California Court of Appeal Vacates $30M Non-Economic Damages Award Due to Failure to Properly Apportion Liability and Attorney Misconduct During Closing Argument
February 08, 2021 —
Krsto Mijanovic, Peter A. Dubrawski, Arezoo Jamshidi & Catherine M. Asuncion - Haight Brown & Bonesteel LLPOn January 20, 2021, the California Court of Appeal, Second District, Division Six (Ventura), in Plascencia v. Deese (B299142), vacated a $30 million non-economic damages award in a highway fatality case because: (1) the award did not properly apportion non-economic damages among everyone at fault in violation of Proposition 51; and (2) the amount of the award appeared to have been influenced by plaintiffs’ counsel’s misconduct and prejudicial remarks during closing argument.
In Plascencia, the plaintiffs sued several defendants for the wrongful death of their daughter arising from a highway fatality accident. All the defendants settled or were dismissed before trial except the trucking defendants. The highway fatality was caused when one defendant driver made an illegal U-turn on a highway as she left another defendant’s fruit stand. The plaintiffs’ daughter swerved to avoid the U-turn driver, lost control of her car, and crashed into the back of the trucking defendants’ diesel tractor-trailer. The truck driver had parked the truck on the side of the highway near the fruit stand, which the trucking defendants’ expert conceded fell below the standard of care.
Reprinted courtesy of
Krsto Mijanovic, Haight Brown & Bonesteel LLP,
Peter A. Dubrawski, Haight Brown & Bonesteel LLP,
Arezoo Jamshidi, Haight Brown & Bonesteel LLP and
Catherine M. Asuncion, Haight Brown & Bonesteel LLP
Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com
Mr. Dubrawski may be contacted at pdubrawski@hbblaw.com
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Ms. Asuncion may be contacted at casuncion@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida SB 2022-736: Construction Defect Claims
February 07, 2022 —
Kelly A. Johnson - Saxe Doernberger & Vita, P.C.*Special thank you to SDV Law Clerk Iliriana Fteja for contributing to this article.
A new bill (SB 2022-736) was recently introduced to the Florida Senate. The proposed amendments to the statutes of limitations and repose could significantly impact construction defect claims by effectively creating additional exposure to contractors and insurance carriers.
The proposed bill requires all actions founded on the design, planning, or construction of an improvement to real property to be commenced within four years after the time to commence an action begins. Under the proposed amendment, the time to commence an action runs from the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion of the contract or termination of the contract between the professional engineer, registered architect, or licensed contractor and their employer. This provision would effectively alter the time to commence an action to whichever triggering event is earliest instead of the latest triggering event per the previous statute.
Read the court decisionRead the full story...Reprinted courtesy of
Kelly A. Johnson, Saxe Doernberger & Vita, P.C.Ms. Johnson may be contacted at
KJohnson@sdvlaw.com
How Many Bridges Does the Chesapeake Bay Need?
August 03, 2022 —
Ethan McLeod - BloombergSteve Kline, a 7th-generation Marylander, knows well the vacation tradition of driving across the twin spans of the Chesapeake Bay Bridge for trips to the beach resort of Ocean City. His grandfather, an ironworker, helped build the bridge’s first span, which opened in 1952.
He’s also very familiar with another seasonal rite: wading through the infamous miles-long traffic backups that last from Memorial Day through the end of summer.
But Kline, president of the nonprofit Eastern Shore Land Conservancy, is not on board with the state’s proposed multibillion-dollar fix — a new 4.3-mile-long crossing, to be built alongside the two current spans of the Bay Bridge. In April, the Maryland Transportation Authority (MDTA) announced it had received federal approval to use this route for a potential new, wider bridge that would be likely to eventually replace its older siblings, addressing the notorious summer bottlenecks for decades to come. And on June 10, at a press conference held near the bridge’s eastbound ramp, Maryland Governor Larry Hogan announced that he would commit $28 million in bridge toll revenue to fund the second phase of an environmental impact study on the idea.
Read the court decisionRead the full story...Reprinted courtesy of
Ethan McLeod, Bloomberg
Defeating the Ten-Year Statute of Repose For Latent Construction Defects
January 28, 2015 —
The Porter Law GroupIt is an all-too-common scenario in California construction: Nine and a half years after completion of a major California construction project, immediately before the 10-year “statute of repose” for suing on “latent” construction defects expires, a lawsuit claiming damages for “recently discovered” latent construction defects is filed. The property owner sues the contractor for the alleged defects. The direct contractor sues all its subcontractors for indemnity and defense. The attorneys spontaneously generate. Experts proliferate. Claimed defects are extrapolated. Four or five years later, after a few dozen attorneys earn a small fortune in fees, the insurance companies make payments. Attorneys collect more fees. The owners take what remains. They repair nothing... and buy vacation homes.
