Picketing Threats
July 09, 2019 —
Jerry Morales - Snell & Wilmer Under ConstructionLetters from unions to owners, general contractors and other contractors informing them of the union’s dispute with one or more of the subcontractors, working at a common construction project site (or common situs), and of the union’s plans to engage in “public informational campaigns” at the site, in furtherance of the dispute, may constitute unlawful threats of secondary boycott.
Unions often send letters to various employers that share a common construction project site, informing them that the union has a dispute with one or more of the subcontractors working or scheduled to work at the same site. In labor law, the employers that do not have a dispute with the union are referred to as “neutral employers,” in contrast with the employers with which the union has the dispute, referred to as “primary employers.”
In the letters, the unions typically describe the reason for the labor dispute (e.g., alleged failure to pay “area standards”), request that the neutrals use their “managerial discretion” not to allow the primary employers to perform work at the project site until the dispute is resolved, and inform that the union will engage in public information campaigns against the primary employer at the common situs. The “public information campaign” is described in the union’s letter as including banner displays, distribution of handbills, picketing and other demonstration activity.
Read the court decisionRead the full story...Reprinted courtesy of
Jerry Morales, Snell & WilmerMr. Morales may be contacted at
jmorales@swlaw.com
Brief Overview of Rights of Unlicensed Contractors in California
September 10, 2014 —
William M. Kaufman – Construction Lawyers BlogUnder California Contractor’s State License Law enumerated in Business and Professions Code Sections 7000 to 7191, a contractor may not “bring or maintain” any action for compensation for performing any act or contract for which a license is required unless the contractor was duly licensed “at all times” during performance. Bus & Prof Code Section 7031(a).
What does this mean and who does it include?
This is a question that often has to be answered on a case by case basis. Basically, California does not want unlicensed contractors to be able to get paid for work that should be performed by a licensed contractor. The law has set forth some general parameters. General contractors, subcontractors, and master developers must be licensed. However, suppliers, manufacturers, laborers and equipment lessors are exempt and do not need a contractor’s license. Essentially, those parties that merely furnish material or supplies without fabricating them into, or consuming them in the performance of work, do not need to be licensed. Bus & Prof Code Section 7052.
There are sever fines and penalties for those who improperly perform construction work without a license. A contract between any contractor and an unlicensed subcontractor is a misdemeanor. Lack of a license bars all actions in law or in equity for collection of compensation for the performance of work requiring a license. There are very few exceptions to this rule. A “savvy” unlicensed contractor cannot simply avoid these requirements by “subbing” out all the work to licensed contractors. Any person who uses the services of an unlicensed contractor may file a court action or cross-complaint to recover all payments made to the unlicensed contractor. In addition, a person who uses the services of an unlicensed contractor is a victim of a crime and eligible for restitution of economic losses regardless of whether that person had knowledge that the contractor was unlicensed. Bus. & Prof Code Sections 7028, 7028.16. It goes without saying that performing work without a license on projects is a bad idea.
Reprinted courtesy of
William M. Kaufman, Lockhart Park LP
Mr. Kaufman may be contacted at wkaufman@lockhartpark.com, and you may visit the firm's website at www.lockhartpark.com
Read the court decisionRead the full story...Reprinted courtesy of
When Is Mandatory Arbitration Not Mandatory?
August 19, 2015 —
Christopher G. Hill – Construction Law MusingsI have discussed my views on mandatory mediation in construction contracts at other places here at Musings and also discussed how the contract is king here in Virginia. A recent Charlottesville, Virginia Circuit Court case combined these two concepts to allow a subcontractor to proceed straight to litigation despite various ADR provisions in the contract between it and the general contractor.
In ProBuild v. DPR & Continental Casualty, the Court looked at a series of ADR steps that were to be followed in the contract between the parties in order to allow DPR, the general contractor to require arbitration as opposed to litigation. The Court considered the surety’s motion to stay the litigation against it pending arbitration between ProBuild and DPR.
In ProBuild, the Court looked at a contractual provision that provided certain steps to be followed in the event of a dispute, starting with a notice of dispute, followed by negotiation, followed by mediation should the disputing party request it, and in the event that mediation was tried and failed, the disputing party or general contractor could require arbitration. The Court determined that ProBuild, the subcontractor, was the disputing party under the contract, had pursued unsuccessful formal negotiations and that neither ProBuild nor DPR requested mediation. The Court then held that because unsuccessful mediation was a prerequisite to required arbitration and because mediation was never pursued, the mandatory arbitration clause did not apply.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Considerations in Obtaining a Mechanic’s Lien in Maryland (Don’t try this at home)
February 23, 2016 —
Christopher G. Hill – Construction Law MusingsFor this week’s Guest Post Friday at Construction Law Musings I welcome Matthew Evans. Matt is the owner of
Law Offices of Matthew S. Evans, III, LLC located in Annapolis, Maryland. He has practiced construction, real estate and land use law in Maryland and D.C. for thirteen years. Prior to opening his own firm in May 2011, Mr. Evans was a partner at a mid-sized firm in Anne Arundel County, Maryland. Mr. Evans lives in Historic Annapolis (only three short blocks from his office) with his wife Margaret, and three children, Matthew (5), Bo (4) and Peyton (2).
