Emotional Distress Damages Not Distinct from “Annoyance and Discomfort” Damages in Case Arising from 2007 California Wildfires
February 16, 2017 —
Kirsten Lee Price & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Hensley v. San Diego Gas & Elec. Co., (No. D070259, filed 1/31/17), the California Court of Appeal for the Fourth Appellate District held that emotional distress damages are available on claims for trespass and nuisance as part of “annoyance and discomfort” damages.
In Hensley, plaintiffs sustained fire damage to their home and property during the 2007 California wildfires. The Hensleys were forced to evacuate as the fires advanced. Although their home was not completely destroyed, it sustained significant damage and they were not able to return home permanently for nearly two months. Thereafter, the Hensleys filed suit against San Diego Gas and Electric Company (“SDG&E”) asserting causes of action for trespass and nuisance, among others. Mr. Hensley, who had suffered from Crohn’s disease since 1991, further claimed that as a result of the stress from the fire, he experienced a substantial increase in his symptoms and his treating physician opined that “beyond a measure of reasonable medical certainty... the stress created by the 2007 San Diego fires caused an increase of [Mr. Hensley’s] disease activity, necessitating frequent visits, numerous therapies, and at least two surgeries since the incident.” SDGE moved, in limine, to exclude evidence of Mr. Hensley’s asserted emotional distress damages arguing he was not legally entitled to recover them under theories of trespass and nuisance. The trial court agreed and excluded all evidence of such damages.
Reprinted courtesy of
Kirsten Lee Price, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Ms. Price may be contacted at kprice@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
CGL Policies and the Professional Liabilities Exclusion
August 14, 2018 —
David Adelstein - Florida Construction Legal UpdatesCommercial general liability (CGL) policies for contractors traditionally contain a professional liabilities exclusion. This exclusion is generally added through a specific endorsement to eliminate coverage for professional services. Read the endorsement The point of the exclusion, in a nutshell, is simply to eliminate a CGL policy for a contractor serving as a professional liability policy.
Contractors need to appreciate a professional liabilities exclusion added through endorsement because oftentimes there are delegated design components they are responsible for. Perhaps the contractor value engineered a system and is responsible for engineering and signing and sealing the engineered documents (through its subcontractor) associated with that system. Perhaps there is a performance specification that requires the contractor to engineer a system. Perhaps there is a design-build component. Regardless of the circumstance, this professional liabilities exclusion can certainly come into play, particularly if a defect is raised with the design or professional services associated with the engineered system.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Home Prices in 20 U.S. Cities Rose at a Faster Pace in October
January 06, 2016 —
Victoria Stilwell & Michelle Jamrisko – BloombergHome values in 20 U.S. cities rose at a faster pace in the year ended October as lean inventories of available properties combined with steadily improving demand.
The S&P/Case-Shiller index of property values climbed 5.5 percent from October 2014 after rising 5.4 percent in the year ended September, the group said Tuesday in New York. The median projection of 21 economists surveyed by Bloomberg called for a 5.6 percent advance. Nationally, prices rose 5.2 percent year-over-year.
A limited supply of properties for sale has helped prop up home values, boosting the household wealth levels of U.S. homeowners in the process. Faster wage growth and continued low borrowing costs will be needed to keep low-income and first-time buyers in the market and provide the next leg of growth in the housing recovery.
Reprinted courtesy of
Victoria Stilwell, Bloomberg and
Michelle Jamrisko, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Risky Business: Contractual Protections in the 'New Normal'
January 04, 2023 —
Daniel Lund III - Construction ExecutiveThe point of contracts is to create certainty to avoid litigated or arbitrated disputes. Still, the various parties in the construction process may have different risk tolerances. For example, general contractors are often characterized as “risk-tolerant.” That risk, though, is usually calculated by the contractor internally, outside the terms of the written contract, based on an assumption that the contractor can get the work done more cheaply and more quickly than the owner anticipated. Project owners typically want and expect close-to-absolute certitude—absolutely as to cost—in their construction contracts. The standard fixed-price or lump-sum construction contract is geared toward protecting that interest.
Post-COVID-19, however, the discussion in the industry suggests that all bets are off when pricing and agreeing to construction work. Labor and materials shortages have sent owners and their design consultants backpedaling when general contractors pursuing a fixed-price contract seek contractual concessions that “un-fix” the price.
Reprinted courtesy of
Daniel Lund III , Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Expired Contract Not Revived Due to Sovereign Immunity and the Ex Contractu Clause
October 27, 2016 —
Chadd Reynolds and David Cook – Autry, Hanrahan, Hall & Cook, LLPA few months ago, a decision by the Supreme Court of Georgia in Georgia Department of Labor v. RTT Associates, Inc. provided a strict rule for contractors that work with state agencies to determine whether a state agency has waived its sovereign immunity. The issue as framed by the Court was “whether an agency’s waiver of immunity from a breach of contract claim as a result of entering into a written contract remains intact in the event the contract is extended without a written document signed by both parties expressly amending the contract, as required by its terms.”
Reprinted courtesy of
David Cook, Autry, Hanrahan, Hall & Cook, LLP and
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLP
Mr. Cook may be contacted at cook@ahclaw.com
Mr. Reynolds may be contacted at reynolds@ahclaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Show Must Go On: Shuttered Venues Operators Grant Provides Lifeline for Live Music and Theater Venues
March 29, 2021 —
David Rao - Snell & Wilmer Real Estate Litigation BlogAlthough it’s been a tough twelve months for many live music venues, movie theaters, and performing arts organizations, help may finally be around the corner. On December 27, 2020, the Economic Aid to Hard-Hit Small Businesses, Nonprofits, and Venues Act was signed into law, creating a $15 billion fund for grants to shuttered venues to be administered by the Small Business Administration’s (“SBA”) Office of Disaster Assistance. The law states that Shuttered Venues Operator Grants (“SVOGs”) will be made available to the following entities and individuals:
- Live venue operators or promoters;
- Theatrical producers;
- Live performing arts organization operators;
- Relevant museum operators, zoos, and aquariums which meet specific criteria;
- Movie theater operators;
- Talent representatives; and
- Each business entity owned by an eligible entity that also meets the eligibility requirements.
Read the court decisionRead the full story...Reprinted courtesy of
David Rao, Snell & WilmerMr. Rao may be contacted at
drao@swlaw.com
Wisconsin Court of Appeals Re-affirms American Girl To Find Coverage for Damage Caused by Subcontractors
September 20, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe trial court's finding of no occurrence and no property damage due to faulty workmanship was reversed by the appellate court. No. 5 Walworth v. Engerman Contracting, Inc., 2021 Wis. App. LEXIS 401 (Wis. Ct. App, July 30, 2021).
Engerman was the general contractor on a construction project at a residence. Engerman was hired to build a poll complex. Engerman subcontracted the project to Downes Swimming Pool Co., Inc. Downes purchased shotcrete (sprayed concrete) from Otto Jacobs Company LLC for the swimming poll walls and base.
After completion, the pool immediately began leaking. An investigation determined that the shotcrete material was not installed correctly, contributing to cracking in the pool walls and the steel reinforcing bars were not sufficient to prevent cracks in the pool walls. The owner demolished the pool and constructed a new one. Thereafter, the owner sued Engerman, its insurers (General Casualty Company of Wisconsin and West Bend Mutual Insurance Company) and Downes and its insurer. Downes filed a third-party complaint against Jacobs and its insurer (Acuity Mutual Insurance Company) alleging Jacobs negligently provided inferior shotcrete to Downes.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com