Understand Agreements in Hold Harmless and Indemnity Provisions
June 06, 2022 —
Jeffrey Cavignac - Construction ExecutiveOne of the most important provisions in a construction contract is the indemnity provision. An indemnity provision, which usually includes a requirement to hold harmless and defend another party, is included in nearly all construction contracts. Generally speaking, the upstream party (a general contractor or owner, for example) is attempting to shift risk to a downstream party (the general contractor or a subcontractor). In simple terms, subject to certain parameters, the downstream party is agreeing to be responsible for the upstream parties’ mistakes.
DEFINING INDEMNIFICATION
Insurance brokers focused on development and construction businesses get asked frequently: “If we sign this, are we insured?” It would be great if this could be answered “yes” or “no,” but life is rarely that straightforward. To understand whether a specific indemnification is insurable, we have to drill down on the actual provision. Let’s look at a typical indemnification below:
“To the fullest extent permitted by law the Contractor shall indemnify, defend and hold harmless the owner, architect, architect’s consultants and agents and employees of any of them from and against any claims, damages, losses and expenses, including but not limited to attorneys’ fees, arising out of or resulting from performance of the work whether caused in whole or in part by the contractor, a subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable.”
Reprinted courtesy of
Jeffrey Cavignac, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Awarding Insurer Summary Judgment Before Discovery Completed Reversed
August 29, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida Court of Appeal reversed the trial court's awarding of summary judgment to the insurer because discovery was not completed. Sacramento v. Citizens Prop. Ins. Corp., 2022 Fla. App. LEXIS 4292 (Fla. Ct. App. June 22, 2022).
The insured filed a claim under the all-risk policy for water damage caused by Hurricane Irma. Citizens denied the claim based upon a policy exclusion. The insured filed suit on March 8, 2019.
On April 24, 2020, Citizens moved for summary judgment. A hearing was set for August 10, 2020. Citizens filed a notice for a deposition of a Mitigation Company representative scheduled to occur on December 1, 2020. On August 14, 2020, the insured filed an opposition to the summary judgment motion arguing that it would be premature to grant the motion because there were still pending depositions. The insured specifically requested that the trial court not enter summary judgment until the mitigation company's representative was deposed because he was a key witness who would be testifying regarding the cause of loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Welcome to SubTropolis: The Massive Business Complex Buried Under Kansas City
February 05, 2015 —
Patrick Clark – BloombergThe underground industrial park known as SubTroplis opened for business in 1964 in an excavated mine below Kansas City, Mo., attracting tenants with the lure of lower energy costs and cheap rents. The walls, carved out of 270-million-year-old limestone deposits, help keep humidity low and temperatures at a constant 68 degrees, eliminating the need for air conditioning or heating. Tenants have reported saving as much as 70 percent on their energy bills, says Ora Reynolds, president of SubTropolis landlord Hunt Midwest. Rents run about $2.25 per square foot, about half the going rate on the surface. "It's also a question of sustainability," says Joe Paris, vice president at Paris Brothers, a specialty foods packager that employs about 200 workers underground. In addition to Paris Brothers, 51 tenants have rented nearly 6 million square feet of space. Others include LightEdge Solutions, a cloud computing company that uses the mild climate to help cool servers, and an underground archive that contains the original film reels to Gone with the Wind and Wizard of Oz.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg
Brown and Caldwell Team with AECOM for Landmark Pure Water Southern California Program
May 15, 2023 —
Brown and CaldwellLOS ANGELES, May 09, 2023 — A joint venture of AECOM and Brown and Caldwell (AECOM-BC Team) has been chosen to provide program and project management support and engineering design services for the
Pure Water Southern California program, one of the largest water reuse programs in the world.
The innovative program, being developed by the Metropolitan Water District of Southern California (Metropolitan) in partnership with the Los Angeles County Sanitation Districts (Sanitation Districts), will produce up to 150 million gallons of high-quality, purified water per day for up to 15 million people.
Anticipated for water delivery by 2032 and potentially earlier, the program will reuse the largest untapped wastewater source in the region that currently flows to the ocean to increase water resiliency, enhance water quality, and fuel economic growth. It will lower Southern California’s reliance on imported water supplies from the Colorado River and Sierra Nevada and replenish groundwater basins while leveraging cutting-edge research and development to increase regional water reuse.
About Brown and Caldwell
Headquartered in Walnut Creek, California, Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and over 1,900 professionals across North America and the Pacific. For more than 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients’ expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: NWP 12 and the Dakota Access Pipeline Easement Get Forced Vacations, while a Potential Violation of the Eighth Amendment Isn’t Going Anywhere
August 10, 2020 —
Anthony B. Cavender - Gravel2GavelHere’s a report on several new decisions made over the past few days.
U.S. SUPREME COURT
U.S. Army Corps of Engineers v. Northern Plains Resources Council
On July 8, 2020, the Court has issued a partial stay of the decision of the U.S. District Court for Montana, which had held that the nationwide use by the Corps of Engineers of its Nationwide Permit 12 to permit oil and gas pipelines must be vacated because the Corps, when it reissued these permits in 2012, failed to follow the requirements of the Endangered Species Act. The breadth of this ruling seems to have surprised and alarmed many past and perspective permittees of the Corps. The stay will not apply to the ongoing Ninth Circuit litigation.
