Is the Removal and Replacement of Nonconforming Work Economically Wasteful?
September 19, 2022 —
David Adelstein - Florida Construction Legal UpdatesThere are times a contractor installs the wrong material or system contrary to the plans and specifications. A nonconformity. The owner wants the already-installed material or system to be replaced in conformity with the plans and specifications. However, what was installed is functionally equivalent to what the plans and specifications required and would be cost prohibitive, i.e., economically wasteful. If the contractor elects to remove and replace the nonconforming work, it may seek a change order because it is economically wasteful. Or, the contractor may refuse (typically, not the best approach) in furtherance of taking on the fight based on the economic wastefulness associated with the removal and replacement. A recent case, David Boland, Inc. v. U.S., 2022 WL 3440349 (Fed.Cl. 2022), talks about this exaction situation and the economic waste doctrine. This is an important doctrine for contractors to understand when faced with a similar predicament.
Here, a contractor was hired by the government to construct a wastewater collection system that was to be owned and operated by a private company. The contractor’s work was going to be incorporated into a larger sewer system that the private company already operated. The contractor was required to install sewer manholes reinforced with steel in accordance with an ASTM standard. The manholes could be rejected if they did not conform to the ASTM standard. Compliance with this ASTM standard was also required by the private company’s construction protocol for the infrastructure, which was incorporated into the contractor’s contract with the government. The contractor was required to strictly comply with the contract.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Former Owner Not Liable for Defects Discovered After Sale
January 29, 2014 —
Beverley BevenFlorez-CDJ STAFFIn a “tentative decision” by Judge Steven Kleifield, Mark Van Peebles and a real estate company have been exonerated “of any liability in a lawsuit involving the sale of the actor’s Playa del Rey condominium, whose buyer says he discovered mold and a flooring defect,” according to the Patch. However, the judge “ordered the Waterfront Homeowners Association to pay Adel Bebawy $26,217 for repair work on the floor and the kitchen as well as civil penalties for not keeping him informed about board meetings.”
The suit began in 2009 after Bebawy alleged “he discovered the floor had a severe slope and that there was significant mold in a bathroom,” reported the Patch. Kleifield, however, stated that the mold didn’t affect the condo’s value. Furthermore, Kleifield wrote that the sloping didn’t become an issue until Bebawy began installing a hardwood floor.
Read the court decisionRead the full story...Reprinted courtesy of
Alabama Still “An Outlier” on Construction Defects
October 14, 2013 —
CDJ STAFFWhile many state Supreme Courts have determined that faulty construction work can be an occurrence under a standard commercial liability policy, the Alabama Supreme Court has taken the contrary view. Writing on the Kilpatrick Townsend blog, Carl A. Salisbury and Edmund M. Kneisel point out that the decision makes Alabama “an outlier,” and they ask, “how much longer will the outliers hold out?”
They note that in the underlying construction defect case, “the arbitrator awarded $3 million in compensatory damages to the homeowners because of improperly installed flashing; improperly installed brick; the lack of weep holes in the brick; improperly installed doors and windows; improper construction of the upper porches; faulty construction of the roof; improper installation of a bathtub.” They summarize: “the house must have leaked like a colander.”
When the insurer denied coverage, the contractor sued. The insurer argued that “the CGL policy form does not cover construction-related acts or omissions because such acts are not an insured ‘occurrence.’” Mr. Salisbury and Mr. Kneisel point out that “the Alabama Supreme Court agreed.”
The problem they see is that “if there is no insurance for any intentional act, then insurance is simply a rip-off — it covers nothing.” They quote Justice Benjamin Cardozo to this effect: “To restrict insurance to cases where liability is incurred without fault of the insured would reduce indemnity to a shadow.” Their argument is that the Alabama decision was not the “correct position,” as exemplified by recent decisions from West Virginia, North Dakota, Connecticut and Georgia. The case “was a prime opportunity for the Alabama Supreme Court to leave the ranks of the outliers and join the majority view.”
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Produce Documents After Failing To Show They Are Confidential
January 19, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe Colorado Supreme Court ordered the insurer to produce documents after failing to demonstrate the documents contained were trade secrets. In Re Rumnock v. Anschutz, 2016 Colo. LEXIS 1228 (Colo. Dec. 5, 2016).
