Construction Law Alert: Builder’s Alternative Pre-litigation Procedures Upheld Over Strong Opposition
April 01, 2014 —
Steven M. Cvitanovic and Whitney L. Stefko - Haight Brown & Bonesteel, LLPLast week, the Court of Appeal, Fifth Appellate District, was tasked with evaluating the enforceability of provisions in home purchase contracts containing alternative pre-litigation procedures which differ from the standard Right to Repair Act procedures. The Court of Appeal, in McCaffrey v. Superior Court of Fresno, et al. ultimately upheld the contractual provisions, and in overturning the trial court's decision, preserved the rights of builders to contract around certain requirements set forth in the Right to Repair Act.
The McCaffrey Group, Inc. constructed single-family homes in a Fresno development. Plaintiffs consisted of 24 homeowners within the development who brought suit against McCaffrey for construction defects in their homes. The homeowners were comprised of three categories: (1) the original purchasers who bought their homes from McCaffrey before January 1, 2003 and had a 2001 version of McCaffrey's contract; (2) the original purchasers who bought their homes from McCaffrey on or after January 1, 2003 and signed a 2003 version of McCaffrey's contract; and (3) the subsequent purchasers who did not buy their homes directly from McCaffrey, but purchased their homes subject to either the 2001 or 2003 version of McCaffrey's home purchase agreement.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Massachusetts Business Court Addresses Defense Cost Allocation and Non-Cumulation Provisions in Long-Tail Context
March 06, 2022 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsA business court in Massachusetts has weighed in on two key issues affecting allocation of insurance coverage for long-tail liabilities in Massachusetts. Specifically, in Crosby Valve LLC et al. v. OneBeacon America Insurance Company, et al.,
[1] involving asbestos bodily injury claims, Judge Kenneth Salinger of the Suffolk County Business Litigation Session addressed:
- whether defense costs in long-tail cases were subject to the same pro rata allocation scheme the Supreme Judicial Court (SJC) adopted to govern successively triggered insurers' indemnity obligations in Boston Gas Company v. Century Indemnity Company;[2] and
- whether “non-cumulation” provisions, like those addressed by the New York Court of Appeals in Matter of Viking Pump,[3] were consistent with this pro rata allocation methodology.
As to the first issue — i.e., allocation of defense costs — Judge Salinger declined to follow Boston Gas, and found the SJC’s holding in that case was limited to an insurers’ indemnity obligations. The SJC in Boston Gas had focused on the language of the policy insuring agreement, saying “[t]his policy applies to ... property damage ... which occurs anywhere during the policy period.” The SJC had also pointed to the policy definition of “occurrence” as “an accident, including injurious exposure to conditions, which results, during the policy period, in property damage neither expected nor intended from the standpoint of the insured.”
[4]
Reprinted courtesy of
Eric B. Hermanson, White and Williams LLP and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The 411 on the New 415 Location of the Golden State Warriors
June 10, 2015 —
Garret Murai – California Construction Law BlogYou can feel the buzz here in the Bay Area as the Golden State Warriors enter Game 4 of the NBA Playoffs following a 35 point upset over the Houston Rockets on Saturday, and a chance tonight to sweep the series and head to the NBA Finals for the first time since 1975.
Formerly the Philadelphia Warriors from 1946 to 1962, and later the San Francisco Warriors from 1962 to 1971, the Golden State Warriors have played in Oakland’s currently named Oracle Arena since 1966 (except for one year when they played in San Jose while the Oracle Arena was being remodeled).
Starting next year, however, construction will begin on the Warriors’ new stadium in the Mission Bay area of San Francisco with completion scheduled for the 2018-2019 season. Although details are just emerging – and even the conceptual plans have changed after some said that the initial design looked like a toilet – here’s the 411 we know on the new 415 location of the Warriors:
- The cost of the new arena is estimated to be $1 billion.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Fact of Settlement Communications in Underlying Lawsuits is Not Ground for Anti-SLAPP Motion in Subsequent Bad Faith Lawsuit
August 24, 2020 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Trilogy Plumbing, Inc. v. Navigators Specialty Ins. Co. (No. G057796, filed 5/27/20, ord. pub. 6/18/20), a California appeals court ruled that an insurance bad faith lawsuit alleging a variety of claim handling misconduct in defending the insured was not subject to an insurer’s special Strategic Lawsuit Against Public Participation (SLAPP) motion to strike because, while the alleged acts were generally connected to litigation, they did not include any written or oral statement or writing made in connection with an issue under consideration or review by a judicial body and, therefore, did not constitute protected activity under California’s anti-SLAPP statute.
