Federal Government Partial Shutdown – Picking Up the Pieces
February 27, 2019 —
Jacob W. Scott - Now that the partial shutdown has ended (though with the specter of another just around the corner), contractors are asking, “What now?” and “What did that cost me?” Although every case is fact-specific, following are some guidelines for moving forward after the shutdown.
Following up on our previous guidance, contractors should make sure that any court, board, or agency filings made during the shutdown were received and properly docketed. If there is any question whether a filing was received, file it again as soon as possible with proof of the earlier attempt to file. The busiest tribunals, such as the federal courts, the Court of Federal Claims, the Boards of Contract Appeals, and the Government Accountability Office, remained open, or at least open to accept filings, and all indications are that filings made during the shutdown were received and acknowledged. But for some of the other tribunals or agencies, such as the Small Business Administration (“SBA”) Office of Hearings and Appeals and the SBA Office of Government Contracting and Business Development, prudence dictates double-checking that all filings were received. In many cases, non-statutory deadlines have been or will be adjusted by the court, board, or agency.
Read the court decisionRead the full story...Reprinted courtesy of
Jacob W. Scott, Smith CurrieMr. Scott may be contacted at
jwscott@smithcurrie.com
Court of Appeal Shines Light on Collusive Settlement Agreements
October 21, 2015 —
Kristian B. Moriarty & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Diamond v. Reshko, (filed 8/20/2015, No. A139251) the California Court of Appeal, First District, held that a defendant was entitled to introduce evidence at trial reflecting amounts paid by co-defendants in settlement of a plaintiff’s claim.
Plaintiff, Christine Diamond, was injured during an automobile accident that occurred while she was a passenger in a taxi driven by Amir Mansouri. Christine, and her husband Andrew, filed suit against Mr. Mansouri, the Yellow Cab Collective (“Yellow Cab”), and the driver of the vehicle that collided with the taxi, Serge Reshko. Before trial, Mansouri and the Yellow Cab Collective settled with Plaintiffs, but agreed to appear and participate as defendants at the jury trial of the action. Mansouri and Yellow Cab paid a total of $400,000 to Plaintiffs in settlement.
Reshko filed a pre-trial motion seeking an order permitting Reshko to admit evidence of the settlement between Plaintiffs and the other defendants. The trial court refused to rule on the motion before trial. Ultimately, evidence of the settlement between Plaintiffs, Mansouri and Yellow Cab was excluded during trial. The jury returned a verdict in favor of Plaintiffs in the total amount of $745,778, finding Mansouri 40 percent at fault, and Reshko 60 percent at fault. The Trial Court entered judgment against Reshko in the sum of $406,698.
Reshko appealed the judgment. The First District Court of Appeal reversed, holding that evidence of the settlement should have been admitted at trial because the settling defendant’s position should be revealed to the court and jury to avoid committing a fraud on the court, and in order to permit the trier of fact to properly weigh the settling defendant’s testimony.
Reprinted courtesy of
Kristian B. Moriarty, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Manager’s Win in Michigan after Michigan Supreme Court Finds a Subcontractor’s Unintended Faulty Work is an ‘Occurrence’ Under CGL
August 03, 2020 —
Gabrielle Szlachta-McGinn - Newmeyer DillionOn June 29, 2020, the Michigan Supreme Court overturned a longstanding precedent that commercial general liability (“CGL”) insurers have historically relied upon to deny insurance coverage for claims involving pre-1986 CGL policies. See Hawkeye-Security Ins. Co. v. Vector Const. Co., 185 Mich. App. 369, 372, 460 N.W.2d 329, 331 (1990). In its recent ruling, the state Supreme Court unanimously agreed that an Insurance Services Office, Inc. (“ISO”) 1986 standard CGL policy, which is sold to construction contractors across the United States, provides coverage for property damage to a policyholder’s work product that resulted from a subcontractor’s unintended faulty workmanship. Skanska USA Bldg. Inc. v. M.A.P. Mech. Contractors, Inc., No. 159510, 2020 WL 3527909 (Mich. June 29, 2020).
