Keeping Detailed Records: The Best Defense to Constructive Eviction
October 24, 2023 —
Ben T. Welch & Ken Brown - Snell & WilmerInevitably, commercial property owners and managers will be faced with a claim by a tenant of constructive eviction. This article is intended to describe what constructive eviction is and to suggest what owners and managers can do to prepare for, and ward off, such claims.
Constructive eviction occurs where a tenant’s “right of possession and enjoyment” of the leasehold is disrupted by the landlord in a manner that renders the premises “unsuitable for the purposes intended.”i Put another way, it is interference that is so “substantial nature and so injurious as to deprive the tenant of the beneficial enjoyment of a part or the whole of the demised premises.”ii Although easy to describe in theory, constructive eviction can be devilishly difficult to determine in the real world. In litigation, determining when interference crosses over the line to constructive eviction is intensely fact-sensitive and resists sweeping generalizations.iii
For instance, Utah courts have held that tenants have been constructively evicted when they have been subjected to continual harassment or insults by the landlord or the landlord’s agent,iv prevented or impaired in their access to the leased premises during operating hours,v or when a landlord fails to provide an operable elevator (or other essential commercial amenities) necessary for a tenant’s business operations.vi By contrast, claims of “discomfort” or “inconvenience” have been rejected as a basis for constructive eviction.vii The same goes for claims that a landlord wrongfully served a three-day notice to pay or quit.viii
Generally, constructive eviction is an affirmative defense made in response to a landlord’s lawsuit for nonpayment of rent.ix It is not, as is commonly supposed, a basis for a tenant’s premature abandonment of the premises. In other words, the defense is raised after the tenant has vacated as a result of being effectively “evicted.”x Further, the defense requires the tenant to actually abandon the premises and do so within a “reasonable time” after the alleged interference.xi A tenant cannot stay in possession and simply refuse to pay rent on the basis of constructive eviction.xii
The key consideration in preparing for, and responding to, a claim of constructive eviction is keeping good records. A tenant claiming constructive evicting likely must prove that the issue was raised in a timely manner and, despite multiple entreaties, was never resolved.xiii As such, it is critical that landlords acknowledge tenant complaints as well as document in writing their efforts to ameliorate those complaints. While a landlord does not carry the burden of proof for constructive eviction, detailed documentation can thwart a tenant’s claim that a landlord has been inattentive or unwilling to address the tenant’s concerns.
Detailed records are also useful in disputes where a tenant claims substantial interference. “The whole point of constructive eviction is that the landlord basically drove the tenant out through the landlord’s action or inaction.”xiv As such, a landlord that is unable to document the steps taken in response to complaints will be grossly disadvantaged whereas the tenant, which had control and knowledge of the premises, will have a much easier time describing how the alleged interference deprived them of enjoying the premises.
Even with meticulous records, however, owners and managers may still face claims of construction eviction. In such instances, counsel should be retained to properly advise on compiling, preserving, and employing the evidence necessary to refute the tenant’s claims.
i Gray v. Oxford Worldwide Grp., Inc., 139 P.3d 267, 269 (Utah Ct. App. 2006).
ii Gray, 139 P.3d at 270 (citing Neslen, 254 P.2d at 850) (internal formatting omitted).
iii See Gray, 139 P.3d at 269–70 (citing Thirteenth & Washington Sts. Corp. v. Neslen, 254 P.2d 847, 850 (Utah 1953)); Brugger v. Fonoti, 645 P.2d 647, 648 (Utah 1982).
iv See Gray, 139 P.3d at 270–71.
v Thirteenth & Washington Sts. Corp. v. Neslen, 254 P.2d 847 (Utah 1953).
vi See Richard Barton Enterprises, Inc. v. Tsern, 928 P.2d 368, 375, 378 (Utah 1996) (citing Union City Union Suit Co. v. Miller, 162 A.D.2d 101, 556 N.Y.S.2d 864 (1990)).
vii See Myrah v. Campbell, 163 P.3d 679, 682–84 (Utah Ct. App. 2007).
viii Barton v. MTB Enterprises, 889 P.2d 476, 477 (Utah Ct. App. 1995); see also Brugger, 645 P.2d at 648 (stating that the tenant’s complaints revolved around standard problems commonly associated with building maintenance and did not rise to the level of substantial interference); viv Reid v. Mutual of Omaha Ins. Co., 776 P.2d 896, 898–900 (Utah 1989) (upholding trial court’s findings of fact concerning insufficiency of disruption so as to justify claim for constructive eviction).