FEDERAL COURTS OF APPEAL
Vega, et al. v. Semple (The U.S. Court of Appeals for the Second Circuit)
On June 29, 2020, the court refused to dismiss a putative class action by past and present inmates of Connecticut’s Garner Correctional Institution who alleged that state correctional officials exposed them to excessive amounts of radon gas in violation of the Eighth Amendment. These officials are alleged to have been “deliberately indifferent” to inmate safety. A 1993 Supreme Court decision, Helling v. McKiney, clearly established the law in this area, and the Garner facility opened in 1992. The defense clams of limited immunity as to federal law violations were rejected.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Social Engineering Scams Are On the Rise – Do I Have Insurance Coverage for That?
June 01, 2020 —
Jeffrey Dennis & Heather Whitehead - Newmeyer DillionCyber attackers all know that the majority of organizations are currently working from home due to the ongoing COVID-19 (commonly referred to as the Coronavirus) pandemic. And, as would be expected, social engineering scams are on the rise. Nonetheless, there may be limitations in your cyber liability insurance policy for these types of claims. It is advisable to take the initiative to review such insurance policies in detail for coverage considerations prior to the occurrence of any cyber incident. And, of course, protect your business from attacks by engaging in precautious cyber safety efforts.
What Is Social Engineering?
Social engineering refers to various means to manipulate individuals in the online environment so that they divulge sensitive, personal information, such as banking information, which may include account numbers and passwords. This can also take the form of receiving a request to transfer funds to what the victim believes is another employee, trusted financial information or other party with whom the person has a business relationship with. Unfortunately, however, those funds ultimately are received by the engineer of the cyber attack.
Reprinted courtesy of
Jeffrey M. Dennis, Newmeyer Dillion and
Heather Whitehead, Newmeyer Dillion
Mr. Dennis may be contacted at jeff.dennis@ndlf.com
Ms. Whitehead may be contacted at heather.whitehead@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Force Majeure, Construction Delays, Labor Shortages and COVID-19
April 06, 2020 —
Elizabeth J. Dye - Gravel2Gavel Construction & Real Estate Law BlogThe global effect of the Coronavirus disease (COVID-19) is still unknown, and the progress of many large-scale construction projects has been affected by “Shelter in Place” orders, although some states and localities have classified construction projects as “essential.” Just last Friday, New York shut down all construction, with few exceptions.
Several states have enacted gathering bans of all sizes (including Michigan, Oregon, New Mexico, Washington, New York, New Jersey, Wisconsin, Illinois, Indiana, Ohio, West Virginia, California) and more people are likely to be quarantined as widespread testing becomes available. These decisions will undoubtedly affect the supply of materials and labor necessary for construction projects.
Officials have turned to increasingly disruptive and measures to control the spread of the virus in addition to event prohibitions and school closures, including restricting people to their homes, and closing businesses that are not “essential.” While many companies have adopted mandatory telecommuting, this is an impossibility on the construction sites. Eventually, supply and labor shortages due to governmental restrictions or quarantines will affect the critical path of construction projects.
Read the court decisionRead the full story...Reprinted courtesy of
Elizabeth J. Dye, PillsburyMs. Dye may be contacted at
elizabeth.dye@pillsburylaw.com
“Based On”… What Exactly? NJ Appellate Division Examines Phrase and Estops Insurer From Disclaiming Coverage for 20-Month Delay
August 20, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPOn May 28, 2019, the New Jersey Superior Court, Appellate Division examined the phrase “based on” in an assault-and-battery exclusion, finding that the phrase means “to make, form, or serve as the foundation of any claim, demand or suit.” C.M.S. Investment Ventures, Inc. v. American European Insurance Company, No. A-2056-17T3, 2019 N.J. Super. Unpub. LEXIS 1215, at *8-9 (N.J. Super. Ct. App. Div. May 28, 2019) (CMS). The CMS case is also notable because the Appellate Division held that a 20-month delay in disclaiming coverage was unreasonable and therefore warranted estoppel.
In CMS, the insured was allegedly warned by its tenant about a faulty ground-floor window that failed to lock properly. Afterward, an intruder broke into the tenant’s apartment and sexually assaulted the tenant, who sued the insured on a premises liability claim. Before she filed suit, the tenant sought payment from the insured’s CGL insurer directly. The insurer denied coverage based on the assault-and-battery exclusion and closed the file, but never informed the insured. Later, the tenant sued the insured, which sought a defense and indemnity from its insurer, which again denied coverage based on the exclusion. The insured then sought a declaration of coverage on grounds that the exclusion was ambiguous, and the insurer “was estopped from denying coverage, because it waited [20] months to inform CMS of its coverage decision.” The trial court ruled in the insured’s favor which led to the appeal in CMS.
Reprinted courtesy of
Timothy Carroll, White and Williams LLP and
Anthony Miscioscia, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of