Perhaps a cynical view, but there are many in the construction defect world who would reach a similar conclusion. The question is: How can you defeat this seemingly inevitable chain of events? Under a case known as Brisbane Lodging L.P. v. Webcor Builders, Inc. 216 Cal.App 4th 1249 (2013) there may be hope. California Code of Civil Procedure sections 337.1 and 337.15 grant a 10-year “statute of repose” for bringing claims for “latent” construction defects. These statutes allow a lawsuit for such claimed defects to be filed in court up until ten years after the project has been completed. Latent defects are generally defined as those which are “not apparent by reasonable inspection” (CCP §337.15(b)). It is extremely common for such claims to be filed immediately before this 10-year deadline expires. When the lawsuit is brought, the cash register begins to ring.
Read the court decisionRead the full story...Reprinted courtesy of
The Porter Law Group
Increasing Use of Construction Job Cameras
January 27, 2014 —
Beverley BevenFlorez-CDJ STAFFJob site cameras are increasingly used on construction sites, for various reasons, reports Tom Sawyer of Engineering News-Record. Mark Penny, senior vice president of the Dallas Region Manhattan Construction Inc., told Sawyer that he uses the camera primarily for marketing purposes: “We have a lot of high-profile jobs that people want to see. They are a great opportunity for us and the client to showcase the construction, which makes the job of selling what we do a lot easier.”
Warren Andres, senior vice president at Andres Construction uses cameras for safety monitoring. Andres told Sawyer that “he has three monitors on his desk. One shows live feeds from all his cameras. If he sees unsafe work, he sends a photo to the superintendent and demands action. Similarly, he says he can spot slow work crews and do enough quality control to send the message that management is watching.”
Vendors commented to Sawyer that “the growing use [of cameras] include the rise of building information modeling and its increased need for accountability; as well as companies chasing work beyond usual areas of operations and needing to extend supervision while holding down travel of staffs trimmed by the recession.”
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to BWB&O’s 2021 Super Lawyers Rising Stars!
July 05, 2021 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is excited to announce Partners Kyle Carroll, Nicole Nuzzo, and Michael D’Andrea, as well as Associates Andy Arakelian and Andrew Steinberg, have been selected to the 2021 Super Lawyers Southern California Rising Stars for their work in Civil and Family litigation!
Super Lawyers is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The patented selection process includes independent research, peer nominations, and peer evaluations.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
More on the VCPA and Construction
February 01, 2023 —
Christopher G. Hill - Construction Law MusingsI have posted before regarding the intersection between the Virginia Consumer Protection Act (VCPA) and construction contracting in regard to residential construction projects. A case out of the Eastern District of Virginia District Court further discusses this intersection as it relates to design contracts that also include the procurement and installation of certain design elements post-design. The basic facts of Marcus v Dennis are as follows:
In October of 2018, Defendant Marlene Dennis, the owner of Marlene Dennis Design, LLC (“MDD”), operating out of Virginia, entered into a contract to provide design services and the procurement and installation of certain design elements for the Plaintiffs, Gregory and Jamie Marcus, at their Maryland home. The Marcuses agreed to $175 per hour to Dennis with a cap of a total of $100,000.00 for design consultation and furniture selection and procurement. The Marcuses also agreed that they would pay no more than $250,000.00 for furnishings, rugs, artwork, decorative lighting, and accessories. In November 2020, Dennis sent an invoice for $68,000.00 and informed the Plaintiffs that the total contract fees would be more than the $100,000.00 cap. After paying $124,722.41 in design fees, the Plaintiffs received an invoice for $255,5560.72 in January of 2021. Despite the cap of $250,000.00, the Plaintiffs wired $255,000.00 to Dennis while requesting the backup invoices for the material charges. After much effort and a threat of litigation, the Plaintiffs received documents from Dennis showing that Dennis inflated the costs of the materials prior to passing the costs along to the Marcuses. The Plaintiffs’ home was unfurnished and empty as of April 10, 2021, and the Marcuses had to hire and pay another design team over $85,000.00 to finish Dennis’ work. Needless to say, the Marcuses sued both Dennis and her firm for breach of contract, breach of fiduciary duty, and for violation of the VCPA. Dennis moved to dismiss the Complaint.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Sacramento’s Commercial Construction Market Heats Up
September 10, 2014 —
Garret Murai – California Construction Law BlogOne reason I changed law firms from the Bay Area to Sacramento was I felt that Sacramento’s construction market, which was one of the areas hardest hit in California following the Real Estate Bubble Burst, was poised for a comeback.
And as with past real estate cycles, residential construction has led the growth, and is now being followed by commercial construction. Indeed, according to data compiled by Engineering News-Record, commercial and institutional projects are propelling Sacramento’s construction market[.]
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at