Payment Bond Surety Entitled to Award of Attorneys’ Fees Although Defended by Principal
February 01, 2023 —
Garret Murai - California Construction Law BlogFor contractors involved in California public works projects the scenario is not uncommon: The general contractor awarded the public works project is required to obtain a payment bond for the benefit of subcontractors and suppliers and the payment bond surety issuing the payment bond requires the general contractor to defend and indemnify the surety from and against any claims against the payment bond.
In
Cell-Crete Corporation v. Federal Insurance Company, 82 Cal.App.5th 1090 (2022), the 4th District Court of Appeal examined whether a payment bond surety, who prevails in a claim against the payment bond, is entitled to statutory attorneys’ fees when the party actually incurring the attorneys’ fees was the general contractor, pursuant to its defense and indemnity obligations, as opposed to the surety itself.
The Cell-Crete Case
General contractor Granite Construction Company was awarded a public works contract issued by the City of Thermal known as the Airport Boulevard at Grapefruit Boulevard and Union Pacific Railroad Grade Separation Project. We’ll just call it the “Project.” Subcontractor Cell-Crete Corporation entered into a subcontract with Granite for lightweight concrete and related work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
When Employer’s Liability Coverage May Be Limited in New York
June 28, 2021 —
Robert S. Nobel & Craig Rokuson - Traub LiebermanNew York recognizes that coverage under Workers’ Compensation (“WC”) and Employer’s Liability (“EL”) policies is generally unlimited. See Tully Const. Co. v. Illinois Nat. Ins. Co., 131 A.D.3d 598 (2d Dept. 2015); Oneida Ltd. v. Utica Mut. Ins. Co., 263 A.D.2d 825, 694 N.Y.S.2d 221 (3d Dept. 1999). However, there is case holding that EL coverage may be limited in certain instances, such as when the primary EL carrier is listed as scheduled underlying insurance on an excess policy.
In Liberty Mut. Ins. Co. v. Ins. Co. of State of Pennsylvania, 43 A.D.3d 666, 841 N.Y.S.2d 288 (1st Dept. 2007), an employee of General Industrial Service Corporation (“General”), a subcontractor on a construction project, sought to recover under New York’s Labor Law against the project’s owner and construction manager. Those defendants, in turn, brought a third-party action for indemnification against General. The employee’s personal injury claim was ultimately settled for $2.5 million. After the settlement, the excess insurer, Liberty, filed suit against the primary employer’s liability insurers, The Insurance Company of the State of Pennsylvania and American International Group of Companies (collectively, “AIG”), which had refused to participate in the defense or settlement of the underlying personal injury litigation. Although the issue of whether the plaintiff in the underling action had sustained a “grave injury” (necessary to support the common law indemnity claim against General and trigger coverage under the Employer’s Lability policy) had not yet been determined, the court held that “[i]n the event the existence of a grave injury is proven, AIG’s liability will be limited to $1 million.”
Reprinted courtesy of
Robert S. Nobel, Traub Lieberman and
Craig Rokuson, Traub Lieberman
Mr. Nobel may be contacted at rnobel@tlsslaw.com
Mr. Rokuson may be contacted at crokuson@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Real Property Alert: Recording Notice of Default as Trustee Before Being Formally Made the Trustee Does Not Make Foreclosure Sale Void
February 18, 2015 —
Krsto Mijanovic and Annette F. Mijanovic – Haight Brown & Bonesteel LLPIn Ram, et al. v. OneWest Bank, FSB, et al. (filed 2/6/15, No. A139055), the California Court of Appeal held that a nonjudicial foreclosure sale is not void merely because the notice of default was recorded by an entity who had not yet been substituted as trustee. The court also held that because the sale was voidable, rather than void, the plaintiffs were required to allege an ability and willingness to tender their debt in addition to alleging that they were prejudiced by the irregularity in the foreclosure process.
Plaintiffs were borrowers who purchased a home subject to a deed of trust. After they defaulted on their loan, nonjudicial foreclosure proceedings were initiated, and the beneficiary of the deed of trust, OneWest Bank, FSB ("OneWest"), purchased the property at the foreclosure sale. Plaintiffs sued OneWest and other entities for wrongful foreclosure, alleging that the sale was void because the entity identified as the trustee on the notice of default, Aztec Foreclosure Corporation ("Aztec"), had not been formally substituted as trustee until after the notice of default was recorded. The trial court sustained OneWest's demurrer and plaintiff appealed.
Reprinted courtesy of
Krsto Mijanovic, Haight Brown & Bonesteel LLP and
Annette F. Mijanovic, Haight Brown & Bonesteel LLP
Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com
Ms. Mijanovic may be contacted at amijanovic@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Round-Up (01/18/23) – Construction Inventory, 3D Printing, and Metaverse Replicas
February 06, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up dives into projections on construction inventory in the housing market, the first 3D-printed house, a replica of South Korea’s Seoul in the Metaverse, and more.
