Rising Construction Disputes Require Improved Legal Finance
November 15, 2022 —
Apoorva Patel - Construction ExecutiveConstruction disputes are famously high stakes, and the industry is currently experiencing an uptick in the value and number of disputes resulting from contractual obligations and third-party or force majeure incidents. While this is not entirely surprising given COVID-19’s disruption of global markets and supply chains, the numbers are noteworthy.
For example, in 2020 alone, the International Chamber of Commerce (ICC)—the leading institution for construction disputes, partly because its clauses feature in many FIDIC standard form contracts—registered 194 construction arbitrations, and construction disputes now comprise over 20% of the ICC caseload.
In addition to the damage to business outcomes that the underlying disputes may present, parties can quickly spend many millions on legal fees and expenses, as well as technical experts and consultants, if and when those disputes progress through the courts or arbitration. According to Norton Rose’s 2020 Global Construction Disputes Report, the average construction dispute value rose sharply from $30.7 million in 2019 to $54.26 million in 2020.
Reprinted courtesy of
Apoorva Patel, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Harmon Towers Demolition Still Uncertain
January 23, 2013 —
CDJ STAFFIt would be a "gift" to MGM Resorts if they were able to tear down the Harmon Tower, according to an article in the New York Times, as analysts are cited that a hotel would "struggle during this economic downturn." Further, William Robinson, a professor of economics at the University of Nevada, Las Vegas, noted that "MGM has tried to cut back on the whole project," adding that "if you are a conspiracy theorist, you thin they are just looking for a way to get out of it." Professor Robinson thinks they would be unlikely to rebuild if allowed to tear down the building.
MGM Resorts has a different take on the matter. Alan M. Feldman, MGM's senior vice president for public affairs, told the New York Times that MGM "had a contract with Perini that we would pay them to give us a certain kind of building type — in this case a luxury hotel." Mr. Feldman contends that Perini had not "kept up their part of the bargain." Perini has stated that the fault was due to the designers and did not comment to the Times.
The claims of design and construction defects have left the building unfinished, with only twenty-six of the planned forty-nine floors constructed. Perini contends the building can still be repaired. MGM that its remediation plan is "to take the building down."
Read the court decisionRead the full story...Reprinted courtesy of
Defective Stairways can be considered a Patent Construction Defect in California
September 24, 2014 —
William M. Kaufman – Construction Lawyers BlogStairs are not safe! At least the Court of Appeal in the Second Appellate District of California doesn’t think so.
A rail station in Los Angeles was completed by the Los Angeles County Metropolitan Transportation Authority (“MTA”) in 1993. The rail station was part of the development of the Southern California Rapid Transit District Metro Rail Project. In 2011, the plaintiff fell on a stairway at the station. In August 2012, Plaintiff sued the MTA for dangerous condition of public property, statutory liability, and negligence. Among other defects, plaintiff alleged the banister of the stairwell was “too low” and the stairwell “too small” given the number, age, and volume of people habitually entering and exiting the rail station. In addition, plaintiff alleged that MTA “failed to provide adequate safeguards against the known dangerous condition by, among other acts and omissions, failing to properly design, construct, supervise, inspect and repair the Premises causing the same to be unsafe and defective for its intended purposes.” MTA, in turn, cross-complained against Hampton- the entity that provided design and construction services at the station.
Hampton demurred to the first amended cross-complaint, asserting a four year statute of limitations defense pursuant to California Code of Civil Procedure section 337.1, claiming the alleged deficiencies were patent defects. On September 11, 2013, the trial court overruled the demurrer finding that the defect was not patent. Hampton appealed.
The appellate court overruled the trial court’s ruling and in fact, granted Hampton’s writ of mandate and even directed the trial court to sustain the demurrer without leave to amend! (Delon Hampton & Associates v. Sup. Ct. (Los Angeles County Metropolitan Transportation Authority) (Cal. App. Second Dist., Div. 3; June 23, 2014) 227 Cal.App.4th 250, [173 Cal.Rptr.3d 407].)
