Third Circuit Limits Pennsylvania’s Kvaerner Decision; Unexpected and Unintended Injury May Constitute an “Occurrence” Under Pennsylvania Law
December 22, 2019 —
Michael S. Levine & Michelle M. Spatz - Hunton Insurance Recovery BlogThe Third Circuit ruled on Friday that differing “occurrence” definitions can have materially different meanings in the context of whether product defect claims constitute an “occurrence” triggering coverage under general liability insurance policies. The Court held in Sapa Extrusions, Inc. v. Liberty Mutual Insurance Company, that product claims against Sapa may be covered under policies that define an “occurrence” as an accident resulting in bodily injury or property damage “neither expected nor intended from the standpoint of the insured.” However, the Court affirmed that coverage was not triggered under policies lacking the “expected” or “intended” limitation, reasoning that, under those policies, there was no question that the intentional manufacturing of Sapa’s product was too foreseeable to amount to an “accident.”
The coverage dispute arose from an underlying action in which Marvin, a window manufacturer, alleged that, between 2000 and 2010, Sapa sold it roughly 28 million defective aluminum window extrusions. Marvin alleged that the extrusions, which are metal frames that hold glass window panes in place, began to oxidize and break down shortly after they were installed, causing Marvin to incur substantial costs to fix and replace them.
Marvin sued Sapa in 2010 in Minnesota federal court, and the parties settled in 2013. Sapa sought coverage for the settlement from its eight general liability insurers for the period implicated by Marvin’s allegations. The insurers denied coverage and Sapa brought suit in the Middle District of Pennsylvania.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Michelle M. Spatz, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Spatz may be contacted at mspatz@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Mortenson Subcontractor Fires Worker Over Meta Data Center Noose
April 19, 2022 —
James Leggate - Engineering News-RecordA worker on a data center project for Facebook parent company Meta in Utah was fired after admitting to tying a noose at the worksite where racist graffiti had also been found months earlier.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Relief Bill's Highway Funds Could Help Construction Projects
January 04, 2021 —
Tom Ichniowski - Engineering News-RecordAmong the many provisions in the coronavirus relief bill, one key item is $10 billion to help state highway agencies make up for losses in state fuel taxes and other revenue due to the pandemic-caused falloff in traffic this year. Construction is one of a list of several eligible uses for the money—one of only a few construction funding provisions in the relief measure.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Real Estate Developer Convicted in $1.3 Billion Tax Case After Juror Removed
October 17, 2023 —
David Voreacos - BloombergA real estate developer was convicted for promoting $1.3 billion in fraudulent tax deductions after a judge removed a deliberating juror who told the judge she was “standing up for White people.”
Jack Fisher was found guilty Friday in Atlanta federal court of selling tax deductions to wealthy individuals using so-called syndicated conservation easements, which offer tax breaks for the promise to avoid developing land. Prosecutors said Fisher relied on exaggerated appraisals and backdated documents in the scheme, which earned him tens of millions of dollars.
Jurors also convicted a lawyer who worked with Fisher, James Sinnott. Attorneys for Fisher and Sinnott didn’t immediately respond to a request for comment.
The nine-week trial nearly came undone by conflicts over race and class within the jury, which began deliberating on Sept. 14. Last week, jurors told US District Judge Timothy Batten they were “hopelessly hung.” Jurors also complained that Juror 26, a White woman, refused to deliberate.
Read the court decisionRead the full story...Reprinted courtesy of
David Voreacos, Bloomberg
Cybersecurity on Your Project: Why Not Follow National Security Strategy?
August 28, 2018 —
Rick Erickson - Snell & Wilmer Real Estate Litigation BlogIn its recent Cybersecurity Strategy, the U.S. Department of Homeland Security (DHS) defined “cyberspace” as “the independent network of information technology infrastructure, including the Internet, telecommunications networks, computers, information and communications systems, and embedded processors and controllers.” To DHS, protecting cyberspace includes threats against “federal and nonfederal information systems.” In other words, both private and public interests are at risk. In his 2018 National Defense Strategy, U.S. Department of Defense Secretary, Jim Mattis, essentially concurred in declaring cyberspace a “warfighting domain” and promising to “invest in cyber defense, resilience, and the continued integration of cyber capabilities into the full spectrum of military operations.”
