New York Appellate Court Holds Insurers May Suffer Consequences of Delayed Payment of Energy Company Property and Business Interruption Claims
March 16, 2020 —
Syed S. Ahmad & Geoffrey B. Fehling - Hunton Andrews KurthA New York appellate court recently held that renewable bio-diesel fuel manufacturer BioEnergy Development Group LLC may pursue tens of millions of dollars in damages from its insurers under two all-risk insurance policies, including amounts in excess of the policy limits, where the insurers refused to pay claims in a timely manner.
BioEnergy purchased two all-risk property policies from Lloyd’s to provide coverage for its manufacturing plant in Memphis, Tennessee. A fire destroyed the Memphis plant in March 2016, eliminating BioEnergy’s production capacity and sole source of revenue. BioEnergy made claims under the policies and sought to rebuild its plant. The insurers acknowledged coverage and eventually made approximately $8 million in interim payments, but the parties disagreed over the value of the total property damage claim, which BioEnergy contended was in excess of $24 million. The disputed claim was submitted to appraisal, which resulted in the insurers agreeing to pay the full business interruption limit of $15.1 million.
The insurers filed a declaratory judgment lawsuit, however, seeking to limit BioEnergy’s recovery to the policy limits of $15.1 million. BioEnergy alleged that the insurers failed to make interim payments in a timely manner after the fire and, as a result, the company suffered increased losses because it could not rebuild without the insurance proceeds. BioEnergy sought actual and consequential damages, plus attorneys’ fees, arising from the delayed payments, including payment of its business interruption losses in excess of the policy limits.
Reprinted courtesy of
Syed S. Ahmad, Hunton Andrews Kurth and
Geoffrey B. Fehling, Hunton Andrews Kurth
Mr. Ahmad may be contacted at sahmad@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Three Reasons Lean Construction Principles Are Still Valid
February 27, 2019 —
Kevin Clary - Construction ExecutiveWhen lean principles were first introduced to the construction industry five years ago, project managers raced to implement the production method. The internet was rife with content about how to easily overhaul a jobsite and transform it into the picture of efficiency.
However, the number of lean construction critics have multiplied significantly in recent months. They claim concepts are near impossible to implement or, even worse, automation eliminates the need for deliberate human processes. These ideas are misleading. Lean principles are still valid for a few key reasons.
1. Lean involves seeing things from the customer’s point of view
One of the defining principles of lean construction is understanding value from the customer’s point of view. The concept encourages stakeholders, including the owner, contractor and supplier, to come together during the early planning stage of the project. The significant level of trust created from this exercise can’t be replicated by machinery. It involves compassion, collaboration and a sense of creativity that artificial intelligence is yet to possess. Moreover, the rapport gained through this service-oriented exercise is worth the time investment.
Reprinted courtesy of
Kevin Clary, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Maximizing Contractual Indemnity Rights: Components of an Effective Provision
December 02, 2015 —
William Kennedy – White and Williams LLPTort law is aimed at providing compensation to the victims of negligence. Tort law encourages plaintiffs to cast a wide net, pursuing claims or suits against not only those whose fault seems manifestly primary, but also against defendants whose causal exposure is minimal, against those whose exposure is purely by operation of law. As discussed in the first installment of this series, "Maximizing Contractual Indemnity: Problems with Common Law," three common law principles – vicarious liability, joint and several liability, and common law indemnity – cause some parties to pay in excess of their actual degree of causal fault. Contractual indemnity can remedy that harsh result.
Part Two: Components of an Effective Provision
Properly composed, “broad form” contractual indemnity provisions permit an Indemnitee to shift the full range of financial consequences from tort exposure, including civil damages, defense fees, expert fees, and litigation expenses. Such contracts permit indemnity even where the underlying damage was incurred due to a degree of negligence or fault on the part of the Indemnitee. Such contracts can also allow an Indemnitee to shift to the Indemnitor the risk of loss for someone from whom the Indemnitor would otherwise be immune from suit (e.g., the Indemnitor’s employees). A well-written contract can even convert an entity which is an Indemnitor as to one party (e.g., a general contractor which has to indemnify a property owner) into an Indemnitee as to another party (e.g., a subcontractor) for the very same risk.
Read the court decisionRead the full story...Reprinted courtesy of
William Kennedy, White and Williams LLPMr. Kennedy may be contacted at
kennedyw@whiteandwilliams.com
Partner Jason Taylor and Senior Associate Danielle Kegley Successful in Appeal of Summary Disposition on Priority of Coverage Dispute in the Michigan Court of Appeals
December 11, 2023 —
Jason Taylor & Danielle K. Kegley - Traub LiebermanIn this appeal brought before the Michigan Court of Appeals, the appellate court ruled in favor of Traub Lieberman’s insurance carrier client (the “Carrier” or “Client”), affirming an award of summary disposition in favor of the Carrier in a coverage lawsuit. The coverage lawsuit involved a priority dispute between the Carrier and another insurer over which company’s policy had responsibility to cover the defense of their mutual insured, a heating and cooling contractor (the “Insured”) in an underlying lawsuit alleging carbon monoxide poisoning. The Carrier issued a contractor’s pollution liability policy and the other insurer issued a commercial general liability policy to the Insurer. Both the Carrier and the other insurer filed cross-motions for summary disposition in the trial court on the priority of coverage issue. The trial court granted the Client’s motion, holding that the CGL carrier was the primary insurer based on the language in the policies’ “other insurance” clauses. The trial court rejected the CGL carrier’s argument to apply the “total policy insuring intent” or “closest to the risk” tests—tests which Michigan courts have not adopted. Specifically, the court rejected the CGL carrier’s argument that the Client’s contractor’s pollution liability policy was more specifically tailored to the loss in the underlying lawsuit. The trial court also rejected CGL carrier’s alternative argument that the “other insurance” clauses in the policies were irreconcilable, requiring a pro rata allocation based on the respective limits of the policies.
