to the terms of a settlement agreement. (Monster Energy Co. v. Schechter (2019) 7 Cal.5th 781.) This decision marks a reversal of the Fourth District Court of Appeal’s 2018 ruling that approval of a contract is not tantamount to an agreement to be bound by that contract.
The underlying action stemmed out of a wrongful death suit by Wendy Crossland and Richard Fournier, parents of the decedent, against Monster Energy Company. The parties negotiated a settlement, a critical of element of which was a confidentiality provision aimed at keeping the the settlement secret.
The confidentiality provision prohibited plaintiffs and their counsel of record from disclosing both the existence of the settlement, or the terms thereof, to any person, entity, or publication, including the legal website Lawyers & Settlements. The attorneys signed the agreement under the phrase “approved as to form and content.”
Shortly after the settlement agreement was executed, the Plaintiffs’ attorney Bruce Schechter disclosed his clients’ settlement with Monster in an interview with Lawyers & Settlements. Monster filed suit against Mr. Schechter for breach of contract, among other causes of action. Mr. Schechter challenged the lawsuit with a SLAPP motion, essentially arguing that the lawsuit was meritless and merely an attempt to thwart freedom of speech.
The trial court denied Mr. Schechter’s motion as to the breach of contract cause of action finding that the settlement clearly contemplated that the attorneys were subjected to the terms of the agreement, and Schechter’s claim that he was not a party because he merely approved as to form and content was “beyond reason.”
The Fourth District Court of Appeal reversed, concluding that Mr. Schechter was not a party to the agreement by virtue of his signature approving the form and content, and the Plaintiffs had no authority to bind their attorney to the terms of the agreement. The Court of Appeal found that by affixing his signature to the agreement Mr. Schechter was merely manifesting his “professional thumbs up” in line with legal industry’s customary understanding.
In its reversal, the California Supreme Court did not disturb the legal community’s understanding of the phrase “approved as to form and content.” Rather, the Court concluded that an attorney’s signature under that often-used phrase does not preclude as a matter of law that the attorney intended to be bound by the agreement. The entire agreement, including the substantive provisions, need to be examined to determine the attorney’s intent in affixing his/her signature to the agreement.
Turning to the Crossland/Fournier Monster settlement agreement, the Court was unpersuaded by Mr. Schechter’s argument that he was not bound to the agreement because counsel was not included in the definition of “party”. The Court stated that it’s the substance of the agreement that determines whether counsel is a party to the contract, as opposed to a party to the lawsuit.
The Court was persuaded, in part, by the important role that confidentiality plays in brokering settlements. It noted that public disclosure of private settlements would serve to “chill” parties’ ability to resolve matters short of trial, and there was little doubt that confidentiality was an important term of the Crossland/Fournier Monster settlement. In concluding that Monster had met its burden to defeat an anti-SLAPP motion, the Court pointed to the numerous references to counsel in the substantive provisions of the agreement which a trier of fact could conclude bound Mr. Schechter to the confidentiality terms.
Danielle Ward has concentrated her law practice on defending developer, general contractor, and subcontractor clients in a variety of construction matters. She has been an attorney with Balestreri Potocki & Holmes since 2010 and can be reached at dward@bph-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
NLRB Hits Unions with One-Two Punch the Week Before Labor Day
November 18, 2019 —
John Baker & Robert Pettigrew - White and Williams LLPThe National Labor Relations Board (the Board) continues to modify the way employers, unions and employees view and relate to each other in the workplace. In two decisions right before Labor Day, the Board strengthened employer rights in their workplaces, while at the same time making life for their union counterparts more difficult.
On August 23, 2019, the Board revisited the issue of whether an employer must grant access to the off-duty employees of an onsite contractor so they can engage in Section 7 activities on the employer’s property. In general, Section 7 activities consist of employees acting together to improve their pay and working conditions, which constitute fundamental rights under the National Labor Relations Act (the Act). In Bexar County Performing Arts Center Foundation d/b/a Tobin Center, the San Antonio-based performing arts center, the Tobin Center, owned the Center as well as grounds that abutted the famed San Antonio River Walk. The Tobin Center housed three resident companies, one of which was the Ballet San Antonio with whom it had a licensor-licensee agreement.