ix See Kenyon v. Regan, 826 P.2d 140, 142 (Utah Ct. App. 1992).
x See Kenyon, 826 P.2d at 142.
xi See Kenyon, 826 P.2d at 142; see also Barton v. MTB Enterprises, Inc., 889 P.2d 476, 477 (Utah Ct. App. 1995); Brugger, 645 P.2d at 648.
xii See Kenyon, 826 P.2d at 142 (citing Fernandez v. Purdue, 518 P.2d 684, 686 (Utah 1974)).
xiii See Brugger, 645 P.2d at 648 (noting that while the tenant had raised legitimate issues concerning state of the premises, the landorld had taken steps to remedy the problems within a reasonable time) (citing 49 Am.Jur.2d, Landlord and Tenant, § 617).
xiv Barton, 889 P.2d at 477.
Reprinted courtesy of
Ben T. Welch, Snell & Wilmer and
Ken Brown, Snell & Wilmer
Mr. Welch may be contacted at bwelch@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Supreme Court Rejects Class Action Status, Reducing Homes from 1000 to 71
July 02, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Las Vegas Review-Journal reported that the “Nevada Supreme Court has rejected a request for class action status for claims of damaged stucco from faulty construction by Del Webb Communities involving nearly 1,000 Sun City Summerlin residents,” however, “the court upheld the award of damages to 71 homeowners following a jury trial in Clark County District Court in 2008.”
The case began in 2003, and the Las Vegas Review-Journal referred to it as “one of the largest construction-defect cases in Nevada history.” But District Judge Allan Earl denied class action lawsuit in 2006. “Attorneys were seeking $70 million for the homeowners.” In 2008, another court “determined that only 71 homeowners merited compensation totaling $4 million for the stucco issues.”
According to the Las Vegas Review-Journal, “[h]omeowners alleged that Del Webb failed to install metal screeds that would protect homes from water damage, and as a result, the homes suffered from cracked stucco, mold and weakened walls.”
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Summary Judgment Motion on Business Risk Exclusions Fails
November 15, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer unsuccessfully moved for summary judgment on the CGL policy's business risk exclusions. Scottsdale Ins. Co. v. TL Spreader, LLC, (W.D. La. Oct. 20, 2017).
Helena Chemical Company contracted with its customer Wild Farms to sell and apply certain herbicides and pesticides to Wild Farms' 123 acre rice filed. Helena subcontracted the TL Spreader, LLC (TLS) to apply the chemicals to Wild Farm's rice field. The TLS employee failed to properly neutralize a chemical being used in the spray.
TLS finished its work on May 6, 2014, completing all its work for Helena's contract with Wild Farms. Three days after completion of the spraying, the rice crop first began to exhibit physical damage in the form of abnormal stunting, lesions, yellowing and death.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Teaming Agreement is Still a Contract (or, Be Careful with Agreements to Agree)
November 18, 2019 —
Christopher G. Hill - Construction Law MusingsI have discussed teaming agreements in this past here at Construction Law Musings. These agreements are most typically where one of two entities meets a contracting requirement but may not have the capacity to fulfill a contract on its own so brings in another entity to assist. However, these agreements are contracts and are treated as such here in Virginia with all of the law of contracts behind them.
One illustrative case occurred here in Virginia and was decided by the Virginia Supreme Court. That case is CGI Fed. Inc. v. FCi Fed. Inc. While this is not strictly a “construction” case, it helps lay out some of the pitfalls of teaming agreements in general.