- Shifts that occurred last year and at the peak of pandemic have transformed the real estate industry, with 2023 emerging as something of a barometer in the manifestations of those changes. (Tony Cantu, Mortgage Professional America (MPA))
- Total new construction of homes across the country is expected to drop by 200,000 dwellings per year until 2026 as skill shortages and supply issues continue to bite. (Sowaibah Hanifie, 7 News)
- Almost all economists and contractors expect some sort of an economic slowdown this year. (Sebastian Obando, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
A Quick Virginia Mechanic’s Lien Timing Refresher
February 27, 2023 —
Christopher G. Hill - Construction Law MusingsAs those who read Construction Law Musings on a regular basis know,
mechanic’s liens are a big part of my construction law practice. These
tricky and strictly enforced statutory collection tools are very powerful when correctly recorded and utterly useless if they aren’t recorded in a timely fashion and with the correct information contained within them. Couple that fact with recent
changes to the mechanic’s lien form in 2019, and I feel the need to give a quick refresher.
If you’ve kept up with Musings, you know about the two big numbers for Virginia mechanic’s lien timing, 90 and 150. These should be kept in mind for every general contractor, subcontractor, or supplier on any construction project in Virginia.
Virginia Code Section 43-4 sets out the reasons to keep these numbers in mind. The code section sets out why you need to know these numbers.
The 90 refers to the deadline for recording a lien. This number affects the right to a lien in Virginia. In order to preserve lien rights, a construction contractor must record the lien within ninety days of the last day of the last month in which the last work was performed or no later than ninety days from the date of completion of the project or other termination of work. The short version is that most general contractors on commercial projects have 90 days from the last work in which to record their lien and most subcontractors have 90 days from the last day of the last month of work. However, the best practice is to simply calculate the 90 days from the last work performed or material supplied to avoid issues and arguments between attorneys regarding timing.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Trump Tower Is Now One of NYC’s Least-Desirable Luxury Buildings
July 08, 2019 —
Shahien Nasiripour - BloombergTrump Tower, once the crown jewel in Donald Trump’s property empire, now ranks as one of the least desirable luxury properties in Manhattan.
The 36-year-old building has been turned into a fortress since Trump won the presidency, ringed with concrete barriers and the two main entrances partially blocked off. It hasn’t been substantially updated in years. And Trump’s name has been a huge turnoff in liberal New York City.
For anyone who owns a unit in the tower, the past two years have been brutal. Most condo sales have led to a loss after adjusting for inflation, property records show. Several sold at more than a 20% loss. By contrast, across Manhattan, just 0.23% of homes over the past two years sold at a loss, according to real-estate data provider PropertyShark, although the firm doesn’t adjust for inflation.
Read the court decisionRead the full story...Reprinted courtesy of
Shahien Nasiripour, Bloomberg
Colorado’s Workers’ Compensation Act and the Construction Industry
June 20, 2022 —
Jordan Kaplan - Colorado Construction LitigationIn general, issues relating to employment law occur in all industries. However, some issues are more likely to be raised in certain employment contexts. For example, office work environments tend to give rise to harassment and discrimination claims while wage and hour disputes and workplace safety claims are common in the oil and gas industry. In the construction industry, employers must be especially cognizant of discrimination and harassment claims, employee misclassification claims, workplace safety issues, and wage and hour claims. In the context of workers’ compensation claims, construction projects often create unusual situations due to the contractual relationships between the parties.
Even relatively simple construction of a single-family residence involves several levels of contracting, including between the owner and general contractor, between the owner or general contractor and design team, between the general contractor and subcontractors, and between the prime subcontractors and lower tiered sub-subcontractors. In most circumstances, this would not be an issue. However, when an injured worker makes a workers’ compensation claim, the contractual relationships among the various entities involved in a project can have a significant impact on which party or parties could be liable for the injury.
Read the court decisionRead the full story...Reprinted courtesy of
Jordan Kaplan, Higgins, Hopkins, McLain & Roswell, LLCMr. Kaplan may be contacted at
kaplan@hhmrlaw.com
Court Reminds Insurer that the Mere Possibility Of Coverage at the Time of Tender Triggers a Duty to Defend in a Defect Action
October 04, 2021 —
Jatin Patel - Newmeyer DillionIt has long been the law in California that an insurer’s duty to defend is broader than the duty to indemnify and that the mere possibility of coverage triggers a duty to defend. Nevertheless, insurers still periodically ignore this clear principle and attempt to narrow the scope of the duty to defend. Recently, a Federal District Court issued a reminder to a wayward insurer.
In Pacific Bay Masonry, Inc., v. Navigators Specialty Insurance Company, (N.D. Cal., Sept. 16, 2021, No. C 20-07376 WHA, 2021 WL 4221747 (“Pacific”)), the Court was asked to assess whether a tender of defense by a concrete masonry subcontractor to its insurer for a construction defect action required a defense. Pacific Bay Masonry, Inc. (“PBM”) installed concrete masonry units (also known as “CMUs”) at a new retail shopping center in Oakland, California. The subsequent owner of the retail center filed suit against the general contractor for alleged construction defects, including “efflorescence of roof deck at CMU wall” and “improper waterproofing and flashing of the CMU block wall." The general contractor filed a cross-complaint against PBM.
PBM tendered the defense of the case to Navigators Specialty Insurance Company (“Navigators”) along with copies of a preliminary defect list, a description of defects, interrogatory responses and an expert witness damage analysis. Navigators denied coverage and a duty to defend citing to the work product exclusion of the policy. PBM asked Navigators to reconsider. Navigators held firm on its denial. Two years later, PBM filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Jatin Patel, Newmeyer DillionMr. Patel may be contacted at
jatin.patel@ndlf.com