Hurricane Harvey: Understanding the Insurance Aspects, Immediate Actions for Risk Managers
September 07, 2017 —
Gregory D. Podolak - Saxe Doernberger & Vita, P.C.As it’s been more than 10 years since a major hurricane made landfall in the U.S., Hurricane Harvey will test many risk managers’ insurance programs and response plans. Such disasters are complex, and decisive decision-making could mean the difference between staying in business and closing for good.
In this Alert, SDV’s Gregory Podolak and Frank Russo of Procor outline, in clear language, what risk managers need to know about large-scale natural disasters in order to mitigate risks up front and stay sound once they’ve hit.
Read the court decisionRead the full story...Reprinted courtesy of
Gregory D. Podolak, Saxe Doernberger & Vita, P.C.Mr. Podolak may be contacted at
gdp@sdvlaw.com
Prospective Additional Insureds May Be Obligated to Arbitrate Coverage Disputes
September 07, 2020 —
Danielle S. Ward - Balestreri Potocki & HolmesThe Court of Appeal closed out 2019 by ruling that an additional insured can be bound to the arbitration clause in a policy when a coverage dispute arises between that additional insured and the carrier. (Philadelphia Indemnity Ins. Co. v. SMG Holdings, Inc. (2019) 44 Cal. App. 5th 834, 837.)
In 2009, Future Farmers of America (“Future Farmers”) entered into a license agreement with SMG Holdings Incorporated (“SMG”) to use the Fresno Convention Center. As part of the agreement, Future Farmers was required to secure comprehensive general liability (“CGL”) coverage and name SMG and the City of Fresno as additional insureds (“AI”) on its policies.
Future Farmers purchased a general liability policy from Plaintiff Philadelphia Indemnity Insurance Company (“Philadelphia”). Neither SMG nor the City of Fresno were added as AIs, but the policy contained a “deluxe endorsement” which extended coverage to lessors of premises for “liability arising out of the ownership, maintenance or use of that part of the premises leased or rented” to the named insured. The policy also contained an endorsement that extended coverage where required by a written contract for liability due to the negligence of the named insured. Philadelphia’s policy also stated that if the insurance company and insured “do not agree whether coverage is provided . . . for a claim made against the insured, then either party may make a written demand for arbitration.”
A patron to Future Farmer’s event at the Fresno Convention Center was seriously injured after he tripped over a pothole in the parking lot and hit his head. He sued both Fresno and SMG. In turn, Fresno and SMG tendered their defense to Philadelphia. Philadelphia denied coverage finding that the incident did not arise out of Future Farmer’s negligence, and that SMG had the sole responsibility for maintaining the parking lot. Consequently, Philadelphia concluded that neither Fresno nor SMG qualified “as an additional insured under the policy” for the injury in the parking lot.
The coverage dispute continued, and in 2016, Philadelphia issued a demand for arbitration which was rejected by SMG. Philadelphia then petitioned the state court to compel arbitration arguing that SMG could not avoid the burdens of the policy while seeking to obtain policy benefits. SMG used Philadelphia’s conclusion that it did not qualify as an AI under the policy to argue that Philadelphia was “estopped from demanding arbitration”. In other words, SMG argued that it could not be held to the burdens of the policy without being provided with the benefits of the policy.
The trial court sided with SMG finding that there was no arbitration agreement between the parties. The court noted that while third party beneficiaries can be compelled to arbitration there was no evidence that applied here, and Philadelphia could not maintain its inconsistent positions on the policy as its respects SMG.
Disagreeing with the trial court, the Court of Appeal concluded that SMG was a third-party beneficiary of the policy. The AI obligations in the license agreement and the deluxe endorsement in the Philadelphia policy collectively establish an intended beneficiary status. The Court saw SMG’s tender to Philadelphia as an acknowledgement of that status.
Relatedly, the Court found that SMG’s tender to Philadelphia – its demand for policy benefits – equitably estopped them from avoiding the burdens of the policy. The Court stated it defied logic to require a named insured to arbitrate coverage disputes but free an unnamed insured demanding policy coverage from the same requirement. Conversely, the Court found no inconsistency in Philadelphia’s denial of coverage to SMG and its subsequent demand for arbitration. Philadelphia did not outright reject SMG’s status as a potential insured, but rather concluded that there was no coverage because the injury occurred in the parking lot. In other words, the coverage determination turned on the circumstances of the injury not SMG’s status under the policy.
