Apartment Building Damaged by Cable Installer’s Cherry Picker
November 20, 2013 —
CDJ STAFFThe owners of Oceana Apartments are suing Shentel Cable Co. and their subcontractors, CCI Systems, Inc. and Big Dog Communications, over the damage caused when a cherry picker rolled downhill and smacked into the building.
Kenneth Benn, an employee of Big Dog Communications, was installing utility wire when the cherry picker started moving. The suit alleges that Mr. Benn either failed to properly apply the brakes or immobilize the vehicle before staring work. Mr. Benn is also named as a defendant in the suit.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Ursinus is Cleared!”
March 11, 2024 —
Daniel Lund III - LexologyUrsinus University in Pennsylvania – a “private, nonprofit liberal arts college” – funded a construction project for a new building utilizing monies loaned by the Montgomery County Health and Higher Education Authority, a public economic development authority “formed by the Board of County Commissioners… authorized to issue bonds relative to projects for eligible educational institution such as Ursinus.”
Loans up to the amount of $23,000,000 became available to the University, and construction proceeded using the loans as construction funds. At issue: whether a project was to be considered publicly funded project such that prevailing wage rates were required to be paid. IBEW filed a related grievance with the Pennsylvania Department of Labor and Industry’s Bureau of Labor Law Compliance, which was refused by the Bureau, on the basis that because work was “financed completely by loans from the Authority, which Ursinus was required to repay in their entirety, the Project was ultimately funded through private sources and exempt from coverage under the [Pennsylvania Prevailing Wage Act].” A grievance to the Prevailing Wage Appeals Board ensued, and the Board took a different position.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Keeping Detailed Records: The Best Defense to Constructive Eviction
October 24, 2023 —
Ben T. Welch & Ken Brown - Snell & WilmerInevitably, commercial property owners and managers will be faced with a claim by a tenant of constructive eviction. This article is intended to describe what constructive eviction is and to suggest what owners and managers can do to prepare for, and ward off, such claims.
Constructive eviction occurs where a tenant’s “right of possession and enjoyment” of the leasehold is disrupted by the landlord in a manner that renders the premises “unsuitable for the purposes intended.”i Put another way, it is interference that is so “substantial nature and so injurious as to deprive the tenant of the beneficial enjoyment of a part or the whole of the demised premises.”ii Although easy to describe in theory, constructive eviction can be devilishly difficult to determine in the real world. In litigation, determining when interference crosses over the line to constructive eviction is intensely fact-sensitive and resists sweeping generalizations.iii
For instance, Utah courts have held that tenants have been constructively evicted when they have been subjected to continual harassment or insults by the landlord or the landlord’s agent,iv prevented or impaired in their access to the leased premises during operating hours,v or when a landlord fails to provide an operable elevator (or other essential commercial amenities) necessary for a tenant’s business operations.vi By contrast, claims of “discomfort” or “inconvenience” have been rejected as a basis for constructive eviction.vii The same goes for claims that a landlord wrongfully served a three-day notice to pay or quit.viii
Generally, constructive eviction is an affirmative defense made in response to a landlord’s lawsuit for nonpayment of rent.ix It is not, as is commonly supposed, a basis for a tenant’s premature abandonment of the premises. In other words, the defense is raised after the tenant has vacated as a result of being effectively “evicted.”x Further, the defense requires the tenant to actually abandon the premises and do so within a “reasonable time” after the alleged interference.xi A tenant cannot stay in possession and simply refuse to pay rent on the basis of constructive eviction.xii
The key consideration in preparing for, and responding to, a claim of constructive eviction is keeping good records. A tenant claiming constructive evicting likely must prove that the issue was raised in a timely manner and, despite multiple entreaties, was never resolved.xiii As such, it is critical that landlords acknowledge tenant complaints as well as document in writing their efforts to ameliorate those complaints. While a landlord does not carry the burden of proof for constructive eviction, detailed documentation can thwart a tenant’s claim that a landlord has been inattentive or unwilling to address the tenant’s concerns.
Detailed records are also useful in disputes where a tenant claims substantial interference. “The whole point of constructive eviction is that the landlord basically drove the tenant out through the landlord’s action or inaction.”xiv As such, a landlord that is unable to document the steps taken in response to complaints will be grossly disadvantaged whereas the tenant, which had control and knowledge of the premises, will have a much easier time describing how the alleged interference deprived them of enjoying the premises.
Even with meticulous records, however, owners and managers may still face claims of construction eviction. In such instances, counsel should be retained to properly advise on compiling, preserving, and employing the evidence necessary to refute the tenant’s claims.
i Gray v. Oxford Worldwide Grp., Inc., 139 P.3d 267, 269 (Utah Ct. App. 2006).
ii Gray, 139 P.3d at 270 (citing Neslen, 254 P.2d at 850) (internal formatting omitted).
iii See Gray, 139 P.3d at 269–70 (citing Thirteenth & Washington Sts. Corp. v. Neslen, 254 P.2d 847, 850 (Utah 1953)); Brugger v. Fonoti, 645 P.2d 647, 648 (Utah 1982).
iv See Gray, 139 P.3d at 270–71.
v Thirteenth & Washington Sts. Corp. v. Neslen, 254 P.2d 847 (Utah 1953).
vi See Richard Barton Enterprises, Inc. v. Tsern, 928 P.2d 368, 375, 378 (Utah 1996) (citing Union City Union Suit Co. v. Miller, 162 A.D.2d 101, 556 N.Y.S.2d 864 (1990)).