Stephen Rumnock was involved in an auto accident with an uninsured driver. Rumnock brought negligence claims against the driver and uninsured/underinsured motorist claims against his insurers, including American Family Insurance Company. American Family initially refused to pay benefits, but eventually paid him policy limits. Rumnock then amended his complaint to add bad faith and abuse of process claims against American Family.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Be Mindful Accepting Payment When Amounts Owed Are In Dispute
August 29, 2022 —
Nicholas Korst - Ahlers Cressman & Sleight PLLCAfter completing work on a project, or even during a project, it is not uncommon for some portion of the contract balance and/or a claim to be in dispute. As a contractor or subcontractor, it is important to be careful what is signed (or not signed) upon receipt of any payment both during and after completion of work on a project. One of the most common documents signed related to a receipt of payment is a lien/claim release document. This can be in the form of a conditional, unconditional, progress and/or final release. The language included in the release document is critically important, especially as it pertains to disputed amounts. As a contractor or subcontractor, if there are known disputes related to amounts owing, whether it be contract balance, disputed change order(s), a delay or inefficiency claim, or any other amounts believed to be owed, it is important to include language in the lien release that expressly carves out the disputed amounts. The same should be done for disputes related to extensions of time. This allows the contractor to accept the payment and release rights for the undisputed work, but continue to reserve its right to pursue the amounts in dispute later. If disputed amounts are not carved out, those amounts may effectively be waived and the subcontractor or contractor may lose all rights to recovery.
As a subcontractor in Alaska recently learned, there are potentially other ways a contractor may waive or lose its rights to recover amounts in dispute – without even signing a waiver or release document. In Smallwood Creek, Inc. v. Build Alaska General Contracting, LLC et al., the general contractor sent the subcontractor a check described as “final payment.” The subcontractor believed it was owed more than what the general contractor had sent and refused to accept the check. Months later, the subcontractor deposited the check. The subcontractor reversed course again and attempted to repay the general contractor the amount deposited. The general contractor refused, claiming the subcontractor’s acceptance of payment constituted satisfaction of all amounts owing to the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas Korst, Ahlers Cressman & Sleight PLLCMr. Korst may be contacted at
nicholas.korst@acslawyers.com
Understanding the Details: Suing Architects and Engineers Can Get Technical
November 02, 2017 —
Steven M. Cvitanovic & Stephen M. Tye - Haight Brown & Bonesteel LLPBefore suing an architect or engineer for professional negligence, a plaintiff must obtain a “certificate of merit” (“Certificate”) under Code of Civil Procedure section 411.35. Boiled down to the basics, the Certificate declares that the attorney consulted with and received an opinion from an expert that a reasonable and meritorious case exists against said design professional. The Certificate must be filed before serving the complaint on any defendant, but can be filed within 60 days under certain circumstances. This rule was recently analyzed against another long-standing rule in California, known as the “relation-back doctrine.” Under the relation-back doctrine, a court will deem a later-filed pleading, such as an amended complaint, to be deemed filed at the time of an earlier complaint.
In Curtis Engineering Corp. v. Superior Court of San Diego County, No. D072046, (Cal. Ct. App. 10/23/17), the Fourth Appellate Court considered the interplay between section 411.35 and the relation-back doctrine, holding that a Certificate filed more than 60 days after filing the original pleading does not relate back to the filing of the original pleading.
Reprinted courtesy of
Steven Cvitanovic, Haight Brown & Bonesteel LLP and
Stephen Tye, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Tye may be contacted at stye@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Negligent Failure to Respond to Settlement Offer Is Not Bad Faith
May 03, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Ninth Circuit found that the insurer's negligent failure to respond to a settlement offer did not constitute bad faith. McDaniel v. Gov't Employees Ins. Co., 2017 U.S. App. LEXIS 4029 (9th Cir. March 7, 2017).
McDaniel was the assignee of claims against GEICO assigned by the insured after settling a wrongful death suit. McDaniel alleged that GEICO unreasonably refused to accept a $100,000 policy limits offer. The case went to trial and a jury awarded McDaniel over $3 million against the insured.
On August 7, 2009, McDaniel's attorney Steven Nichols extended a $100,000 policy limits settlement offer with a fifteen day acceptance deadline to GEICO's attorney Michael Griott. The parties subsequently agreed to extend the acceptance deadline to ten days following MacDaniel's service of responses to outstanding interrogatories, which Nichols hand-delivered to Griott on August 27, 2009. On September 1, 2009, Griott emailed GEICO claims adjuster Aldin Buenaventura with a letter attachment indicating that Nichols had submitted the requested interrogatories and, in bold and underlined text, that "[o]ur response to Plaintiff's policy limits demand is due on or before September 11, 2009.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
What California’s COVID-19 Reopening Means for the Construction Industry
July 05, 2021 —
Garret Murai - California Construction Law BlogThis past Wednesday, Governor Newsom announced that California would reopen after being in lockdown for over a year due to COVID-19. Gone is Governor’s Stay at Home Executive Order. Gone is California’s Blueprint for a Safer Economy. And gone is the state’s somewhat confusing four-tier, yellow (minimal), orange (moderate), red (substantial) and purple (widespread), risk-level mapping system.
So what does this mean for the construction industry?
Well it’s not quite business back to usual. CalOSHA’s Standards Board voted this past Thursday to pass revised COVID-19 Emergency Temporary Standards (“Revised Standards”). That same day, Governor Newsom signed Executive Order N-09-21 implementing the Revised Standards immediately while they are being reviewed by the Office of Administrative Law.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com