In this case, the parties entered into a fairly typical small business (FCI) Big Business (CGI) teaming arrangement for the processing of visas for the State Department. The parties negotiated the workshare percentage (read payment percentage) should FCI get the work and the teaming agreement set out a framework for the negotiation of a subcontract between FCI, the proposed general contractor, and CGI, the proposed subcontractor. After a while working together, FCI submitted a proposal to the State Department and as part of the negotiations of this proposal, the work percentage for CGI was lowered in exchange for some management positions for CGI relative to the work by amendment to the original teaming agreement. However, one day later FCI submitted a proposal to the State Department that not only didn’t include the management positions, but further lowered CGI’s workshare.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Contractual Warranty Agreements May Preclude Future Tort Recovery
January 11, 2022 —
Taylor Ostrowski - Colorado Construction Litigation BlogWhen a buyer purchases a product that is later discovered to be defective, the court offers a remedy to make the buyer whole. Such remedies can arise either out of a contract, including express and/or implied warranties, or under common law through a tort theory. However, what happens when a buyer has already received the remedy specified in the contractual warranty, only to discover the product manufacturer misrepresented the quality of its product by failing to disclose a defect? Can the buyer subsequently recover for the same product under a tort theory of recovery? The Colorado Court of Appeals analyzed such questions in its December 2021 decision in Dream Finders Homes, LLC v. Weyerhaeuser NR Co., 2021 COA 143.
In Dream Finders, the court examines the rights of sophisticated buyers who purchased defective products and received a warranty from the product manufacturer with purchase. The court specifically determines whether such buyers may recover under the tort theory product misrepresentation and failure to disclose when the buyers have already received the remedy specified and the warranty expressly excludes the type of damage the buyer now seeks.
Read the court decisionRead the full story...Reprinted courtesy of
Taylor Ostrowski, Higgins, Hopkins, McLain & Roswell, LLCMs. Ostrowski may be contacted at
ostrowski@hhmrlaw.com
Renters Trading Size for Frills Fuel U.S. Apartment Boom
July 16, 2014 —
Prashant Gopal – BloombergKatie Graham is living large. Just in a small apartment.
She moved into the new ParkCentral tower in Nashville, Tennessee, for its gym, rooftop deck with heated pool, and the bars and restaurants in the neighborhood below. She didn’t mind the size of the 562-square-foot (52-square-meter) studio.
“I just wanted to be in a good area and wanted good amenities, so I wasn’t looking for something huge,” said Graham, 25, who relocated from her hometown in Jackson, Tennessee, two hours away. “I’m by myself and don’t need all that. The bigger the area, the more furniture you have to buy.”
Young professionals are paying top-market rents to live in new upscale apartment towers sprouting in Nashville and other downtowns across the country. They’re sacrificing living space for a prime urban location and extras such as cooking classes, dog-wash stations and poolside Wi-Fi. Developers, in the biggest U.S. apartment-construction boom in almost a decade, are shrinking the size of units so they can command luxury rates without narrowing the pool of potential tenants.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
Is Construction Defect Notice under Florida Repair Statute a Suit?
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFIn Altman Contractors, Inc. v. Crum & Forster Specialty Ins. Co., “the United States District Court for the Southern District of Florida addressed what constitutes a ‘suit’ within the context of Florida’s right-to-repair procedure for construction defect disputes,” according to Keith Moskowitz, Michael Barnes, J. Stephen Berry, and Cynthia Liu of Dentons. The district court “held that a notice under Chapter 558 of the Florida statutes, the ‘notice and repair’ statute, ‘does not constitute a “civil proceeding”’ and thus ‘is not a “suit”’ triggering an insurer’s duty to defend under Altman’s Crum & Forster commercial general liability (CGL) policies.”
The article states that “[w]hether the 11th Circuit affirms the district court’s decision or not, its opinion will be important to insurers questioning when insurance coverage is triggered by an event other than a formal proceeding initiated in a court of law.”
Read the court decisionRead the full story...Reprinted courtesy of
Design Immunity Does Not Shield Public Entity From Claim That it Failed to Warn of a Dangerous Condition
May 17, 2021 —
Garret Murai - California Construction Law BlogReaders of this blog are familiar with the concept of the design immunity defense.
Codified at Government Code section 830.6, it provides in pertinent that a public entity is not liable for an injury caused by a plan or design of a public improvement where the plan or design has been “approved in advance . . . by the legislative body of the public entity or by some other body or employee exercising discretionary authority to give such approval or where such plan or design is prepared in conformity with standards previously so approved” if the trial or appellate court finds that there “is any substantial evidence upon the basis of which (a) a reasonable public employee could have adopted the plan or design or the standards therefor or (b) a reasonable legislative body or other body or employee could have approved the plan or design or the standards therefor.”
In the next case, Tansavatdi v. City of Rancho Palos Verdes, Case No. B293670 (January 29, 2021), the 2nd District Court of Appeal examined whether the design immunity defense also serves as a defense to a claim that a public entity has a duty to warn of a dangerous condition on public property.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com