The appellate court found that the purpose of section 337.1 is to “provide a final point of termination, to proctect some groups from extended liability.” A “patent deficiency” has been defined as a deficiency which is apparent by reasonable inspection. See Tomko Woll Group Architects, Inc. v. Superior Court (1996) 46 Cal.App.4th 1326, 1336. The court found a patent defect can be discovery by the kind of inspection made in the exercise of ordinary care and prudence, whereas a latent defect is hidden and would not be discovered by a reasonably careful inspection. See Preston v. Goldman (1986) 42 Cal.3d 108, 123. The test to determine whether a construction defect is patent is an objective test that asks “whether the average consumer, during the course of a reasonable inspection, would discover the defect…” See Creekbridge Townhome Owners Assn., Inc. v. C. Scott Whitten, Inc. (2009) 177 Cal.App.4th 251, 256.
Mr. Kaufman may be contacted at wkaufman@lockhartpark.com, and you may visit the firm's website at www.lockhartpark.com
Read the court decisionRead the full story...Reprinted courtesy of
William M. Kaufman, Lockhart Park LP
National Engineering and Public Works Roadshow Highlights Low Battery Seawall Restoration Project in Charleston
April 29, 2024 —
Engineering and Public Works RoadshowCHARLESTON, SC — On Thursday, the nationwide Engineering and Public Works Roadshow stopped at the Low Battery Seawall Restoration Project in Charleston. The event highlighted the role engineers and public works professionals play in infrastructure projects like the local seawall improvements that increase coastal resiliency along the historic urban shoreline.
The event, which took place along the newly constructed battery wall section between King Street and Battery Place along Murray Boulevard, marked the latest stop of the Engineering and Public Works Roadshow – a joint effort by the American Council of Engineering Companies, the American Public Works Association, and the American Society of Civil Engineers to bring public attention to the essential role engineers and public works professionals play in making our modern world possible.
The battery project underscores the importance of innovative engineering solutions in addressing the challenges of climate change and rising sea levels. Thursday's event was also a chance to spotlight the engineering, construction, and public officials involved in the project, whose work often goes unrecognized.
About the Engineering and Public Works Roadshow: The Engineering and Public Works Roadshow is a series of nationwide events highlighting critical infrastructure projects and the skilled professionals who make them possible. It is an opportunity to learn about the importance of infrastructure investment, showcase the work of engineers and public works professionals, and celebrate these projects' positive impact on our communities. Learn more at www.infrastructureroadshow.org.
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.
April 28, 2011 —
Beverley BevenFlorez CDJ STAFFIn the construction defect suit Kikirov v. 355 Realty Associates, LLC, et al., the Supreme Court of the State of New York granted a dismissal of the plaintiff’s fourth cause of action, but denied the defendants’ motion in all other respects. The plaintiff alleged breach of contract, among other claims. “355 Realty was the sponsor of 355 Kings Highway Condominium, a condominium project located at 355 Kings Highway, in Brooklyn, New York. The condominium units were allegedly marketed as ‘ultra luxury condos,’ and a ‘Manhattan style condominium building,’ which would be the ‘epitome of luxury and quality.’ The construction of the six-story 28 unit residential condominium building began in approximately November 2003. […] Plaintiff entered into a purchase agreement, dated December 21, 2005, with 355 Realty (which was executed on behalf of 355 Realty by Michael Marino, as its member) for the purchase of Unit 2G in the building.”
The plaintiff alleged that construction defects emerged soon after moving into the unit: “After taking occupancy of his condominium unit, plaintiff allegedly experienced serious leakage and moisture problems in his unit, which caused a dangerous mold condition to develop, in addition to causing actual damage to the structural elements of his unit. According to plaintiff, the walls, moldings, and wood floors of his unit are constantly wet and moist, and there is severe buckling of the wood floors. Plaintiff claims that these problems have caused his unit to be uninhabitable. Plaintiff alleges that he has been forced to remove all of his personal belongings from his unit and has been unable to occupy his unit.”
According to the plaintiff, Foremost attempted to repair the defects, but only made the situation worse: “Specifically, plaintiff asserts that Foremost’s contractors opened his walls to remove the stained drywall, but never corrected the cause of the leaks, destroyed the walls, and never properly taped and painted the sheet rock. Plaintiff alleges that Foremost repaired the openings in a defective manner. Plaintiff also claims that his floor was repaired at that time by a subcontractor hired by Foremost, but the basic structural problem was never resolved and the leaks continued, compromising the beams and causing the mold conditions, in addition to all of the physical damage present in the unit. On or about July 16, 2009, plaintiff allegedly sent a notice of the defects to 355 Realty and to the managing agent designated by the condominium board, by certified mail, return receipt requested. Plaintiff asserts that defendants have failed and refused to repair and remedy the defective condition, and that the damage is extensive and requires major structural repairs.”
