Cameron Sheldon - Ahlers Cressman & Sleight PLLCIn March 2022, the Washington State Court of Appeals, Division One, issued Marpac Constr., LLC v. Dep’t of Lab. & Indus., No. 82200-4-I, 2022 WL 896850, at *1 (Wash. Ct. App. Mar. 28, 2022) holding Marpac Construction, LLC (“Marpac”) liable for three willful Washington Industrial Safety and Health Act of 1973 (WISHA) violations pertaining to safe crane operation near energized power lines.
Marpac was the general contractor on an apartment complex construction project in West Seattle. The worksite had high voltage power lines running throughout the site. Seattle City Light had flagged some with a 10-foot offset, but none of the other power lines were flagged. Marpac’s superintendent assumed that the lines were between 26 kilovolts (kV) and 50 kV based on their connection to the lines flagged by Seattle City Light. The superintendent never called Seattle City Light to check the voltage of the lines and the lines remained above ground.
In September 2016, a subcontractor began work on the project’s structural foundation. The subcontractor expressed concerns about working around the power lines, but Marpac promised it was working on mitigation of the power line hazard and directed the subcontractor continue working. At one point, the subcontractor’s employees had to move the crane and concrete forms away from the power lines to allow a cement truck to park in its place. The crane’s line contacted the power lines, causing serious injuries to two of the subcontractor’s employees.
Read the court decisionRead the full story...Reprinted courtesy of
Cameron Sheldon, Ahlers Cressman & Sleight PLLCMs. Sheldon may be contacted at
cameron.sheldon@acslawyers.com
Colorado House Bill 17-1279 – A Misguided Attempt at Construction Defect Reform
March 29, 2017 —
David McClain - Colorado Construction LitigationOn March 17th, House Bill 17-1279, concerning the requirement that a unit owners’ association obtain approval through a vote of unit owners before filing a construction defect action, was introduced and assigned to the House State, Veterans, and Military Affairs Committee. The bill is currently scheduled for its first committee hearing on March 29th, at 1:30 in the afternoon. While, on its face, this appears to be a step in the right direction towards instituting “informed consent” before an HOA can file a construction defect action, the bill actually restricts the ability of developer to include more stringent requirements in the declaration of covenants, conditions, and restrictions for an association, thereby lowing the threshold of “consent” required to institute an action.
House Bill 17-1279 would amend C.R.S. § 38-33.3-303.5 to require an association’s executive board to mail or deliver written notice of the anticipated commencement of a construction defect action to each unit owner and to call a meeting of the unit owners to consider whether to bring such an action. Any construction professional against which a claim may attend the unit owners’ meeting and have an opportunity to address the unit owners and may include an offer to remedy any defect in accordance with C.R.S. § 13-20-803.5(3). The conclusion of the meeting would initiate a 120-day voting period, during which period the running of any applicable statutes of limitation or repose would be tolled. Pursuant to this bill, an executive board may only institute a construction defect action only if authorized by a simple majority of the unit owners, not including: 1) any unit owned by any construction professional, or affiliate of a construction professional, involved in the design, construction, or repair of any portion of the project; 2) any unit owned by a banking institution; 3) any unit owned in which no defects are alleged to exist, and/or 4) any unit owned by an individual deemed “nonresponsive.”
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
New York Federal Court Enforces Construction Exclusion, Rejects Reimbursement Claim
August 03, 2020 —
Eric D. Suben - Traub LiebermanIn Crescent Beach Club, LLC v. Indian Harbor Insurance Company, 2020 WL 3414697 (E.D.N.Y. June 22, 2020), the district court considered application of a CGL policy issued to a property owner containing the following exclusion:
"This policy does not apply to any ‘bodily injury’, ‘property damage’, ‘personal and advertising injury’, or any other loss, cost, defense fee, expense, injury, damage, claim, dispute or ‘suit’ either arising out of, or related to, any construction, renovation, rehabilitation, demolition, erection, excavation or remedition [sic] of any building and includes planning, site preparation, surveying or other other [sic] construction or development of real property. This exclusion, however, shall not apply to routine maintenance activities."
Plaintiff in the underlying action alleged injury while engaged in construction work at the insured’s premises. The information the insurer received was conflicting as to whether plaintiff was demolishing a pergola (excluded) or merely removing vines (not excluded). The insurer reserved its rights accordingly.
At his deposition in the underlying action, the plaintiff testified he was in a manlift performing demolition at the time he was injured. The insured’s property manager also testified that the pergola was being demolished. Approximately one month after the depositions, the insurer denied coverage based on the exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
Eric D. Suben, Traub LiebermanMr. Suben may be contacted at
esuben@tlsslaw.com
Real Estate & Construction News Roundup (05/10/23) – Wobbling Real Estate, Booming (and Busting) Construction, and Eye-Watering Insurance Premiums
May 22, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, the commercial real estate sector continues to wobble, construction booms and busts, flood insurance premiums reach eye-watering levels, and more.