In short, the Court concluded that the potential insured takes the good with the bad. If one seeks to claim coverage as an additional insured, they can be subject to the restrictions of the policy including arbitration clauses even if they did not purchase the policy.
Securing additional insurance has become increasingly more difficult and limited over the years, and this holding presents yet another hurdle to attaining AI coverage. For those seeking coverage, it is important to note that the Court’s ruling may have turned out differently had the carrier outright denied SMG’s AI status, rather than concluding that the injury was not covered.
Your insurance scenario may vary from the case discussed above. Please contact legal counsel before making any decisions. BPH’s attorneys can be reached via email to answer your questions.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle S. Ward, Balestreri Potocki & HolmesMs. Ward may be contacted at
dward@bph-law.com
Housing Buoyed by 20-Year High for Vet’s Loans: Mortgages
July 23, 2014 —
Prashant Gopal and Jody Shenn – BloombergDuring his third deployment in Afghanistan, Air Force Staff Sgt. Claude Hunter was so eager to return to the U.S. and buy a house that he signed a contract for a property that his agent showed him over Skype.
Hunter got back in time to close the deal, paying $219,000 in May for the four-bedroom Waldorf, Maryland, house that he financed with a U.S. Department of Veterans Affairs mortgage. It didn’t require a down payment.
“On Facebook, my friends have started posting: ‘I got my VA loan, I got my house,’” said Hunter, 31. “Everybody is just ready. A lot of them have done their jobs overseas and are coming home.”
America’s fragile housing recovery is getting a boost from military buyers using VA mortgages as the U.S. draws down troops after more than a decade of combat in Iraq and Afghanistan. About 4.7 million full-time troops and reservists served during the wars and many are now able to take advantage of one of the easiest and cheapest paths to homeownership. The program’s share of new mortgages, at a 20-year high, is also increasing as other types of government-backed loans have grown more costly.
Mr. Gopal may be contacted at pgopal2@bloomberg.net; Ms. Shenn in New York at jshenn@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal and Jody Shenn, Bloomberg
Preserving your Rights to Secure Payment on Construction Projects (with Examples)
March 22, 2017 —
David Adelstein – Florida Construction Legal UpdatesAll participants across the construction industry should understand what efforts they should take to maximize and collateralize payment. No one wants to work for free and, certainly, no one in the construction industry wants to work without ensuring there is some mechanism to recover payment in the event they remain unpaid. Being proactive and knowledgeable can go a long way when it comes to recovering your money.
Your Contract – It starts with the contract. You should understand those risks that are allocated to you and those that are allocated to another party. And, you should understand the contractual mechanism to resolve claims and disputes and whether your contract has a prevailing party attorney’s fees provision. In addition to contractual rights, there are tools for you to maximize your collection efforts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Risk Management and Contracting after Hurricane Irma: Suggestions to Avoid a Second Disaster
September 14, 2017 —
Stephen H. Reisman, Gary M. Stein & Adam P. Handfinger – Peckar & Abramson, P.C.Peckar & Abramson attorneys have assisted contractors in the immediate aftermath of several Hurricanes, including Andrew in 1992, Wilma in 2005, Ike in 2008, and Sandy in 2012. Based on this experience, we offer some post-storm strategies for contracting and risk management in three situations:
- Ongoing projects in the area directly impacted by the storm;
- Projects remote from the storm-impacted areas, but which may be affected by material or labor shortages; and
- Requests for assistance in recovery/clean-up/rebuild eff orts, which would be new projects.
