Arizona Supreme Court Confirms Eight-Year Limit on Construction Defect Lawsuits
July 18, 2011 —
CDJ STAFFActing on the case of Albano v. Shea Homes Ltd. Partnership, the Arizona Supreme Court has ruled that Arizona’s eight-year statute of repose applies. The case was referred to the court by the Ninth Circuit Court of Appeals which had asked for a clarification of Arizona law. The case focused on three questions:
1. Does the filing of a motion for class certification in an Arizona court toll the statute of limitations for individuals, who are included within the class, to file individual causes of action involving the same defendants and the same subject matter?2. If so, does this class-action tolling doctrine apply to statutes of repose, and more specifically, to the statute of repose for construction defects set forth in Arizona Revised Statutes ("A.R.S.") § 12-552?3. If the doctrine applies to statutes of repose, and specifically § 12-552, may a court weigh the equities of the case in determining whether, and to what extent, an action is tolled?
The litigation at hand has a lengthy history, starting with a case referred to as “Hoffman” in 2003. The Albano plaintiffs were not able to join in Hoffman, and they filed their own lawsuit in 2006. An additional lawsuit was filed by the Albano plaintiffs in 2007. The courts decided that the Albano plaintiffs’ lawsuit was untimely.
The Arizona Supreme Court concluded that the statute of repose was the appropriate standard for this case. They noted that “the eight-year statute of repose period began to run on November 6, 1997, the date of the Town of Gilbert’s final inspection. Albano II was filed on November 5, 2007.”
The court found that the plaintiffs had waited too long for start their suit. As a result, they found it unnecessary to answer the first or third questions. Justice A. John Pelander of the Arizona Supreme Court wrote the opinion, dated June 30, 2011.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Home Damaged by Falling Boulders
March 08, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe policy's earth movement exclusion barred coverage for the home damaged by large boulders rolling down from the hillside above. Sullivan v. Nationwide Affinity Ins. Co. of Am., 2021 U.S. App. LEZXIS 628 (10th Cir Jan. 11, 2021).
Plaintiffs' home sustained extensive damage when two or three large builders rolled down a steep hillside and struck the home. The insurer, Nationwide, hired an engineering firm that determined the boulders were not influenced by meteorological conditions such as torrential rain or high winds. The report noted that rockfall hazards existed primarily due to an undercut sandstone outcrop, and evidenced by numerous rocks from rockfall events that scattered Plaintiffs' property.
Based on the report, Nationwide denied coverage under the earth movement exclusion. The exclusion provided Nationwide did "not insure for loss caused directly or indirectly by . . . Earth Movement" and regardless of "whether or not the loss event results in widespread damage or affects a substantial area." The policy further defined "earth movement" to include "landslide . . . or any other earth movement including earth sinking, risking or shifting."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Broker's Motion for Summary Judgment on Negligence Claim Denied
July 30, 2018 —
Tred R. Eyerly - Insurance Law HawaiiAfter being sued for negligence for failing to secure proper coverage, the broker was unsuccessful in seeking dismissal by way of summary judgment. Liverman Metal Recycling, Inc. v. Arthur J. Gallagher & Co., 2018 U.S. Dist. LEXIS 87957 (E.D. N.C. May 25, 2018).
Plaintiffs were two companies, Empire and Liverman, that processed scrap metal. They were in the process of merging under a management plan by which Empire would acquire Liverman. As part of the plan, Empire's employees were moved on to Liverman's payroll processing system. Concurrently, Liverman renewed its workmen's compensation policy. Defendant Arthur J. Gallagher & Company, an insurance broker, handled the renewal with the insurer, Bridgefield Insurance Company.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
English v. RKK. . . The Saga Continues
December 16, 2019 —
Christopher G. Hill - Construction Law MusingsRemember back in 2018 when I thought I’d told you the end of the English Construction story regarding its various consultants, etc.? I was wrong. The matter went up on appeal to the 4th Circuit Court of Appeals where the Appeals Court considered the summary judgment granted to the defendant Rummel, Klepper & Kahl (“RKK”) based upon what came down to a contributory negligence reading of the indemnity clause that was allowed to survive in the first district court opinion relating to these ambiguous contracts finding that English was negligent so couldn’t recover. The 4th Circuit also considered the finding that defendant CDM Smith did not breach its contract as a matter of law and that English’s negligence was the cause of the damages.
