CGL Coverage for Liquidated Damages and the Contractual Liability Exclusion
October 09, 2023 —
Stu Richeson - The Dispute ResolverLiquidated delay damages are common in construction contracts and are generally imposed when a contractor fails to achieve substantial completion within the time required by the contract. While contracts like the AIA A201-2017 have provisions for extending the time to achieve substantial completion when delays are caused by circumstances beyond the contractor’s control, delays can result from factors other than improper management or planning and the like, for which the owner is not required to give the contractor additional time. Courts are split on whether there is ever coverage under a CGL policy for contractually agreed upon liquidated delay damages.
Liquidated delay damages are often excluded under the contractual liability exclusion of most CGL policies. The contractual liability exclusion excludes coverage for “liability for which the Insured is obligated to pay damages by reason of the assumption of liability in a contract or agreement.” Courts often find the contractual liability exclusion in a CGL policy precludes coverage for liquidated delay damages, because such damages are contractual in nature and are triggered by the failure to bring the contract to substantial completion by a fixed deadline, regardless of the cause of the delay. However, some courts will look to the cause of the delay and find that there is coverage under a CGL policy for liquidated delay damages that are the result of property damage caused by an accident or occurrence.
In Clark Const. Grp., Inc. v. Eagle Amalgamated Serv., Inc., 01-2478-DV, 2005 WL 2092998, at *1 (W.D. Tenn. Aug. 24, 2005) a general contractor entered a contract for the renovation of the convention center in Memphis. Part of the project included the demolition of a structure attached to the convention center. The demolition work was improperly performed by a subcontractor and resulted in damage to the convention center.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Seven Key Issues for Construction Professionals to Consider When Dealing With COVID-19
April 13, 2020 —
Jason Adams - Linked InBy now every construction professional has been inundated with articles regarding the impacts of COVID-19 on the construction industry. The sheer volume of information is overwhelming and changes by the hour. This article is intended to summarize key issues affecting construction professionals and serve as a general road map for navigating the crisis.
1. Determine Project Status
The first consideration is whether the construction projects at issue are allowed to proceed given “shelter in place” and related orders.
Generally speaking, Governor Newsom has deemed construction to be essential and, therefore, exempt from California’s “Safer at Home” order. There is some debate as to whether the governor’s order takes priority over contradictory local (City and County) orders. For example, some Northern California counties and the City of Berkeley have issued orders expressly providing that their local orders legally supersede the State order because the local orders are more restrictive.
If a local ordinance, public entity representative, or the project owner orders the project to shut down, the parties will need to make a fact specific determination regarding how to proceed at that time.
If the project proceeds, employee safety is paramount. In the City of Los Angeles employers are required to develop a “comprehensive COVID-19 exposure control plan” that includes a laundry list of safety requirements. Regardless of the jurisdiction, the parties must err on the side of caution and comply with social distancing (six feet), refrain from holding meetings, and close the project to the public. Anyone who can work remotely should be encouraged to do so.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Adams, Gibbs GidenMr. Adams may be contacted at
jadams@gibbsgiden.com
Federal Courts Reject Insurers’ Attempts to Recoup Defense Costs Expended Under Reservation of Rights
April 11, 2022 —
Anthony L. Miscioscia & Margo Meta - White and WilliamsIn situations where there is a dispute over a duty to defend, an insurer may provide a defense to its insured, subject to a reservation of rights, to not only deny coverage for a defense, but also to file a declaratory judgment action and recoup defense costs in the event it is determined there is no duty to defend. But are defense costs recoupable? Last week, federal trial courts in Georgia and Pennsylvania answered this question with a resounding “no”.
In Chemical Equipment Labs, Inc. v. Travelers Property Casualty Company of America, Case No. 19-3441, 2022 U.S. Dist. LEXIS 61298 (E.D.Pa. Mar. 31, 2022), the United States District Court for the Eastern District of Pennsylvania was called to determine whether Travelers Property Casualty Company of America (Travelers) was entitled to reimbursement of defense costs after it was determined that it had no duty to defend its insured in an arbitration for breach of a charter agreement. The Travelers’ policies did not contain an express reimbursement provision. The court found that Travelers was not entitled to reimbursement because under Pennsylvania law, “[r]eimbursement of defense costs requires an express provision in the written insurance contract.”
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams and
Margo Meta, White and Williams
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Ms. Meta may be contacted at metam@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
43% of U.S. Homes in High Natural Disaster Risk Areas
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFRealtyTrac released data that declared that “35.8 million U.S. single family homes and condos with a combined estimated market value of $6.6 trillion are in counties with high or very high natural hazard risk.” Each county was assigned one of five risk catagories for overall risk of natural disaster: Very High, High, Moderate, Low, and Very Low. States whose scores fell into the “Very High” category included California, Florida, New York, New Jersey, and North Carolina.
“The weather is beautiful in SoCal, but we are statistically more susceptible to the risk of fire, floods and earthquakes than most areas. Our agents must be articulate in explaining the higher risks to buyers. People have to be able trust their agent to fully disclose the risks of natural disasters and homeownership to allow buyers to make the most informed decisions,” Mark Hughes, chief operating officer with First Team Real Estate, covering the Southern California market, told RealtyTrac. “A well-informed knowledgeable buyer is best prepared to take on the potential risks associated with SoCal homeownership.”
