David Adelstein - Florida Construction Legal UpdatesIn contract law, there are two doctrines that have similarities but are indeed different. These doctrines are known as novation and modification. There are times you may want to make arguments relative to these doctrines because they are important for your theory of the dispute. Thus, you want to make sure you understand them so you can properly plead and prove the required elements to substantiate the basis of the theories. Understanding the elements will help you understand the evidence you will need to best prove your factual theories.
A novation is essentially substituting a new contract for an old contract.
“‘A novation is a mutual agreement between the parties for the discharge of a valid existing obligation by the substitution of a new valid obligation.’” Thompson v. Jared Kane Co., Inc., 872 So.2d 356, 361 (Fla. 2d DCA 2004) (citation omitted). To prove a novation, a party must prove four elements: “(1) the existence of a previously valid contract; (2) the agreement of the parties to cancel the first contract; (3) the agreement of the parties that the second contract replace the first; and (4) the validity of the second contract.” Id. at 61. Whether the parties consented to the substitute contract can be implied from the factual circumstances. Id.
Parties are more familiar with a modification because it is not uncommon that parties may agree to modify contractual terms. The contract remains in effect but certain terms or obligations are modified. For example, a change order to a contract is a modification.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Multifamily Building Pushes New Jersey to Best Year since 2007
December 04, 2013 —
CDJ STAFFOne project that might be seen as typical for New Jersey is Fair Lawn Promenade, which is being built at the former site of a Kodak film processing plant. The development will revitalize an existing area, rather than send people further from the cities into the New Jersey countryside. The development is within walking distance of a commuter rail station.
This project and ones like it have pushed New Jersey to a 37% increase in residential building over last year. Almost 60% of this year’s residential building in New Jersey has been multifamily. And it’s likely to stay that way for a while, according to Patrick O’Keefe, an economist at CohnReznick. He says that millennials have less of a “commitment to the American dream of homeownership.”
Read the court decisionRead the full story...Reprinted courtesy of
Gardeners in the City of the Future: An Interview with Eric Baczuk
July 08, 2019 —
Aarni Heiskanen - AEC BusinessI had the pleasure of interviewing Eric Baczuk, Designer at Google. We discuss his views on the future urban experience and design. We also touch on Sidewalk Labs of which Eric was a founding team member.
What are you working on currently?
I lead a design team imagining future of communication and thinking about possibilities for what–if anything–might replace the smartphone in our daily lives. What could be the next affordance or device that could offer us a more seamless interface with the digital world?
Can you be more specific about the interfaces?
It’s really just imagining a future with digital interfaces that might be a bit more natural and more humane than what is currently available. In many ways, I think the phone has monopolized social life. You see people standing on the street, for example, waiting for the bus, and 99 percent will have their noses glued to their phones. I think it’s quite anti-social, and in some ways, prevents the friendly, serendipitous encounters that used to be so characteristic of urban living.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Is There a Conflict of Interest When a CD Defense Attorney Becomes Coverage Counsel Post-Litigation?
September 01, 2011 —
Chad Johnson of Higgins, Hopkins, McLain & Roswell, LLCIn Weitz Co., LLC v. Ohio Cas. Ins. Co., the U.S. District Court for the District of Colorado was asked to rule on a motion to disqualify counsel in an insurance coverage action. 11-CV-00694-REB-BNB, 2011 WL 2535040 (D. Colo. June 27, 2011). Motions to disqualify counsel are viewed with suspicion, as courts “must guard against the possibility that disqualification is sought to ‘secure a tactical advantage in the proceedings.’” Id. at *2 (citing Religious Technology Center v. F.A.C.T. Net, Inc., 945 F. Supp. 1470, 1473 (D. Colo. 1996).
Weitz Company, LLC (“Weitz”) is a general contractor and defendant in an underlying construction defect suit which had concluded before the action bringing rise to this order. In the underlying action, Weitz made third-party claims against subcontractors, including NPW Contracting (“NPW”). Weitz was listed as an additional insured under NPW’s policies with both Ohio Casualty Insurance Company and Mountain States Mutual Casualty Company (collectively “the Carriers”). The Carriers accepted Weitz’s tender of defense under a reservation of rights. However, neither insurance carrier actually contributed to Weitz’s defense costs in the underlying action. At the conclusion of the construction defect action, the parties unsuccessfully attempted to apportion the attorney’s fees and costs. Eventually, Weitz brought suit against the recalcitrant carriers. The Lottner firm, which had previously represented Weitz in the underlying construction defect action, continued to represent Weitz in this coverage action.