The plaintiff filed suit on May 4, 2010, and the original complaint asserted eight causes of action. “By decision and order dated September 13, 2010, the court granted a motion by defendants to dismiss plaintiff’s second cause of action for breach of implied covenants of good faith and fair dealing, his third cause of action for breach of implied warranties, his fifth cause of action for negligence as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his seventh cause of action for negligence as against Vision, Foremost, and MMJ, and his eighth cause of action for violations of General Business Law § 349 and § 350, and granted plaintiff leave to replead his first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his fourth cause of action for breach of statutory warranties, and his sixth cause of action for breach of contract as against Vision, Foremost, and MMJ.”
The plaintiff amended their complaint on October 18, 2010, and “has repleaded these three causes of action by asserting a first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, a second cause of action for breach of statutory warranties, and a third cause of action for breach of contract as against Vision, Foremost, and MMJ. In addition, plaintiff, in his amended complaint, has added a fourth cause of action for fraud.”
The defendants, on the other hand, “argue that each of the four causes of action alleged by plaintiff in his amended complaint fail to state a claim upon which relief may be granted, and that plaintiff’s amended complaint must be dismissed pursuant to CPLR 3211 (a) (7). Defendants also cite to CPLR 3211 (a) (1), and (5), asserting that dismissal is also required based upon documentary evidence and the Statute of Limitations contained in the limited warranty.”The defendants’ motion to dismiss the first cause of action, breach of contract against 355 Realty, was denied: “While defendants dispute that the alleged defects are actually structural in nature, plaintiff’s allegations as to their structural nature are sufficient, at this juncture, to withstand defendants’ motion to dismiss. Thus, dismissal of plaintiff’s first cause of action must be denied.”
Next, the court reviewed the second cause of action, which was breach of statutory warranties: “Defendants’ motion also seeks dismissal of plaintiff’s second cause of action for breach of statutory warranties, which alleges that, under applicable law, including General Business Law § 777-a, et seq., the sponsor warranted to purchasers of units that the units would be constructed in a skillful, careful, and workmanlike manner, consistent with proper design, engineering, and construction standards and practices, and free of material latent, design, and structural defects. Defendants argue that General Business Law § 777-a, known as the housing merchant implied warranty, is inapplicable to this case because it is limited to the construction of a ‘new home,’ defined in General Business Law § 777 (5) as ‘any single family house or for-sale unit in a multi-unit residential structure of five stories or less.’ As noted above, the building in which plaintiff’s condominium unit is located is a six-story building.”
The motion to dismiss the second cause of action is denied. The court provided this reasoning: “the full text of the offering plan has not been provided, the court is unable to examine the entire written agreement so as to determine the purpose of the inclusion of the text of General Business Law § 777.”
In the third cause of action, the plaintiff alleges “a breach of contract claim as against Vision, Foremost, and MMJ based upon their contract with 355 Realty, pursuant to which they agreed to be the general contractors/construction managers for the condominium, to undertake oversight responsibility for the design and construction of the condominium, to prepare and/or review drawings, plans, and specifications for the condominium, and to otherwise manage and oversee the project. Plaintiff alleges that Vision, Foremost, and MMJ breached their contractual obligations in that the condominium units were improperly and inadequately designed and constructed, and completed in an incompetent and unworkmanlike manner, with material design and construction defects.”
The motion to dismiss the third cause of action was denied as well: “Plaintiff alleges, in his amended complaint, that Vision, Foremost, and MMJ have acknowledged notice of the defects and have not denied that they are responsible for providing a warranty to plaintiff. Plaintiff also refers to this warranty, in his amended complaint, by noting that paragraph 16 of the purchase agreement stated that the ‘[s]eller shall not be liable to . . . the [p]urchaser for any matter as to which an assignable warranty . . . has been assigned . . . to [p]urchaser and in such case the sole recourse of such . . . [p]urchaser . . . shall be against the warrantor . . . except that in the event a contractor or subcontractor is financially unable or refuses to perform its warranty . . . [s]eller shall not be excused from its obligations enumerated in the [offering p]lan under Rights and Obligations of Sponsor.’ Consequently, the court finds that dismissal of plaintiff’s third cause of action as against Foremost and MMJ must also be denied.”