Reprinted courtesy of
Jason Taylor, Traub Lieberman and
Danielle K. Kegley, Traub Lieberman
Mr. Taylor may be contacted at jtaylor@tlsslaw.com
Ms. Kegley may be contacted at dkegley@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Texas Jury Finds Presence of SARS-CoV-2 Virus Causes “Physical Loss or Damage” to Property, Awards Over $48 Million to Baylor College of Medicine
September 26, 2022 —
Michael S. Levine & Kevin V. Small - Hunton Insurance Recovery BlogA Texas jury has found that the presence of SARS-CoV-2 virus on the property of Baylor College of Medicine (BCM) caused “physical loss or damage” and resulting economic loss, triggering coverage under BCM’s commercial property insurance program. The jury awarded BCM over $48 million following a three-day trial; the award consisted of $42.8 million in business interruption, $3.3 million in extra expense, and $2.3 million in damage to research projects.
The verdict came after the court denied the insurers’ pre-trial motion for summary judgment, rejecting the insurers’ contention that a virus cannot—as a matter of law—cause physical loss or damage to property. In denying the motion, the court held that whether the presence of the virus causes physical loss or damage presents a question of fact for the jury to resolve; a copy of the order rejecting the insurers’ summary judgment argument can be found
here.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Kevin V. Small, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Small may be contacted at ksmall@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Look Out! Texas Building Shedding Marble Panels
November 13, 2013 —
CDJ STAFFThe streets around the Omni Building in Lubbock, Texas have been barricaded for an indefinite period, since the marble panels have been falling off the building. The panels weight about 300 pounds each.
The building’s owners attempted to remedy the problem by replacing the marble with stucco, but that too came loose in the wind and fell to the ground. The city issued a stop work order preventing the installation of any more stucco. The city “told them that all needed to come down, both the old and the new,” according to Steve O’Neil, the city’s chief building official.
The city has filed a lawsuit to compel the owners to fix the building. Glen Robertson, Lubbock’s mayor, sees another possible solution, “or demolish it because, as it stands right now, it is truly a health and safety hazard to our citizens.
Read the court decisionRead the full story...Reprinted courtesy of
Nonresidential Construction Employment Expands in August, Says ABC
December 16, 2019 —
Associated Builders and Contractors - Construction ExecutiveThe construction industry added 14,000 net new jobs in August, according to an Associated Builders and Contractors analysis of data released by the U.S. Bureau of Labor Statistics. On a year-over-year basis, industry employment has expanded by 177,000 jobs, or 2.4%.
Nonresidential construction employment increased by 11,600 net jobs in August and is up by 114,200 net jobs over the last 12 months, translating into 2.5% growth. The majority of job gains emerged from nonresidential specialty trade contractors, which added 5,400 jobs last month and nearly 103,000 positions over the past year. Heavy and civil engineering added 4,400 net new jobs, while nonresidential building added 1,800 jobs on a monthly basis.
The construction unemployment rate stood at 3.6% in August, up 0.2 percentage points from the same time last year. Unemployment across all industries stood at 3.7% in August, unchanged from the previous month.
“While job growth across all industries fell short of projections, today’s employment report was just about perfect,” said ABC Chief Economist Anirban Basu. “Yes, employment growth has been softening for quite some time, with average monthly job growth totaling 150,000 during the last six months after approaching 200,000 during the prior six-month period. And employment growth estimates were also revised lower for both June and July. That said, looking beyond the headline number, August’s labor market performance was more than respectable, even accounting for about 25,000 of the jobs being added for temporary Census work.
Reprinted courtesy of
ABC, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Cincinnati Goes Green
May 10, 2013 —
CDJ STAFFColumbus Dispatch reports that under a program in Cincinnati, homeowners can receive tax breaks that eliminate their property taxes for up to fifteen years. As a result, while about 100 single-family homes in Cincinnati are LEED-certified, Columbus can claim only one. The rest of the state also lags behind, with only eighteen percent of LEED-certified homes outside Cincinnati.
Jim Weiker reports that energy efficiency is at the top of homebuyers’ wants, even beating out granite countertops. But although green certification seems to support a four percent increase in price, builders aren’t rushing to follow LEED standards.
Read the court decisionRead the full story...Reprinted courtesy of