More Reminders that the Specific Contract Terms Matter
January 24, 2022 —
Christopher G. Hill - Construction Law MusingsIf there is a theme I have pounded upon here at Construction Law Musings in the over 13 years of posting, it is that the specific terms of your construction contracts will make a huge difference. While there have been reminders galore, a case from the Eastern District of Virginia presented another wrinkle on this theme. The wrinkle? A factoring company.
In CJM Financial, Inc. v. Leebcor Services, LLC et. al., the Court examined this scenario (though it went into more detail than I will here): Leebcorp hired a subcontractor, Maston Creek Services to provide certain construction services under two separate contracts. Maston then hired CJM, a factoring company, and assigned CJM its receivables and the right to collect those receivables. We wouldn’t be discussing this case if all had worked out as planned, so you likely anticipate at least some of what came next. The short story is that Matson failed to pay some of its suppliers and Leebcorp exercised its termination rights under those contracts when Matson refused to cure. In the interim, CJM had paid part of certain payment applications to Matson in compliance with the factoring agreement. When Leebcorp failed to pay CJM for Matson’s work, CJM exercised its assigned rights to collect the receivables and sued Leebcorp for breach of contract. In response, Leebcorp counterclaimed for, among other counts including civil conspiracy, breach of contract based on Matson’s failure to perform. CJM moved to dismiss the counterclaims.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
When an Insurer Proceeds as Subrogee, Defendants Should Not Assert Counterclaims Against the Insured/Subrogor
June 14, 2021 —
Gus Sara - The Subrogation StrategistIn a subrogation action, one party is substituted to the rights and remedies of another with respect to a lawful claim. The substituted party (the subrogee) is legally able to pursue any right or seek any remedy that would be available to the subrogor regarding that claim. But can a defendant in a subrogation action assert any claim against the subrogee that it would have against the subrogor? In Federated Mut. Inc. Co. v. Kosciusko County, No. 3:20-CV-960, 2021 U.S. Dist. Lexis 88735, the United States District Court for the Northern District of Indiana considered whether a defendant could assert counterclaims against the insureds/subrogors in an action filed in the name of their subrogee. The court held that since the insurerds/subrogors were not a party to the action and the defendant could assert the substance of its counterclaim as a defense, the defendant could not file counterclaims against the insureds/subrogors in the insurer’s subrogation action.
Kosciusko County arose from a motor vehicle accident involving a semi-tractor trailer owned by Bellman Oil Company, Inc. (Bellman) and B & B Transport, Inc. (B & B). The accident occurred on a highway in Kosciusko County in October of 2019. The accident caused the semi-tractor trailer containing ethanol fuel to roll over four times and burst into flames. Federated Mutual Insurance Company (FMIC) insured Bellman and B & B for the semi-tractor trailer and issued payments as a result of the accident.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Factories Boost U.S. Output as Builders Gain Confidence: Economy
June 18, 2014 —
Victoria Stilwell – BloombergAmerican manufacturers are churning out more goods and homebuilders are regaining confidence as evidence mounts that the world’s largest economy is making a comeback after a slow start to 2014.
Output at factories, mines and utilities rose 0.6 percent in May, reflecting gains at makers of automobiles, business equipment and construction supplies, according to Federal Reserve data today in Washington. Builder sentiment this month jumped by the most in almost a year, another report showed.
Improving consumer and business spending means assembly lines will probably remain busy in the second half of the year, giving growth a boost after the expansion sputtered in the first quarter. The reports, which came as the International Monetary Fund cut its 2014 forecast for the U.S., give Fed policy makers meeting this week reason to continue trimming stimulus at a measured pace to ensure the rebound is sustained.
“We’re back on track,” said Michael Feroli, chief U.S. economist at JPMorgan Chase & Co. in New York, and the second-best production forecaster over the last two years, according to data compiled by Bloomberg. “Everything is growing at a pretty good clip.”