Projects Directly Impacted By Hurricane Irma:
1. Immediately review each Owner contract to determine what notices are required for delays and/or extra costs arising from the storm. Contract notice requirements and time limits vary, whether for force majeure or other similar time and compensation rights. There is no effective one-size-fits-all solution. While the initial notice letters will likely look very similar, you should make sure that each is sent as required by the contract. Check each contract’s requirements for particulars regarding content, the form of delivery, and parties and individuals designated to receive the letters as well as carbon copy recipients like the architect. Follow-up notices and time periods differ from contract to contract and should be tracked so that if, for example, a follow-up notice is required in a week per the contract terms, it is tracked to ensure compliance.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Stephen H. Reisman,
Gary M. Stein and
Adam P. Handfinger
Mr. Reisman may be contacted at sreisman@pecklaw.com
Mr. Stein may be contacted at gstein@pecklaw.com
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Treasure Island Sues Beach Trail Designer over Concrete Defects
September 10, 2014 —
Beverley BevenFlorez-CDJ STAFFThe city of Treasure Island, Florida “has filed a lawsuit against Graham Landscape Design of St. Petersburg and Coastal Technology Corp. of Vero Beach for failing to properly design the 1-mile trail along the city's beachfront, which has hundreds of cracks in its concrete surface,” reported the Tampa Bay Times.
"The city has been unable to resolve the construction defects of the Central Beach Trail outside of the litigation process," City Attorney Maura Kiefer said to the Tampa Bay Times.
Cracks allegedly began appearing on the $1.2 million dollar trail soon after the project was concluded (March 2013). Treasure Island “submitted a performance bond claim and notified insurance companies representing Graham Landscape of the problem.”
Consultants hired by Phil Graham IV, the owner of the design company, determined that the cracking was caused by “a combination of problems in the design, construction and composition of materials.”
Read the court decisionRead the full story...Reprinted courtesy of
Portion of Washington State’s Prevailing Wage Statute Struck Down … Again
July 04, 2023 —
Brett Hill & Mason Fletcher - Ahlers Cressman & SleightIn 2018, the Washington Legislature amended its prevailing wages statute adopting S.S.B 5493 and codified as RCW 39.12.015(3). RCW 39.12.015(3) changed how the Washington State Department of Labor and Industries’ industrial statistician set the prevailing wages for employees on public works projects, from a county-by-county basis to a “geographic jurisdiction” basis established in collective bargaining agreements (“CBA”) or if multiple CBAs, the CBA with the higher wage would prevail. This change proved problematic for contractors since it allowed a minority of employees to determine the prevailing wage through side agreements and limited meaningful wage negotiations by industry trade groups. Contrary to the previous rule wherein wages were set by the average or majority wage rate in a certain county (which was normally the collectively bargained wage) and provided some flexibility to the industrial statistician in determining the prevailing wage, now, RCW 39.12.015(3)(a) directs the industrial statistician to “establish the prevailing rate of wage by adopting the hourly wage … paid for the geographic jurisdiction established in [CBAs],” removing flexibility, and requiring the inclusion of CBA (which could encompass multiple counties) wage rates as a part of the prevailing wage formula.
Reprinted courtesy of
Brett Hill, Ahlers Cressman & Sleight and
Mason Fletcher, Ahlers Cressman & Sleight
Mr. Hill may be contacted at brett.hill@acslawyers.com
Mr. Fletcher may be contacted at mason.fletcher@acslawyers.com
Read the court decisionRead the full story...Reprinted courtesy of
“Time Is Money!” In Construction and This Is Why There Is a Liquidated Damages Provision
February 01, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn construction, the adage “Time is Money!” rings true for all parties involved on a project. This includes an owner of a project that wants a project completed on time, i.e., by a substantial completion date. While substantial completion is often defined as when an owner can use a project for its intended purpose, this intended purpose typically equates to beneficial occupancy (in new construction) and other factors as identified in the contract.
The best mechanism for an owner to reinforce time and the substantial completion date is through a liquidated damages provision (also known as an LD provision) that includes a daily monetary rate for each day of delay to the substantial completion date.
A liquidated damages provision is not designed, and should NEVER be designed, to serve as a penalty because then it would be unenforceable. Instead, it should be designed to reasonably compensate an owner for delay to the substantial completion date that cannot be ascertained with any reasonable degree of certainty at the time the contract is being negotiated and executed. (Liquidated damages are MUCH easier to prove than actual damages an owner may incur down the road.) As an owner, you don’t really want to assess liquidated damages because that means the project is not substantially completed on time. And, in reality, a timely completed and performing project should always be better and more profitable than a late and underperforming project. However, without the liquidated damages provision, there isn’t a great way to hold a contractor’s feet to the fire with respect to the substantial completion date.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com