Colorado HB 13-1090: Concerning Payment of Amounts Due Under a Construction Agreement
February 21, 2013 —
David M. McLain — Higgins, Hopkins, McLain & Roswell, LLCOn January 17, 2013 Representative Fischer introduced House Bill 13-1090 into the Colorado House of Representatives. HB 1090 was assigned the House Business, Labor, Economic and Workforce Development Committee.
The bill, sponsored by Senator Tochtrop in the Senate, sets the following requirements for both private and public construction contracts:
The owner and contractor must make regular progress payments approximately every 30 days to contractors and subcontractors for work actually performed.
To receive the progress payments, the contractor and subcontractor must submit a progress payment invoice plus any required documents.
A contractor must pass on the progress payment to the subcontractor within 5 days or by the end of the billing cycle.
Interest accrues on unpaid progress payments.
A contract may extend a billing cycle to 60 days, but the contract must duly warn of this.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLainmclain@hhmrlaw.com
Legal Disputes Soar as Poor Information Management Impacts the AEC Industry
July 03, 2022 —
Ideagen PlcManagers in Architecture, Engineering and Construction (AEC) are facing more disruptive disputes in 2022 compared to last year according to the latest independent research from regulatory compliance company Ideagen.
The survey of business leaders from AEC firms in the US and UK revealed that 78% of respondents experienced some kind of dispute in the business, compared to 63% in 2021, with information accessibility and visibility, caused largely by high staff turnover, the main root causes. With the challenges that the industry continues to face following COVID and increasing costs of materials, this is an added but unnecessary challenge facing the industry.
Stuart Rowe, Vice President of Collaboration Strategy at Ideagen, whose customers include the US Navy, Gensler, Arup and Ramboll, said: "The working world has continued to change in the last 12 months, which is reflected in the AEC industry's evolving priorities. The COVID-19 pandemic led to a huge shift to remote working which saw an increased need for effective collaboration tools, however, this year is appears that hybrid working is the new normal in the industry.
"Four-fifths of the people we spoke to said email is still king for project correspondence. This is a huge concern as most project scope changes reside in email inboxes. Failing to properly manage all information and records also prevents a Golden Thread, or a Single Source of Truth, across projects and businesses."
Ideagen undertook the independent survey to support developments to their Mail Manager software, used by 2,500 architecture, engineering and construction firms in 16 countries worldwide. It revealed a number of insights into how the industry is managing changing work patterns. Download the full research
here.
Read the court decisionRead the full story...Reprinted courtesy of
The Rubber Hits the Ramp: A Maryland Personal Injury Case
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFAn elderly woman filed suit against the Town of Ocean City, Maryland, “after allegedly falling from her wheelchair because of a defective rubber warning mat on a resort street corner,” according to The Dispatch.
The accident occurred when the woman’s wheelchair “struck one of the hard rubber warning mats on the handicap-accessible street corners.”
The plaintiff is seeking “$750,000 in damages on three counts including negligence, strict liability and a violation of the Americans with Disabilities Act (ADA).” However, The Dispatch reported that it is not clear who is liable, since the sidewalk is owned and maintained by the town, but the State Highway Administration installed the rubber warning mats.
Read the court decisionRead the full story...Reprinted courtesy of
California Enacts New Claims Resolution Process for Public Works Projects
January 19, 2017 —
Garret Murai – California Construction Law BlogIf you’re a public entity or contractor involved in public works construction you should be aware of a new law,
AB 626, which took effect on the first of this year and establishes a new mandatory claims resolution process for disputes on public works projects. Here’s what you need to know:
What is the new law and where is it codified at?
AB 626 added new Public Contract Code Section 9204 that according to the bill’s author, Assemblymember David Chiu of San Francisco, establishes “a claim resolution process applicable to any claim by a contractor in connection with a public works project.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Apartment Building Damaged by Cable Installer’s Cherry Picker
November 20, 2013 —
CDJ STAFFThe owners of Oceana Apartments are suing Shentel Cable Co. and their subcontractors, CCI Systems, Inc. and Big Dog Communications, over the damage caused when a cherry picker rolled downhill and smacked into the building.
Kenneth Benn, an employee of Big Dog Communications, was installing utility wire when the cherry picker started moving. The suit alleges that Mr. Benn either failed to properly apply the brakes or immobilize the vehicle before staring work. Mr. Benn is also named as a defendant in the suit.
Read the court decisionRead the full story...Reprinted courtesy of
What is Bad Faith?
April 04, 2022 —
Stacy M. Manobianca - Saxe Doernberger & Vita, P.C.As a policyholder, you may have heard the term “bad faith” in the context of litigation against your insurer. Bad faith in the insurance context is a catch-all term for a broad category of claims that can be brought against your insurer. Bad faith claims are common in insurance coverage litigation, and they can be a powerful tool in a policyholder’s arsenal. This post will serve as an introduction to some basic concepts surrounding bad faith litigation.
Table of Contents
- Bad Faith Defined:
- Statutory vs. Common Law Bad Faith Claims
- Breach of Contract vs. Tort Bad Faith Claims
- Substantive vs. Procedural Bad Faith Claims
- Best Practices Throughout the Claims Process:
- Involve an Experienced Coverage Attorney
- Conclusion
Read the court decisionRead the full story...Reprinted courtesy of
Stacy M. Manobianca, Saxe Doernberger & Vita, P.C.Ms. Manobianca may be contacted at
SManobianca@sdvlaw.com
No Coverage for Repairs Made Before Suit Filed
August 22, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter a hurricane damaged the building the insured was constructing, there was no coverage under the CGL policy for repairs the insured made in the absence of a suit being filed. Planet Construction J2911 LLC. v. Gemini Ins. Co., 2022 U.S. Dist. LEXIS 105468 (W.D. La. June 13, 2022).
Planet Construction was a general contractor hired to build a fitness club. On August 27, 2020, Hurricane Laura struck the area. After the storm, a pipe in the sprinkler system broke, allegedly due to faulty materials and workmanship by a subcontractor, S&S Sprinkler. Planet Construction sought coverage under its policy with Gemini as well as under S&S's policy with Zurich. Both insurers denied coverage and Planet Construction filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
ASCE Statement on House Failure to Pass the Infrastructure Investment and Jobs Act
October 04, 2021 —
Tom Smith - American Society of Civil EngineersThe following is a statement by Tom Smith, Executive Director, American Society of Civil Engineers (ASCE):
WASHINGTON, DC. – Today, American families and businesses are paying the price while the House plays politics and fails to pass the bipartisan Infrastructure Investment and Jobs Act (IIJA), a historic piece of legislation that would have monumental impacts on the economy, public safety, global competitiveness, and each American's well-being. After decades of kicking the can down the road on meaningful infrastructure legislation, Congress is missing an extraordinary chance to reverse this unsustainable trend with passage of the IIJA, instead choosing to allow critical projects to be delayed.
This legislation was passed in a strong vote by the Senate on August 10th, and almost two months later, it sits on the sidelines as the federal program for transit, roads, and bridges expired on September 30th and projects come grinding to a halt. While other countries are making investments in their future, we are letting politics steal this opportunity to move forward.
It does not have to be this way. This comprehensive bill would bring relief to communities facing strained power grids, aging bridges, leaking water pipes, and spotty broadband. American families do not want to have to wonder if their power will stay on in the next storm, if the bridge connecting their community will close for emergency repairs, or if a week of virtual school means their child will miss out.
We urge the House to pass this bipartisan, commonsense legislation today to create jobs, make goods and services move more quickly and reliably, and make American communities more climate-resilient. Our infrastructure bill has come due, and now is the time to act.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of