Some of the most common calls I get are from irate contractor or subcontractor clients who have not been paid demanding that I “lien the property”. Many times after calming the client down, I determine, to their dismay, that they are not entitled to a mechanic’s lien. In Maryland, the mechanic’s lien law is driven by statute, which contains specific requirements which must be met before the client is entitled to a lien.
The first question is whether the contractor or subcontractor is entitled to a lien for the work performed. Under Maryland law, “every building erected and every building repaired, rebuilt, or improved to the extent of 15 percent of its value is subject to establishment of a lien…for the payment of all debts.” It’s easy when dealing with new construction. No matter how small your portion of the work, the property is subject to the establishment of a lien. It is more difficult to determine entitlement when there is either a total or partial renovation or other work. The question becomes how do you determine the value of the building, and whether it has been improved “to the extent of 15 percent of its value.” Believe me, I have seen creative and some not so creative methods of calculation used by counsel to prove that certain work does or does not meet the requirement.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Legislative Update: Bid Protest Law Changes to Benefit Contractors
November 24, 2019 —
Brett M. Hill - Ahlers Cressman & Sleight PLLCA new statute became effective July 28, 2019 that benefits contractors who have bid protests in Washington. A bid protest is the only way for disappointed bidders to challenge irregularities in the public bidding process on public works projects. Bid protests ensure the integrity of the public bidding system and are the contractor’s only remedy if its bid is improperly rejected or the winning bidder has errors in its bid that render it nonresponsive.
Under the old law, a contractor was required to submit their bid protest within 2 days after the bid opening. The problem was that a contractor often does not know the basis to protest an award without seeing the other bids to determine whether the winning bid was responsive. Many owners provide copies of the bids if requested at the bid opening, but some contractors found that owners were refusing to provide copies of the other bids until after the 2-day protest period expired.
The new law, which passed this last Legislative session[1], states that a contractor has two days after the bid opening to either submit a written protest or request copies of the competing bids. If the contractor requests copies of the competing bids from the owner, the contractor then has until 2 days after the competing bids are provided by the owner before the contractor is required to submit its bid protest.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers Cressman Sleight PLLCMr. Hill may be contacted at
brett.hill@acslawyers.com
Payne & Fears LLP Recognized by Best Lawyers in 2024 “Best Law Firms” Rankings
November 27, 2023 —
Payne & Fears LLPPayne & Fears LLP has been recognized by Best Lawyers 2024 “Best Law Firms” list. Firms included in the 2024 edition of Best Lawyers “Best Law Firms” are recognized for professional excellence with consistently impressive ratings from clients and peers.
Payne & Fears LLP has been ranked in the following practice areas:
- Metropolitan Tier 1
- Orange County
- Commercial Litigation
- Employment Law – Management
- Insurance Law
- Labor Law – Management
- Litigation – Labor & Employment
- Litigation – Real Estate
- Metropolitan Tier 3
- Orange County
- Litigation – Intellectual Property
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Attorneys Recognized in the 2024 Edition of The Best Lawyers in America®
September 06, 2023 —
Traub LiebermanRelated Attorneys:
Lisa L. Shrewsberry,
Brian C. Bassett,
Rina Clemens,
Lauren S. Curtis,
Scot E. Samis,
Anthony Hatzilabrou,
Adam P. Joffe,
Heather Jones,
Ashley Kellgren,
Jessica N. Kull,
Ryan S. Parker,
Nicole E. Shapiro
Traub Lieberman is pleased to announce that five Partners have been selected by their peers for inclusion in the 2024 edition of The Best Lawyers in America®. In addition, seven attorneys have been included in the 2024 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Hawthorne, NY; Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Difficult Task for Court to Analyze Delay and Disorder on Construction Project
August 23, 2021 —
David Adelstein - Florida Construction Legal UpdatesOne of my favorites quotes from a case, and I am sure others in the construction industry feel the same way or can relate, is from the District of Columbia Court of Appeals in Blake Construction Co., Inc. v. C.J. Coakley Co., Inc., 431 A.2d 569, 575 (D.C. 1981):
We note parenthetically and at the outset that, except in the middle of a battlefield, nowhere must men coordinate the movement of other men and all materials in the midst of such chaos and with such limited certainty of present facts and future occurrences as in a huge construction project such as the building of this 100 million dollar hospital. Even the most painstaking planning frequently turns out to be mere conjecture and accommodation to changes must necessarily be of the rough, quick and ad hoc sort, analogous to ever-changing commands on the battlefield. Further, it is a difficult task for a court to be able to examine testimony and evidence in the quiet of a courtroom several years later concerning such confusion and then extract from them a determination of precisely when the disorder and constant readjustment, which is to be expected by any subcontractor on a job site, become so extreme, so debilitating and so unreasonable as to constitute a breach of contract between a contractor and a subcontractor.
Do you agree with this sentiment? The reality is that retrospectively analyzing delay on a complicated construction project with numerous moving parts on a day-by-day, hour-by-hour, basis is no easy feat. It is not easy for the parties and certainly not easy for courts to unravel. With every party claiming delay based on a retrospective analysis there will be another party with either a different delay analysis or providing credible cross examination as to flaws with the delay analysis. The same bodes true with loss of productivity / inefficiency claims and the particular case-specific facts are important, preferably with evidence such as photos, videos, notifications, daily reports, manpower reports, etc., supporting the facts. But the facts are complicated, and the delay analysis is complicated, and it is a difficult task for a trier of fact to unravel these facts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com