Caution to GCs! An Exception to Privette Can Leave You Open to Liability
February 01, 2023 —
Nicole Whyte - Bremer Whyte Brown & O'Meara LLPIn a recent important decision, Brown v. Beach House Design & Development the Court of Appeal addressed an issue that frequently arises under the Privette doctrine—the extent to which a general contractor can be held liable for injuries to a subcontractor’s employee.
The injuries in Brown arose when a window casing subcontractor’s employee fell from a scaffold erected by a plastering subcontractor at a construction site. According to evidence offered by the plaintiff in opposition to a motion for summary judgment filed by the general contractor, the scaffold was not properly secured to the building where the work was being performed. As a result the scaffold was defective and failed, causing the injuries.
Read the court decisionRead the full story...Reprinted courtesy of
Nicole Whyte, Bremer Whyte Brown & O'Meara LLPMs. Whyte may be contacted at
nwhyte@bremerwhyte.com
Changes to Arkansas Construction and Home Repair Laws
September 30, 2011 —
CDJ STAFFA new law, set to take effect in 2012, lowers the ceiling on when work must be done by a licensed contractor. Through the end of the year, projects costing $20,000 or more had to be done by an Arkansas licensed contractor. As of January 1, 2012, that new limit will be $2,000.
This will apply to all single-family residences and according to Lovely County Citizen, covers “construction, alteration, renovation, repair, modification, improvement, removal, demotion, or addition to a pre-existing structure.” Residential building contractors will be required to have workers compensation insurance, as will home improvement contactors if they take jobs worth more than $20,000.
Morris Dillow, a building inspector in Holiday Island, said, “It will get these scammers out of here who are ripping people off.” He cited the example of a contractor who after getting paid for roof repairs and painting, left the job unfinished.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
District Court's Ruling Affirmed in TCD v American Family Mutual Insurance Co.
May 10, 2012 —
CDJ STAFFIn the case, TCD, Inc. v American Family Mutual Insurance Company, the district court’s summary judgment was in favor of the defendant. In response, the Plaintiff, TCD, appealed “on the ground that the insurance company had no duty to defend TCD under a commercial general liability (CGL) insurance policy.” The appeals court affirmed the decision.
The appeals ruling provides a brief history of the case: “This case arises out of a construction project in Frisco, Colorado. The developer, Frisco Gateway Center, LLC (Gateway), entered into a contract with TCD, the general contractor, to construct a building. TCD entered into a subcontract with Petra Roofing and Remodeling Company (Petra) to install the roof on the building. The subcontract required Petra to "indemnify, hold harmless, and defend" TCD against claims arising out of or resulting from the performance of Petra’s work on the project. The subcontract also required Petra to name TCD as an additional insured on its CGL policy in connection with Petra’s work under the subcontract.”
Furthermore, “TCD initiated this case against Petra and the insurance company, asserting claims for declaratory judgment, breach of insurance contract, breach of contract, and negligence. The district court entered a default judgment against Petra, and both the remaining parties moved for summary judgment. The court granted summary judgment on the entirety of the action, in favor of the insurance company, concluding that the counterclaims asserted by Gateway against TCD did not give rise to an obligation to defend or indemnify under the CGL policy.”
The appeals court rejected each contention made by TCD in turn. First, “TCD contend[ed] that Gateway’s counterclaims constitute[d] an allegation of ‘property damage,’ which is covered under the CGL policy.” The appeals court disagreed. Next, “TCD argue[d] that [the court] should broaden or extend the complaint rule, also called the ‘four corners’ rule, and allow it to offer evidence outside of the counterclaims to determine the insurance company’s duty to defend in this case.” The appeals court was not persuaded by TCD’s argument.
The judgment was affirmed. Judge Roman and Judge Miller concur.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Appeals and Agency Developments at the Close of 2020
December 29, 2020 —
Anthony B. Cavender - Gravel2GavelTHE FEDERAL APPELLATE COURTS
The U.S. Court of Appeals
On November 23, 2020, the court, in a 2-to-1 vote, rejected the plaintiff’s request for an emergency injunction pending appeal in the case of Manzanita Band of Kumeyaay Nation, et al. v. Wolf. The majority held the requirement for such relief did not meet the requirements set forth in Winter v. NRDC, 555 US 7 (2008). Here, the plaintiffs allege that that the government’s construction of a border wall violates several environmental laws that were illegally waived by the Secretary of the Interior. Judge Millett dissented in part because the plaintiffs demonstrated a likelihood of success on the merits. She pointed to the argument that the authority of the Secretary—or Acting Secretary—to take these actions has been successfully challenged in several federal district courts. An expedited pleading schedule was established by the court.