Read the full story…
Reprinted courtesy of Higgins, Hopkins, McLain & Roswell, LLC. Mr. Johnson can be contacted at johnson@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Structural Failure of Precast-Concrete Span Sets Back Sydney Metro Job
February 23, 2017 —
Chris Webb - Engineering News-RecordA key component of Australia’s biggest public transport infrastructure project—Sydney’s $6.3-billion Metro North West—is the subject of a
critical and detailed technical report describing how an elevated viaduct span failed at a stitch joint between two precast segments during construction last September. Project officials say the affected span, which did not suffer a progressive collapse, has since been removed and its replacement fast-tracked to avoid further delays. Little additional detail was provided.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Webb, ENRENR may be contacted at
ENR.com@bnpmedia.com
Subcontractor Allowed to Sue Designer for Negligence: California Courts Chip Away at the Economic Loss Doctrine (Independent Duty Rule)
August 30, 2017 —
John P. Ahlers - Ahlers & Cressman PLLCAn architect may have to pay over $1 million to a subcontractor who was contractually obligated to rely on the designer’s plans – even though the architect was not a party to the contract.[1] That was the ruling in U.S. f/u/b/o Penn Air Control, Inc. v. Bilbro Constr. Co., Inc.[2]
The dispute involved a $7.3 million design-build contract award to Bilbro Construction (“Bilbro”) to renovate a facility for the Naval Facilities Engineering Command in Monterey, California. Bilbro hired an architect (“FPBA”) to serve as the designer of record and provide all the architectural design services. FPBA’s design team included an acoustical sub-consultant (Sparling). The general contractor (design builder) also retained Alpha Mechanical (Alpha) as the mechanical electrical and plumbing (“MEP”) design/build subcontractor. Alpha, in turn, subcontracted the MEP design to Shadpour Consulting Engineers. During the design phase of this project, Alpha’s MEP design was reviewed by FPBA, Bilbro, and Sparling at the 35, 75, and 100 percent design completion levels. Alpha demonstrated that it regularly received direct communications during design development from Sparling and FPBA, including comments, changes, and revisions. One example Alpha cited was it raised some concerns about anticipated noise level in eight rooms. Sparling made several recommendations to Alpha and Shadpour that were implemented.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
3D Printing Innovations Enhance Building Safety
October 07, 2019 —
Mahmut Ekenel & Melissa Sanchez - Construction ExecutiveThe mention of 3D printing alone is enough to get people excited, often conjuring images of a desktop console that can download and create three dimensional objects such as prototypes, or mechanical parts. And yet, in recent years the technology has given way to a slight impatience, as people begin to wonder how and when it will have a direct impact on both their lifestyles and their businesses.
The construction industry has been quick to take advantage of these innovations, and the effects are tangible, especially regarding building safety. The 3D construction technology allows for several key advantages in terms of faster construction times, uncompromised quality of construction and lower costs—allowing for affordable dwellings to be quickly built for people in need.
These advantages also lead to safety improvements during the building process. The ability to accelerate construction time without requiring an increase in labor results in a fewer construction-related workplace injuries and a reduction in material waste, making it an environmentally friendly construction method as well.
ICC-Evaluation Service (ICC-ES), a subsidiary of the International Code Council (ICC) which develops model codes and standards (i.e. International Building Code, International Residential Code) and delivers a wide array of building safety services, has taken the lead on developing acceptance criteria to address building code compliance of 3D printed construction. Currently, 3D construction technology is not within the provisions of the International Building Code (IBC) or International Residential Code (IRC). The acceptance criteria introduces new compliance measures for interior and exterior 3D printed concrete walls (with and without structural steel reinforcement), load-bearing and non-load-bearing walls, and shear walls in one-story, single-unit, residential dwellings. The 3D walls are constructed by printing two outer layers of 3D concrete and then filling the core with 3D concrete to form a solid wall.
Reprinted courtesy of
Mahmut Ekenel & Melissa Sanchez, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Ekenel may be contacted at mekenel@icc-es.org
Ms. Sanchez may be contacted at msanchez@icc-es.org
Read the court decisionRead the full story...Reprinted courtesy of
Low Interest Rates Encourages Homeowners to become Landlords
June 18, 2014 —
Beverley BevenFlorez-CDJ STAFFCNN Money reported that more homeowners are deciding to keep their homes rather than sell, and become landlords instead. "Clients tell us all the time, 'We're never going to sell our home, even after we buy a new one,'" Glenn Kelman, CEO of the brokerage, Redfin, told CNN Money.