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, BloombergMs. Stilwell may be contacted at
vstilwell1@bloomberg.net
Holding the Bag for Pre-Tender Defense Costs
February 02, 2017 —
John J. Kozak, Esq. - Florida Construction Law NewsFor a variety of reasons, additional insureds (and even named insureds) under commercial general liability policies will sometimes wait months, and even years, to tender the defense of a claim or lawsuit, incurring significant legal fees in the interim. When the claim finally is tendered, a dispute often arises over who should pay the pre-tender defense costs. Surprisingly, there is very little Florida legal authority specifically dealing with this issue. However, the recent federal 11th Circuit Court of Appeals case of EmbroidMe.com, Inc. v. Travelers Property Casualty Co. of America, No. 14-10616, 2017 U.S. App. LEXIS 368 (11th Cir. Jan. 9, 2017), applying Florida law, addresses the issue head-on and provides CGL carriers with a large hammer in refusing to pay pre-tender fees.
Read the court decisionRead the full story...Reprinted courtesy of
John J. Kozak, Esq., Cole, Scott & Kissane, P.A.Mr. Kozak may be contacted at
john.kozak@csklegal.com
The Problem with One Year Warranties
June 10, 2015 —
Craig Martin – Construction Contractor AdvisorContractors often ask if they should include a one year warranty in their subcontracts. I tell them that they can, but it may be more effective to include a one-year correction period. If a contractor does include a warranty in the contract, it may actually extend the time in which a contractor may be sued. I recommend instead a Correction Period.
Typical Construction Warranties
Form construction contracts, like the AIA forms, often times contain warranty language. The AIA A201, General Conditions, contains a warranty section that covers materials, but it does not address how long the work is warranted:
“3.5 WARRANTY
The Contractor warrants to the Owner and Architect that materials and equipment furnished under the Contract will be of good quality and new unless the Contract Documents require or permit otherwise. The Contractor further warrants that the Work will conform to the requirements of the Contract Documents and will be free from defects, except for those inherent in the quality of the Work the Contract Documents require or permit.”
Instead, the AIA A201, section 13.7, limits the time by which claims must be brought to 10 years or the applicable statute of limitations.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Reversing Itself, West Virginia Supreme Court Holds Construction Defects Are Covered
July 31, 2013 —
Tred Eyerly, Insurance Law HawaiiThe West Virginia Supreme Court previously held that construction defects were not covered under a CGL policy. The Court, however, reversed itself in Cherrington v. Erie Ins. Prop. & Cas. Co., 2013 W.Va. LEXIS 724 (W.V. June 18, 2013).
The underlying complaint against the general contractor alleged various defects in the plaintiff’s recently constructed house, including an uneven concrete floor, water infiltration through the roof and chimney joint, a sagging support beam, and numerous cracks in the drywall walls and partitions throughout the house. Erie Insurance denied coverage. The insured general contractor sued, but the trial court found that faulty workmanship was not sufficient to give rise to an “occurrence.”
The West Virginia Supreme Court reversed its prior rulings determining there was no coverage for construction defects. The court recognized its prior position was in the minority, as is Hawaii's position on coverage for construction defects. See Group Builders Inc. v. Admiral Ins. Co., 123 Haw. 142, 148, 231 P.3d 67, 73 (Haw. Ct. App. 2010). Now joining the majority position, the West Virginia Supreme Court found that defective workmanship causing property damage was an “occurrence” under a CGL policy. Further, the homeowner had demonstrated that she sustained "property damage" as a result of the allegedly defective construction of her home.
The trial court also determined that the business risk exclusions barred coverage. Again, the West Virginia Supreme Court disagreed.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Experts Weigh In on Bilingual Best Practices for Jobsites
February 22, 2018 —
Jim Parsons – ENRIt’s the rare construction firm that doesn’t cite people as its most important resource. And over the past two decades, that asset has become increasingly bilingual. Indeed, more than 27% of workers in construction are Hispanic or of Latino ethnicity, according to the most recent available data from the U.S. Bureau of Labor Statistics (BLS).
Read the court decisionRead the full story...Reprinted courtesy of
Jim Parsons, Engineering News-Record
Review the Terms and Conditions of Purchase Orders- They Could be Important!
February 15, 2018 —
Christopher G. Hill – Construction Law MusingsThere are many moving parts on a commercial construction project. These range from site surveys to weather events to ordering materials. On most large construction projects, the prime contract and subcontracts are generally
drafted ahead of time and hopefully reviewed by both in house personnel and an
experienced construction attorney. However, there are situations, particularly where the contract may be one for service or provision of materials where individual purchase orders are issued as opposed to what would likely be looked at as a long form subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PC