The U.S. Court of Appeals for the Fourth Circuit
On November 17, 2020, in Ergon-West ,Inc. v. EPA, the court again reversed the EPA’s decision denying regulatory relief to a small refinery seeking a waiver of the renewable fuels mandate of the Clean Air Act. Ergon is a small refinery and requested relief in the basis of the economic harm that compliance would entail. In 2018, the court ruled in Ergon’s favor and remanded the case back to the agency. After relief was again denied, the court held that “Ergon has come forward with sufficient evidence undermining one aspect” of the agency’s latest decision, and the ruling was returned to EPA for additional analysis. It appears that a complicated process has become even more complicated.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Eyerly may be contacted at
te@hawaiilawyer.com
Colorado Supreme Court to Hear Colorado Pool Systems, Inc. v. Scottsdale Insurance Company, et al.
October 10, 2013 —
David M. McLain — Higgins, Hopkins, McLain & Roswell, LLCThe Colorado Pool case has been featured in two past blog entries, including: “An Arapahoe County District Court Refuses to Apply HB 10-1394 Retrospectively,” which discussed the case at the trial court level, and “Colorado Court of Appeals Finds Damages to Non-Defective Property Arising From Defective Construction Covered Under Commercial General Liability Policy,” which discussed the case at the Court of Appeals level. In both instances, the courts held that retroactively applying C.R.S. C.R.S. § 13-20-808 to policies in effect prior to the date of the statute’s enactment would be impermissibly retrospective because it would change the coverage under the policy for which the parties had originally bargained.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLainDavid M. McLain can be contacted at
mclain@hhmrlaw.com
Your Construction Contract
April 08, 2024 —
David Adelstein - Florida Construction Legal UpdatesYour construction contract is an important topic. What’s even more important is YOUR process for reviewing and negotiating construction contracts.
Are you simply acting as a riverboat gambler willing to assume undue risk because you don’t value the investment in understanding what you are signing? If so, it becomes hard to complain about what you agreed to and signed when you chose NOT to invest in the process. Investing in the process means you are working with a construction attorney, you have an insurance broker that understands your industry, you have resources in place to ensure risk is negotiated and allocated, and you understand what risk you are assuming to make sure you are properly protecting and perfecting your rights, and transferring risk downstream.
When it comes to construction contracts, there are really three approaches:
1. Riverboat Gambler. This is the “I’ll sign whatever you give me because I don’t want to lose the contract / revenue.” Under this approach, you are not worried about undue risk because you don’t value the investment in the next two approaches. Your thought process is that you’ll care about the risk when an issue pops up, i.e., the riverboat gambler. This is not an approach I’d recommend because it is contrary to the adage, “an ounce of prevention is worth a pound of cure.” This is simply a reactive approach to issues and risks. The other two approaches are more proactive and better suited to understand and manage risk.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Pushing the Edge: Crews Carve Dam Out of Remote Turkish Mountains
July 04, 2023 —
Pam McFarland - Engineering News-RecordRugged Construction | Part Two of an ENR Series
On a cold, gray day in late March, the mountains on the drive to the Yusufeli hydroelectric dam project site in northeastern Turkey seem ominous.
With the highest of these rising more than 3,000 meters above sea level—some of them snow-capped—the jagged rock formations look stark and imposing, the type only a trained professional should attempt to cross.
Reprinted courtesy of
Pam McFarland, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
When is a “Notice of Completion” on a California Private Works Construction Project Valid? Why Does It Matter for My Collection Rights?
January 27, 2020 —
William L. Porter - Porter Law GroupWhat is a Notice of Completion?
A “notice of completion” is a document recorded by the owner of property where construction work was performed. Specifically, it is recorded at the Office of the County Recorder in the County where the work was performed. The notice of completion tells the world at large that the construction project is complete. It also triggers the deadlines for those who have not been paid to make their claims for payment.
Is an Owner of a California Private Works Project Required to Record a Notice of Completion?
No, there is no requirement that an owner of a California private works construction project record a Notice of Completion. However, there are consequences which depend on whether an Owner elects to record the notice or not.
For My Collection Rights, Why Does it Matter Whether a Notice of Completion Has Been Recorded?
The date of recording of a valid notice of completion sets the deadline for those who have not been paid for work performed and materials supplied to a California construction project to pursue such important collection remedies as the “mechanics lien”, the “stop payment notice” and the “payment bond claim.” These are very powerful collection remedies for those who have not been paid. If the deadline to pursue these remedies is missed by a claimant, then the claimant’s right to pursue these remedies is also missed. One of these remedies, the mechanics lien, will enable the claimant to sell the owner’s property where the work was performed in order to get paid.
Read the court decisionRead the full story...Reprinted courtesy of