Read the court decisionRead the full story...Reprinted courtesy of
Can a Receiver Prime and Strip Liens Against Real Property?
September 20, 2021 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogCourts overseeing receivers generally enjoy broad discretion in directing and approving a receiver’s proposed actions. But does that authority extend to a receiver not only granting a super-priority lien ahead of existing liens, but also selling the real property free and clear of all liens? In County of Sonoma v. Quail, 56 Cal.App.5th 657 (Ct. App. 2020), the California Court of Appeals answered that question in the affirmative.
Quail involved a 47,480 square-foot lot with two houses, a few garages, several outbuildings, and numerous trailers surrounded by a veritable junk yard. Despite many of these structures being uninhabitable, unsanitary, and dangerous, multiple families resided on the lot. Although Sonoma County (the “County”) ordered the owner to remediate the property several times, he failed and refused to do so. After several years of these violations going unabated, the County ultimately sought and obtained the appointment of a receiver over the real property.
To obtain funds necessary to repair the property, the receiver asked the court for permission to borrow money through the issuance of a receivership certificate to be secured by a super-priority lien—i.e., a lien ahead of all other liens—against the real property. Although the trial court initially declined to prime existing liens, when the receiver could find no one to lend money (since the land lacked equity), the trial court relented and approved a super-priority lien despite the senior secured lender’s objection (the “lender”).
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Housing Starts in U.S. Slumped More Than Forecast in March
April 20, 2016 —
Sho Chandra – BloombergNew-home construction in the U.S. slumped more than projected in March, reflecting a broad-based retreat that showed the industry lost momentum heading into the busiest time of year.
Residential starts decreased 8.8 percent to a 1.09 million annualized rate that was the lowest since October and weaker than any forecast of economists surveyed by Bloomberg, Commerce Department data showed Tuesday in Washington. Permits, a proxy for future construction, also dropped.
Read the court decisionRead the full story...Reprinted courtesy of
Sho Chandra, Bloomberg
Using the Prevention Doctrine
April 22, 2019 —
David Erhart - Gordon & Rees Construction Law BlogThe following scenario happens regularly in the construction industry. A contractor on a project reaches out to a subcontractor to perform work. Excited about the prospect of performing the work, the subcontractor signs a contract and puts it nose to the grindstone. After dutifully completing the work the subcontractor turns to the contractor and asks to be paid. But, the contractor refuses saying that there is a provision in the subcontract that says the contractor is only obligated to pay the subcontractor if the contractor receives payment from the owner. So the contractor has completed the work, but has no money to show for it.
One potential remedy for a subcontractor in this situation is the use of the prevention doctrine. “Under the prevention doctrine, ‘if a promisor prevents or hinders fulfillment of a condition to his performance, the condition may be waived or excused.’” Cox v. SNAP, Inc., 859 F.3d 304, 308 (4th Cir. 2017) (quoting Moore Bros. Co. v. Brown & Root, Inc., 207 F.3d 7171, 725 (4th Cir. 2000)). “Put simply, ‘where a party to a contract is the cause of the failure of the performance of the obligation due him or her, that party cannot in any way take advantage of that failure.’” Haddon Hous Assocs v. United States, 711 F.3d 1330, 1338 (Fed. Cir. 2013) (quoting Restatement (Second) of Contracts § 245; Williston, § 39:4).
Read the court decisionRead the full story...Reprinted courtesy of
David Erhart, Gordon & Rees Scully MansukhaniMr. Erhart may be contacted at
derhart@grsm.com
Disappearing Data: Avoid Losing Electronic Information to Avoid Losing the Case
February 01, 2022 —
Daniel C. Wennogle & Jennifer Knight Lang - Construction ExecutiveIt happens: A contractor on a delayed project ends up in litigation over liquidated damages, but the key communications regarding delays and approvals were sent and received by the project manager on a mobile device using text messages and personal email accounts. Unfortunately, the project manager left the company a year ago on bad terms and has changed phones. The information that would serve to mitigate the contractor’s liability has disappeared. With better awareness and policies for capturing and managing electronic information, this is avoidable.
Proactive and effective management of electronically stored information on construction projects can not only reduce costs and discovery disputes should litigation arise but can also provide critical evidence in reducing liability exposure in such disputes. The Federal Rules of Civil Procedure (as well as most state rules, which often mirror federal rules), provide for sanctions if a party fails to preserve electronically stored information (ESI) that should have been preserved in anticipation of litigation but is lost due to the failure to take reasonable steps to preserve it.
Even in arbitration, where discovery and disclosure obligations are often more limited than in the court setting, preservation of ESI can help strengthen claims and defenses, avoiding accusations of spoliation that can derail a case. Arbitrators can also fashion appropriate sanctions for destruction of relevant evidence, not to mention the impact that apparent spoliation can have on a party’s credibility.
Reprinted courtesy of
Daniel C. Wennogle & Jennifer Knight Lang, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Lang may be contacted at jennifer.lang@moyewhite.com
Mr. Wennogle may be contacted at daniel.wennogle@moyewhite.com
Read the court decisionRead the full story...Reprinted courtesy of