The Court of Appeals reversed both of the holdings by the Western District of Virginia court, essentially stating that there was enough of a factual dispute to render any summary judgment to be premature.
As to English’s arguments regarding the indemnity scheme in the contracts, the court found that the interpretation was at least ambiguous enough that summary judgment was inappropriate, stating:
While we are not prepared to settle conclusively these interpretation disputes at the summary judgment stage, English’s proffered interpretation is, at the very least. reasonable. Indeed, of the two interpretations, English’s seems to be more closely aligned with the actual language in the contract. The district court thus erred in rejecting English’s interpretation and adopting RK&K’s interpretation as a matter of law.
[A]t bottom, while the district court was authorized to construe unambiguous language as a matter of law, it could not resolve genuine disputes regarding the meaning of ambiguous contractual language against the nonmoving party on summary judgment. We therefore vacate the court’s grant of summary judgment to RK&K and remand for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
AI Systems and the Real Estate Industry
April 03, 2023 —
Robert G. Howard & Craig A. de Ridder - Gravel2Gavel Construction & Real Estate Law BlogArtificial intelligence (AI) systems captured considerable attention with the release of a large language chatbot, ChatGPT, by OpenAI, in November of last year. On March 14, OpenAI unveiled GPT-4, a more powerful “multimodal” chatbot responding to both text and images. And, on March 21, Google launched its conversational computer program, Bard, to compete with GPT-4. These chatbots allow users to initiate detailed queries or requests and receive prompt responses in complete sentences. Users are not forced to scroll through a list of results like those produced by search engines and follow-up questions can be asked.
AI systems have been touted for many years and these new breakthroughs may drastically change the way that we create content.
Notwithstanding their unprecedented capabilities, AI systems can produce imperfect results. New chatbots, for example, can generate plausible-sounding but nonsensical, biased or false responses. Accordingly, heavy fact-checking is necessary. OpenAI has warned that ChatGPT is prone to filling in replies with incorrect data if there is not enough information available on the topic on the internet. Bard includes a website disclaimer that it “may display inaccurate or offensive information that doesn’t represent Google’s views.” On March 20, a breach at OpenAI allowed users to see other people’s chat histories before the service was shut down. Further, there is a real risk that courts will rule that certain content generated by these systems infringes the copyright or database rights of the owner of the materials and data that the technologies relied on. When entering into agreements with AI software providers, companies should also be concerned about
other risks, including misappropriation of data, security, confidentiality, privacy and third-party claims.
Reprinted courtesy of
Robert G. Howard, Pillsbury and
Craig A. de Ridder, Pillsbury
Mr. Howard may be contacted at robert.howard@pillsburylaw.com
Mr. de Ridder may be contacted at craig.deridder@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Supreme Court Weighs in on Timeliness of Claims Against Subcontractors in Construction Defect Actions
March 16, 2017 —
Jean Meyer - Colorado Construction LitigationOn February 27, 2017, the Colorado Supreme Court announced its decision in the Goodman v. Heritage Builders, No. 16SA193, 2017 CO 13 (Colo. February 27, 2017) case. In ten short pages, the Colorado Supreme Court completely reshuffled Colorado construction law with respect to application of the statutes of limitation and repose on third-party claims in construction defect cases. Specifically, the Colorado Supreme Court overruled a series of earlier Court of Appeals' decisions that found C.R.S. § 13-80-104(1)(b)(II) (“104(1)(b)(II)”) had no effect on the six-year statute of repose. For context, 104(1)(b)(II) permitted third-party actions for indemnity and contribution to toll until ninety days after the claims in the underlying action were resolved by settlement or judgment. In the construction context, 104(1)(b)(II) was intended to allow a general contractor’s claims against liable subcontractors to toll for the statutorily defined period. This allowed the general contractor to first focus its attention on defending the claims against and thereafter to pursue its claims against the subcontractors.