In the fourth cause of action, the plaintiff alleges “that defendants made false statements and representations orally, in advertisements, and in the purchase agreement, that the condominium was properly and adequately designed and constructed and completed in a competent and workmanlike manner, in accordance with the condominium plans and specifications and proper design, engineering, and construction standards and practices consistent with applicable standards for a first class, luxury condominium in Brooklyn.”
The court dismissed the fourth cause of action stating, “it must be dismissed because it is duplicative of his first cause of action for breach of contract.” Therefore, “defendants’ motion to dismiss plaintiff’s amended complaint is granted to the extent that it seeks dismissal of plaintiff’s fourth cause of action, and it is denied in all other respects.”
Read the court’s decision… Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Denial of Coverage to Additional Insured Constitutes Bad Faith
May 21, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe insurer's unreasonable denial of a defense and indemnity to a lessor/additional insured was found to be in bad faith. Seaway Props. v. Fireman's Fund Ins. Co., 2014 U.S. Dist. LEXIS 55998 (W.D. Wash. April 22, 2014).
Seaway leased restaurant space to Ciao Bella Food, LLC. In January 10, 2010, the underlying plaintiff was on her way to the restaurant when she attempted to step down from a concrete platform between the building parking lot and the entrance to the restaurant. Seaway's lease gave Ciao Bella the right to use the common areas, including the parking lot, but did not grant Ciao Bella exclusive control over the common areas. The plaintiff suffered injuries and claimed both Ciao Bella and Seaway were liable.
Seaway's lease required Ciao Bella to maintain a CGL policy and to name Seaway as an additional insured. Ciao Bella did so by securing a policy with Fireman's Fund. Fireman's Fund had notice of the plaintiff's claim by November 2010. Seaway demanded in March 2012 that Fireman's Fund indemnify and defend it. In September 2012, two years after it first learned of the plaintiff's injury, Fireman's Fund denied coverage, asserting that Seaway was not an insured under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Texas Central Wins Authority to Take Land for High-Speed Rail System
October 03, 2022 —
Barclay Nicholson & Erica Gibbons - Sheppard Mullin Construction & Infrastructure Law BlogMove over luxury bus lines and quick flights. Central Texans should be on the lookout for bulldozers and train stops. On June 24, 2022, the Supreme Court of Texas held that Texas Central Railroad & Infrastructure, Inc. and related entities (collectively “Texas Central”) have eminent domain authority to acquire property for a proposed high-speed rail system between Dallas and Houston.
[1] Specifically, the Court held that the corporation qualifies as an “interurban electric railway company” under the Texas Transportation Code. This ruling grants Texas Central the broad condemnation authority to procure land for the project.
Texas Central has Statutory Authority to Take Land
The plaintiff in the matter, a farm owner with property south of Dallas along the proposed path of the bullet train, challenged the companies power to condemn land. The landowner’s declaratory judgment action challenged Texas Central’s eminent-domain authority. Under Texas law, condemnation power must be conferred by the legislature, either expressly or by necessary implication.
[2]
Here, Texas Central was created for the purpose of constructing, acquiring, maintaining, or operating lines of electric railway between Texas municipalities. The Court found that Texas Central is engaged in activities to further that purpose. Therefore, the Court concluded, that although legislators did not contemplate high-speed railways at the time of drafting the Transportation Code, Texas Central nonetheless qualified as “interurban electric railway companies” under the statute.
Reprinted courtesy of
Barclay Nicholson, Sheppard Mullin and
Erica Gibbons, Sheppard Mullin
Mr. Nicholson may be contacted at bnicholson@sheppardmullin.com
Ms. Gibbons may be contacted at egibbons@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Pang Elected Vice President of APABA-PA Board of Directors
December 21, 2016 —
White and Williams LLPMelissa Pang has been elected Vice President of the Asian Pacific American Bar Association of Pennsylvania's (APABA-PA) Board of Directors. She will serve a one-year term in the position, beginning January 1, 2017. As part of her responsibilities, Melissa will co-chair the National Asian Pacific American Bar Association Northeast Regional Conference, which will be hosted by the APABA-PA in Philadelphia.
Melissa has been a member of the APABA-PA since 2010 and has served on the board since 2015. Her involvement includes participation on the Law Student Outreach Committee as well as the Annual Banquet Committee. In 2016, she chaired the organization's Lunar Banquet.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Pang, White and Williams LLPMs. Pang may be contacted at
pangm@whiteandwilliams.com