In 2008, Skanska USA Building, Inc., the construction manager on a renovation project for Mid-Michigan Medical Center, signed a subcontract with defendant M.A.P. Mechanical Contractors (“MAP”) to install a new heating and cooling (“HVAC”) system. Id. During the renovation, MAP installed some of the expansion joints in the new HVAC system backwards. Id. The defective installation caused approximately $1.4 million in property damage to concrete, steel and the heating system, which Skanska discovered nearly two years after MAP completed the project. Id. After performing the repairs and replacing the damaged property, Skanska sought repayment for the repair costs from MAP and also submitted a claim to Amerisure seeking coverage as an insured under the CGL policy. Id. When Amerisure rejected Skanska’s claim, Skanska sued both parties. Id. Amerisure relied on the holding in Hawkeye and argued that MAP’s defective workmanship was not a covered “occurrence” under the CGL policy, which the policy defined as an accident. Id. at *4.
The Michigan Court of Appeals ignored the express language contained in the CGL policy and applied a prior appellate court precedent from Hawkeye, finding that MAP’s faulty work was not an “occurrence” and thus, did not trigger CGL coverage. Id. at *4. The Court of Appeals further reasoned that Skanska was an Amerisure policyholder and that the only property damage was to Skanska’s own work, which was not covered under the CGL policy. Id. at *5.
In a landmark decision, the Michigan Supreme Court reversed, holding unanimously that the Court of Appeals incorrectly applied the holding of Hawkeye because it failed to consider the impact of the 1986 revisions to standard CGL insurance policies. Id. at *10. Chief Justice Bridget M. McCormack explained that the Hawkeye decision rested on the 1973 version of the ISO form insurance policy, which specifically excluded certain business risks from coverage such as property damage to a policyholder’s own work. Id. The Supreme Court agreed that while Hawkeye was correctly decided, it did not apply here because the 1986 revised ISO policy includes an exception for property damage caused by a subcontractor’s unintentional faulty work. Id.
The Supreme Court said that under the plain reading of the current CGL policy language, an “accident” could include a subcontractor’s unintentional defective work that damaged a policyholder’s work product and thus, may qualify as an “occurrence” covered under the policy. Id. at *9. The Supreme Court defined an “accident” (which was not defined in the Amerisure policy) as “an undefined contingency, a casualty, a happening by chance, something out of the usual course of things, unusual, fortuitous, not anticipated, and not naturally to be expected.” Id. at *5; see Allstate Ins. Co. v. McCarn, 466 Mich. 277, 281, 645 N.W.2d 20, 23 (2002). The Supreme Court noted that there was no evidence suggesting that MAP purposefully installed the expansion joints backwards, nor was there evidence indicating that the parties affected by MAP’s negligence anticipated, foresaw, or expected MAP’s defective installation or property damage. Skanska, 2020 WL 3527909, at *4. Therefore, the Supreme Court concluded that an “occurrence” may have happened, which would trigger coverage under the CGL policy. Id. at *10.
Although this landmark decision changes Michigan law, the decision is limited to cases involving the 1986 ISO policy language revisions to CGL insurance policies. Id. The Supreme Court's decision does not overturn Hawkeye, but rather limits Hawkeye’s authority to cases involving the 1973 ISO form. Id.
Gabrielle Szlachta-McGinn was a summer associate at Newmeyer Dillion as part of the firm's 2020 summer class. You may learn more about Newmeyer Dillion's construction litigation services and find the group's key contacts at https://www.newmeyerdillion.com/construction-litigation/.
Read the court decisionRead the full story...Reprinted courtesy of
EPA and the Corps of Engineers Repeal the 2015 “Waters of the United States” Rule
January 13, 2020 —
Anthony B. Cavender - Gravel2GavelThe pre-publication version of the final rule to be promulgated by EPA and the U.S. Army Corps of Engineers (ACOE) to repeal the 2015 redefinition of the Clean Water Act’s term “Waters of the United States” which is the linchpin of these agencies’ regulatory power under the CWA, was made available on September 12, 2019. The rule should be published in the Federal Register in the next few weeks, and it will be effective 60 days thereafter. Many challenges are expected to be filed in the federal courts.