- In its latest Financial Stability report, the Federal Reserve acknowledges that the shaky commercial real estate sector could potentially harm the U.S. financial system. (Courtenay Brown, Axios)
- New data from the California Department of Finance shows that even though the state’s population significantly decreased during the COVID-19 pandemic, home building soared, reaching levels not seen since 2008. (Terry Castleman, Los Angeles Times)
- Already weakened by rising interest rates, inflation and debt, Sweden’s real estate sector took another hit as SBB’s shares continued to slump. (Reuters)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Burg Simpson to Create Construction Defect Group
November 06, 2013 —
CDJ STAFFBurg Simpson Eldredge Hersh & Jardine, P.C. has announced that the attorneys of Sullan2, Sandgrund, Perczak & Nuss, P.C. will be joining them as S2SPN Construction Defect Group of Berg Simpson. The group will be headquartered at Burg Simpson’s Engelwood offices.
The combined firms will comprise 55 attorneys. Michael Burg, founding shareholder at Burg Simpson, said that “in Colorado for the past 29 years, these lawyers have provided the highest level of construction defect representation.” His counterpart, Scott Sullan of Sullan2, Sandgrund, Perczak & Nuss said that he and his colleagues are “delighted to be a part of the Burg Simpson team.” The two firms join forces effective January 1, 2014.
Read the court decisionRead the full story...Reprinted courtesy of
Preparing Your Business For Internal Transition
October 14, 2019 —
Stephen P. Katz, Esq. - ConsensusDocsWhen is it right to start thinking about succession planning and preparing a construction company for transition? Many would agree – in concept, at least – that serious thought regarding succession and transition planning should begin at a company’s inception and be revisited throughout its lifecycle, but as a practical matter, it is frequently not part of the mindset when growing a business. This article explores issues that construction company owners should consider in order to achieve smooth transition of ownership and control. We will address three critical questions:
- What happens to the business when an owner retires;
- In the event an owner(s) become disabled; and,
- Unplanned exit/owner pre-deceases her/his exit from the company
Owners who do not plan carefully for transition are often faced with the less than appealing option of liquidating their business for much less than its value, or by closing the business with no return upon that event. However, those who plan carefully can realize the value of their life’s work, pass the business to the next generation and see their legacy continue.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen P. Katz, Esq., Peckar & Abramson, P.C.Mr. Katz may be contacted at
skatz@pecklaw.com
2017 Legislative Changes Affecting the Construction Industry
November 21, 2017 —
Melinda S. Gentile – Peckar & Abramson, P.C.Originally published by CDJ on July 13, 2017
The 2017 Florida Legislative Session recently concluded, and a number of important construction-related House Bills (HB) and Senate Bills (SB) were presented during the Session, most notably SB 204/HB 377. These Bills may impact General Contractors and Construction Managers in a number of ways, not the least of which is the period of time that a cause of action may be initiated for the design, planning or construction of an improvement.
The following construction-related Bills passed in both the House and Senate and will become law if approved by the Governor.
Senate Bill (SB) 204/House Bill (HB) 377: Relating to the Statute of Repose for causes of action based on design, planning or construction of an improvement to real property. This bill passed both the House and the Senate and was approved by the Governor on June 14, 2017. This bill becomes effective on July 1, 2017.
Read the court decisionRead the full story...Reprinted courtesy of
Melinda S. Gentile, Peckar & Abramson, P.C.Ms. Gentile may be contacted at
mgentile@pecklaw.com
California’s Skilled and Trained Workforce Requirements: Public Works and AB 3018, What You Need to Know
December 09, 2019 —
Brenda Radmacher & Nicholas Krebs - Gordon & Rees Construction Law BlogDo you have the proper skilled and trained workforce for your construction projects? If you take on public works projects in California, you may not be in compliance with the new changes in the law. To avoid civil penalties or nonpayment and potentially being precluded from future bids on public works contracts, you must critically review your team and proposal prior to accepting an award. Once awarded a public contact requiring a skilled and trained workforce, diligent reporting practices and oversight are required to maintain compliance.
Compliance with California’s skilled and trained workforce requirements for contractors, engineers, architects, design professionals, and suppliers competing for public works construction projects in California is mandated through enforcement with the enactment of AB 3018. Signed by Governor Brown in his last legislative session, AB 3018 dramatically increased the penalties for non-compliance with the existing skilled and trained workforce requirements in California. The new penalties include civil fines by the Labor Commissioner up to $10,000 per month per non-compliant contractor, disqualification from bidding on future public works contract, and withholding of payment for delinquent contractors. This update provides information on California’s skilled and trained workforce requirements, identifies key issues on compliance to avoid penalties, and discusses the impact of enforcement on construction professionals’ business practices.
Reprinted courtesy of
Brenda Radmacher, Gordon & Rees Scully Mansukhani and
Nicholas Krebs, Gordon & Rees Scully Mansukhani
Ms. Radmacher may be contacted at bradmacher@grsm.com
Mr. Krebs may be contacted at nkrebs@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of