However, beginning in 2008, in the Thermo Dev., Inc. v. Cent. Masonry Corp., 195 P.3d 1166 (Colo. App. 2008) case, the Colorado Court of Appeals began chipping away at the force of 104(1)(b)(II). This trend continued in the Shaw Constr., LLC v. United Builder Servs., Inc., 2012 COA 24, 296 P.3d 145 decision, the Sierra Pac. Indus., v. Bradbury, 2016 COA 132, _ P.3d_ decision, and culminating in the Sopris Lodging, LLC v. Schofield Excavation, Inc., 2016 COA 158, reh'g denied (Nov. 23, 2016) decision. Effectively, in these decisions, the Colorado Court of Appeals determined that third-party claims could not be brought beyond Colorado’s six-year statute of repose, regardless if they were brought within the ninety day tolling provision set forth in 104(1)(b)(II).
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
Appellate Attorney’s Fees and the Significant Issues Test
June 29, 2017 —
David Adelstein - Florida Construction Legal UpdatesThe significant issues test to determine the prevailing party in construction lien actions (which, by the way, also applies to breach of contract actions) applies to appellate attorney’s fees too! Under this test, the trial court has discretion to determine which party prevailed on the significant issues of the case for purposes of attorney’s fees. The trial court also has discretion to determine that neither party was the prevailing party for purposes of attorney’s fees.
In a recent decision, Bauer v. Ready Windows Sales & Service Corp., 42 Fla. L. Weekly D1417a (Fla. 3d DCA 2017), there were competing motions for appellate attorney’s fees. Both parties believed they should be deemed the prevailing party under Florida Statute s. 713.29 (statute that authorizes prevailing party attorney’s fees under Florida’s Construction Lien Law). The appellate court held that neither party was the prevailing party under the significant issues test: “[W]e conclude that each party lost on their appeal, while each party successfully defended that part of the judgment in their favor on the other party’s cross-appeal. Because both parties prevailed on significant issues, this Court finds that appellate fees are not warranted for either party.”
Bauer, supra. Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
California Builders’ Right To Repair Is Alive
March 19, 2014 —
David J. Byassee - Ulich & Terry LLPThe California Supreme Court surprised everyone on December 11, 2013 when it denied Brookfield Homes’ request for review of the ruling in the case of Liberty Mutual Ins. Co. v. Brookfield Crystal Cove, LLC (2014) 219 Cal.App.4th 98, which was decided by the Court of Appeal for the Fourth Appellate District Division Three (Orange County). In that case the Court of Appeal held that the Right to Repair Act aka SB800 is not the exclusive remedy for a homeowner seeking damages for construction defects that have resulted in property damage. Under the ruling, homeowners may choose to sue builders under common law theories of liability such as strict liability and negligence, in addition to liability under the Act. This ruling made homeowners' compliance with the prelitigation requirements of the Act optional and thereby put builders' “right to repair” in jeopardy. The ruling undermined the expectations of California's homebuilders who, for the past decade, understood that their liability is limited by the Act and that they have a right to repair.
Since the Liberty Mutual case was handed down, the topic has become a hotbed item with several divisions of the Court of Appeal. On February 19, 2014, the Court of Appeal for the Second Appellate District Division Three (Los Angeles County) issued a ruling against Premier Homes in the case of Burch v. Superior Court 2014 Cal.App.LEXIS 159 that, without independent analysis, simply adopted the holding in the Liberty Mutual case.
But on February 21, 2014, the Court of Appeal for the Second Appellate District Division Four (Los Angeles County) ruled in the case of KB Home Greater Los Angeles, Inc. v.Superior Court 2014 Cal.App.LEXIS 167 that a homeowner's failure to give the builder an opportunity to inspect and repair a construction defect excused the builder's liability under the Act. Additionally, the Court of Appeal went out of its way to state it had ruled earlier in that case that the Act is the exclusive remedy.
The various rulings lay a foundation for ultimate intervention by the California Supreme Court. In the meantime, these opposing cases will be cited by counsel for homeowners and builders alike for opposing positions as they continue to navigate construction defect disputes.
Mr. Byassee is a strategic litigator specializing in representation of builders and developers. For more information regarding dispute resolution procedures under SB800, Mr. Byassee may be contacted at (949) 250-9797 or by email at dbyassee@ut-law.com.
Published courtesy of
David J. Byassee, Ulich & Terry LLP
Read the court decisionRead the full story...Reprinted courtesy of