The construction industry is a key player in cybersecurity because contractors, designers and owners are responsible for building and delivering projects providing critical public services like national defense, health care, law enforcement, transportation, and utilities. Like any business reckoning with risks in cyberspace, moreover, everyone on a construction project has valuable data and confidentialities to protect. Cyber breaches on a project may also compromise electrical power, physical safety and, inevitably, a lot more than the critical path schedule and profit margins. Cybersecurity insurance is not very affordable or comprehensive, either, and it usually excludes any property damage or bodily injury resulting from a cyber event.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Erickson, Snell & WilmerMr. Erickson may be contacted at
rerickson@swlaw.com
Nationwide Immigrant Strike May Trigger Excusable Delay and Other Contract Provisions
February 23, 2017 —
Adam P. Handfinger & Meredith N. Reynolds – Peckar & Abramson, P.C.Yesterday, February 16, 2017, media outlets reported a nationwide strike by immigrants and
businesses referred to as “A Day Without Immigrants”. The protest, organized largely through
social media, was a response by some to the Trump Administration’s immigration and foreign
trade policies. Participating businesses shut down and immigrants refused to work or spend
money in an eff ort to demonstrate the role of foreign-born workers in the U.S. economy.
While the number of businesses and individuals that participated is not yet known, several
contractors reported labor shortages and construction project delays or temporary shut
downs as a result of the protest.
Reprinted courtesy of
Adam P. Handfinger, Peckar & Abramson, P.C. and
Meredith N. Reynolds, Peckar & Abramson, P.C.
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Ms. Reynolds may be contacted at mreynolds@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Colorado Supreme Court affirms Woodbridge II’s “Adverse Use” Distinction
December 20, 2021 —
Luke Mecklenburg - Snell & Wilmer Real Estate Litigation BlogLast year, I posted regarding the Colorado Court of Appeals’ decision in Woodbridge II, which concluded that the “adverse use” element for prescriptive easement claims only requires the claimant to “show a nonpermissive or otherwise unauthorized use of property that interfered with the owner’s property interests.” Viento Blanco, LLC, 2020 COA 34 (Woodbridge II), ¶ 2. Thus, Woodbridge II concluded, the claimants acknowledgement or recognition of an owner’s title alone is insufficient to defeat “adverse use” in the prescriptive easement context. Id. That decision was up for review by the Colorado Supreme Court at the time of my prior post. It has now been affirmed, thereby settling an arguable appellate decision split created by Woodbridge II. See Lo Viento Blanco, LLC v. Woodbridge Condo. Ass’n, Inc., 2021 CO 56 (“Woodbridge”).
“Like the division below, and for much the same reasons,” the Colorado Supreme Court affirmed in Woodbridge “that under Colorado law, a claimant’s acknowledgement or recognition of the owner’s title during the claimant’s asserted prescriptive period does not interrupt the prescriptive use or undermine the claimant’s adverse use.” Woodbridge, ¶ 2. Writing for a unanimous court, Justice Gabriel’s opinion agreed with the Court of Appeals’ reasoning “that although Woodbridge recognized that it did not hold title, no evidence indicated that it had acted in subordination to the owner’s title.” Id. ¶ at 13. The Court further agreed with Woodbridge II’srejection of Lo Viento’s “permissive use” argument because “the permission offered … was conditional and Woodbridge never agreed to any of the conditions set forth therein.” Id. On that basis, Woodbridge confirmed that “a claimant seeking to establish a prescriptive easement need not show that it asserted exclusive ownership of the property during the prescriptive period,” but only “that its use was without permission or otherwise unauthorized and that it interfered with the owner’s property interests.” Id. at ¶ 23.
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & WilmerMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
Bankrupt Canada Contractor Execs Ordered to Repay $26 Million
April 25, 2022 —
Scott Van Voorhis - Engineering News-RecordJohn Aquino, the former president of a major and now bankrupt Ontario construction contractor, plans to appeal a provincial court ruling that puts him and his associates on the hook for $26.2 million drained from the company, according to his attorney.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com