vii See Myrah v. Campbell, 163 P.3d 679, 682–84 (Utah Ct. App. 2007).
viii Barton v. MTB Enterprises, 889 P.2d 476, 477 (Utah Ct. App. 1995); see also Brugger, 645 P.2d at 648 (stating that the tenant’s complaints revolved around standard problems commonly associated with building maintenance and did not rise to the level of substantial interference); viv Reid v. Mutual of Omaha Ins. Co., 776 P.2d 896, 898–900 (Utah 1989) (upholding trial court’s findings of fact concerning insufficiency of disruption so as to justify claim for constructive eviction).
ix See Kenyon v. Regan, 826 P.2d 140, 142 (Utah Ct. App. 1992).
x See Kenyon, 826 P.2d at 142.
xi See Kenyon, 826 P.2d at 142; see also Barton v. MTB Enterprises, Inc., 889 P.2d 476, 477 (Utah Ct. App. 1995); Brugger, 645 P.2d at 648.
xii See Kenyon, 826 P.2d at 142 (citing Fernandez v. Purdue, 518 P.2d 684, 686 (Utah 1974)).
xiii See Brugger, 645 P.2d at 648 (noting that while the tenant had raised legitimate issues concerning state of the premises, the landorld had taken steps to remedy the problems within a reasonable time) (citing 49 Am.Jur.2d, Landlord and Tenant, § 617).
xiv Barton, 889 P.2d at 477.
Reprinted courtesy of
Ben T. Welch, Snell & Wilmer and
Ken Brown, Snell & Wilmer
Mr. Welch may be contacted at bwelch@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
South Carolina Couple Must Arbitrate Construction Defect Claim
June 28, 2013 —
CDJ STAFFThe South Carolina Court of Appeals has rejected a claim by Sun City property owners that they were not bound by the arbitration clause in their purchase agreement. Roger and Mary Jo Carlson brought the claim against Del Webb Communities and Pulte Homes. About 140 homeowners are alleging problems in the community. According to the court, the Carlsons will have to go through arbitration with the companies over the alleged stucco defects to their home.
Read the court decisionRead the full story...Reprinted courtesy of
New Executive Orders Expedite the Need for Contractors to Go Green
August 22, 2022 —
Vince Calio - Construction ExecutiveThe importance of going green just became even more crucial for small construction companies, as President Joe Biden signed three executive orders on June 6, 2022, aimed at boosting clean energy construction projects and the use of domestically manufactured clean energy technology.
Specifically, the orders require the U.S. Department of Energy to deploy the use of the Defense Production Act of 1950 to expand American manufacturing of solar panel parts, environmentally friendly building insulation, heat pumps, equipment for making clean power-generating fuels and critical power grid infrastructure. Federal construction contracts will also require local contractors to use eco-friendly materials.
According to an announcement from the White House, the order will encourage the use of project labor agreements that offer wages “above and beyond the prevailing rate and include local hire provisions.” The order will also encourage clean construction projects in low-income areas burdened by legacy pollution.
Reprinted courtesy of
Vince Calio, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
HHMR Celebrates 20 Years of Service!
October 18, 2021 —
David M. McLain – Colorado Construction LitigationI remember it (almost) like it was yesterday. It was September of 2001, and I was a third-year associate at Long & Jaudon, practicing with the construction litigation group. After a long weekend away, I received word that the firm had just announced that it would cease providing legal services. Long & Jaudon, which formed in 1967, had been a stalwart of Colorado’s defense bar, counting among its number some of the finest and most well-respected defense attorneys in the state. To learn that the firm would be shutting its doors was devastating. I would be out of a job.
Soon after L&J’s announcement, Dave Higgins, one of that firm’s senior partners, inquired as to whether I would be interested in starting a new firm focused on supporting Colorado’s construction industry and its insurers. Instead of riding into the sunset of retirement, Dave wanted to leave a legacy. That legacy is Higgins, Hopkins, McLain & Roswell. Shortly after the sprout of the idea, I spent an afternoon at a picnic table in Cheesman Park with Dave Higgins, Steve Hopkins, and Sheri Roswell, sketching out an idea for a new law firm. Twenty years later, HHMR is still here, still serving Colorado’s construction industry and its insurers, and still embodying the principles of service and stewardship upon which the firm was founded.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
One More Mechanic’s Lien Number- the Number 30
March 06, 2023 —
Christopher G. Hill - Construction Law MusingsI’ve spoken here often about the numbers
90 and 150 as they relate to
Virginia mechanic’s liens. These numbers are important for all mechanic’s liens in Virginia, whether commercial or residential (meaning liens for 1 and 2-family homes). There is another number, 30, that is important for those construction contractors that perform work on single and two-family homes. Where a mechanic’s lien agent is named on the building permit (or possibly just named if not stated on the permit), and
among other requirements,
Va. Code 43-4.01 requires that, in order to have lien rights at the project, the contractor must provide notice to the mechanic’s lien agent within 30 days of beginning work that it is performing work and shall seek payment for the work.
Further, the mechanic’s lien agent notice must contain the following:
(i) the name, mailing address, and telephone number of the person sending such notice, (ii) the person’s license or certificate number issued by the Board for Contractors pursuant to Chapter 11 (§ 54.1-1100 et seq.) of Title 54.1, if any, and the date such license or certificate was issued and the date such license or certificate expires, (iii) the building permit number on the building permit, (iv) a description of the property as shown on the building permit, and (v) a statement that the person filing such notice seeks payment for labor performed or material furnished.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at