The 2015 rule was very controversial, and petitions challenging the rule were filed in many federal district courts, several courts of appeal, and finally in the Supreme Court (see NAM v. Department of Defense), which held that all initial challenges must be filed in the federal district courts. The upshot of these challenges is that, at this time, the 2015 rule has been enjoined in more than half the states while the other states are bound by the 2015 rule, a situation which is frustrating for everyone.
In addition to repealing the 2015 rule, the agencies also restored the pre-2015 definition had had been in place since 1986. As a result, the pre-2015 definition of waters of the U.S. will again govern the application of the following rules: (a) the ACOE’s definition of “waters of the U.S.” at 33 CFR Section 328.3; (b) EPA’s general Oil Discharge rule at 40 CFR Section 110; (c) the SPCC rules at 40 CFR Part 112; (d) EPA’s designation of hazardous substances at 40 CFR Part 116; (e) EPA’s hazardous substance reportable quantity rule at 40 CFR Part 117; (f) the NPDES permitting rules at 40 CFR Part 122; (g) the guidelines for dredged or fill disposal sites at 40 CFR Part 230; (g) Exempt activities not requiring a CWA 404 permit (guidelines for 404 disposal sites at 40 CFR Part 232); (h) the National Contingency Plan rules at 40 CFR Part 300; (i) the designation of reportable quantities of hazardous substances at 40 CFR Part 302; and (j) EPA’s Effluent Guidelines standards at 40 CFR Part 401.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Hirer Not Liable Under Privette Doctrine Where Hirer Had Knowledge of Condition, but not that Condition Posed a Concealed Hazard
December 11, 2023 —
Garret Murai - California Construction Law BlogThe Privette doctrine, so-called because of a case of the same name,
Privette v. Superior Court, 5 Cal.4th 698 (1993), provides a rebuttable presumption that a hirer is not liable for workplace injuries sustained by employees of hired parties. In other words, if a property owner hires a contractor, and one of the contractor’s employees gets injured while working on the property, there is a rebuttable presumption that the property owner is not liable for the employee’s injuries, the rationale being that because the contractor is required to carry workers’ compensation insurance the contractor is in the better position to absorb losses incurred a workplace injury.
There are, however, two widely recognized exceptions to the Privette doctrine. The first, is the Hooker exception, again named after a case of the same name,
Hooker v. Department of Transportation, 27 Cal.th 198 (2002), which provides that a hirer is liable for injuries to a hired parties’ employees, if the hirer retained control over the work being performed, negligently exercised that control, and the negative exercise of that control contributed to the employee’s injury.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Congratulations to our 2019 Southern California Super Lawyers Rising Stars
July 30, 2019 —
John Arbucci, Frances Brower, Lisa Hsiao, Kristian Moriarty & Michael Parme - Haight Brown & Bonesteel LLPCongratulations to attorneys John Arbucci, Frances Brower, Lisa Hsiao, Kristian Moriarty and Michael Parme who were selected to the 2019 Southern California Rising Stars list. Each year, no more than 2.5 percent of the lawyers in the state are selected by the research team at Super Lawyers to receive this honor.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
T. Giovanni “John” Arbucci,
Frances Brower,
Lisa Hsiao,
Kristian Moriarty and
Michael Parme
Mr. Arbucci may be contacted at jarbucci@hbblaw.com
Ms. Brower may be contacted at fma@hbblaw.com
Ms. Lisa may be contacted at lhsiao@hbblaw.com
Mr. Kristian may be contacted at kmoriarty@hbblaw.com
Mr. Parme may be contacted at mparme@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Former Superintendent Sentenced in Rhode Island Tainted Fill Case
July 05, 2023 —
James Leggate - Engineering News-RecordA federal judge sentenced a contractor’s former superintendent June 20 for misleading officials about the source of fill and quality of contaminated fill used on the $410 million Route 6/10 interchange project in Rhode Island.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Surfside Condo Collapse Investigators Uncover More Pool Deck Deviations
September 12, 2023 —
James Leggate - Engineering News-RecordThe investigation into the 2021 collapse of the Champlain Towers South condominium in Surfside, Fla., has uncovered more deviations between the as-built conditions of the pool deck and the building’s design. But investigators emphasize their data are still preliminary as they continue to gather and test evidence from the collapse that killed 98 people.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com