In addition to plays, movies and other productions, the Tobin Center hosted the San Antonio Symphony (the Symphony) to perform for 22 weeks of the year. The Ballet San Antonio also occasionally utilized the Symphony for live musical performances at its ballets. When, however, the Ballet San Antonio decided to use recorded music for a particular production, off-duty employees of the Symphony protested by leafletting the public on the Tobin Center property. The leaflets advised the public of this decision and urged that they “DEMAND LIVE MUSIC!” Their protests were not directed at the property owner, who denied them access to its property.
Reprinted courtesy of
John Baker, White and Williams LLP and
Robert Pettigrew, White and Williams LLP
Mr. Baker may be contacted at bakerj@whiteandwilliams.com
Mr. Pettigrew may be contacted at pettigrewr@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Berger: FIGG Is Slow To Hand Over All Bridge Collapse Data
November 12, 2019 —
Richard Korman - Engineering News-RecordThe Florida International University Tragedy
About half an hour before the almost-completed pedestrian bridge collapsed onto a busy Miami-area road last year, killing six people, Denney Pate, the bridge’s engineer-of-record, sent a text to Linda Figg, the chief executive of FIGG Bridge Engineers.
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Additional Elements a Plaintiff Must Plead and Prove to Enforce Restrictive Covenant
April 19, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida Statute s. 542.335 is a statute that deals with restrictive covenants in contracts that impose a restraint on trade. It is an important statute to determine invalid restraints on trade that unreasonably or unfairly prevent competition. Any invalid restraint on trade is unenforceable. Restrictive covenants–or covenants in agreements that restrict you or prevent you from doing something–may unsuspectingly be included in contracts or the impact of the restrictive covenant may not be appreciated at the onset.
A party seeking to enforce a restrictive covenant in a contract has the additional burden of PROVING the validity and reasonableness of the restrictive covenant:
Under section 542.335, three requirements must be satisfied for a restrictive covenant to be enforceable: (1) the restrictive covenant must be “set forth in a writing signed by the person against whom enforcement is sought”; (2) the party seeking to enforce the restrictive covenant “shall plead and prove the existence of one or more legitimate business interests justifying the restrictive covenant”; and (3) the party seeking to enforce the restrictive covenant “shall plead and prove that the contractually specified restraint is reasonably necessary to protect the legitimate business interest or interests justifying the restriction.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
SB800 Not the Only Remedy for Construction Defects
October 01, 2013 —
CDJ STAFF“We anticipate an increase in residential construction defect litigation in response to this ruling,” David Frenznic, a construction defect lawyer at Wilke, Fleury, Hoffelt, Gould & Birney LLP told the Central Valley Business Times. Mr. Frenznic was responding to an August ruling by the California Court of Appeals that found that SB800 does not create the only remedy for homeowners with construction defects.
“Homeowners who suffer actual damage as a result of construction defects have a choice of remedies,” said Mr. Frenznick. SB800 established a shorter statute of limitations for construction defect claims, however, “the ruling makes clear that common law claims are still governed by the longer statues of limitations.”
Read the court decisionRead the full story...Reprinted courtesy of
Increasing Use of Construction Job Cameras
January 27, 2014 —
Beverley BevenFlorez-CDJ STAFFJob site cameras are increasingly used on construction sites, for various reasons, reports Tom Sawyer of Engineering News-Record. Mark Penny, senior vice president of the Dallas Region Manhattan Construction Inc., told Sawyer that he uses the camera primarily for marketing purposes: “We have a lot of high-profile jobs that people want to see. They are a great opportunity for us and the client to showcase the construction, which makes the job of selling what we do a lot easier.”
Warren Andres, senior vice president at Andres Construction uses cameras for safety monitoring. Andres told Sawyer that “he has three monitors on his desk. One shows live feeds from all his cameras. If he sees unsafe work, he sends a photo to the superintendent and demands action. Similarly, he says he can spot slow work crews and do enough quality control to send the message that management is watching.”
Vendors commented to Sawyer that “the growing use [of cameras] include the rise of building information modeling and its increased need for accountability; as well as companies chasing work beyond usual areas of operations and needing to extend supervision while holding down travel of staffs trimmed by the recession.”