In Trilogy Plumbing, the policyholder was sued in 33 different construction defect lawsuits, some of which Navigators defended, and others which were denied or had the defense withdrawn. The Navigators’ policies were subject to a $5,000 deductible, and Trilogy alleged that Navigators breached the contracts by “demanding deductible reimbursement amounts greater than the policies’ $5,000 stated deductible, and by seeking reimbursement of ordinary defense fees and expenses as if they were subject to deductible reimbursement,” “claiming a right to seek reimbursement from Trilogy for defense fees and expenses Navigators paid for the benefit of third-party additional insureds,” “providing conflicted defense counsel who took instructions only from Navigators without disclosing conflicts of interest,” “failing to reasonably settle cases and by withdrawing [the] defense as a strategic means of trying to force Trilogy to fund its own settlements,” “misrepresenting its deductible provisions,” “refusing to account for deductible amounts it charges and collects,” and others.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
When to Withhold Retention Payments on Private or Public Projects
August 29, 2018 —
Nicholas Karkazis - Gordon & Rees Construction Law BlogTo ensure that construction contractors and subcontractors receive timely progress and retention payments, the California Legislature enacted statutes that impose deadlines and penalties on owners and direct (general) contractors who delay payments. (Cal. Civ. Code, §§ 8800, 8802, 8812, 8814; Pub. Contract Code, §§ 7107, 10262.5; Bus. & Prof. Code, § 7108.5.) However, there is an exception to these deadlines and penalties on both private and public projects. The exception allows an owner or direct contractor to withhold payment1 when there is a good faith dispute between an owner and a direct contractor or between a direct contractor and a subcontractor. (Civ. Code, §§ 8800, subd. (b), 8802, subd. (b), 8812, subd. (c), 8814, subd. (c); Pub. Contract Code, §§ 7107, subds. (c), (e), 10262.5, subd. (a); Bus. & Prof. Code, § 7108.5, subd. (a).)
But the term “good faith dispute” has been a source of confusion where direct contractors owe subcontractors retention payments, but want to withhold the payment because of a dispute.2 California appellate courts were split, with one court finding that any type of bona fide dispute justified withholding, and another finding that only disputes related to the payment itself justified withholding. (Compare Martin Brothers Construction, Inc. v. Thompson Pacific Construction, Inc. (2009) 179 Cal.App.4th 1401 [any bona fide dispute could justify withholding] with East West Bank v. Rio School Dist. (2015) 235 Cal.App.4th 742 [disputes related to the payment itself may justify withholding].) In May 2018, the California Supreme Court clarified that for a direct contractor to withhold a retention payment on a private project, the good faith dispute must somehow relate to the payment itself. (United Riggers & Erectors, Inc. v. Coast Iron & Steel Co. (2018) 4 Cal.5th 1082, 1097-1098.)
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas Karkazis, Gordon & Rees Scully MansukhaniMr. Karkazis may be contacted at
nkarkazis@grsm.com
Ninth Circuit Reverses Grant of Summary Judgment to Insurer For Fortuitous Loss
July 01, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Ninth Circuit reversed the district court's issuance of summary judgment regarding coverage for damages when the insured's plant had to be shut down due to an accident. Ingenco Holdings, LLC v. Ace American Ins. Co., 2019 U.S. App. LEXIS 10946 (9th Cir. April 15, 2019).
Ingenco operated a gas purification plant which converted raw landfill gas into usable natural gas. The final step in the purification process involved the removal of excess nitrogen from the landfill gas. The gas was directed through adsorbent beads, to which nitrogen adhered, contained within pressure vessels.The beads could not withstand the direct pressure of the landfill gas inflow. which, if untreated, could grind the beads down into dust. To reduce the force of the gas flow on the beads, a "diffuser basket" was suspended from the top of each bead-filled pressure vessel. The diffuser basket acted as a shield that prevented the full force of the incoming landfill gas from striking the beads directly.
In 2010, metal brackets securing a diffiuser basket broke. This resulted in damage to other components and an eventual shutdown of the entire facility. The plant remained idle for several months as Ingenco investigated alternative nitrogen filtration options and undertook repairs.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insurance Policies Broadly Defining “Suits” May Prompt an Insurer’s Duty to Defend and Indemnify During the Chapter 558 Pre-Suit Notice Process
May 30, 2018 —
Daniel Garcia - Gordon & Rees Construction Law BlogIn Altman Contractors, Inc. v. Crum & Forster Specialty Insurance Company, No. SC16-1420, 2017 WL 6379535 (Fla. Dec. 14, 2017), the Florida Supreme Court addressed whether the notice and repair process set forth in chapter 558, Florida Statutes, constitutes a “suit” within the meaning of a commercial liability policy issued by Crum & Forster Specialty Insurance Company (“C&F”) to Altman Contractors, Inc. (“Altman”). The Court found that because the chapter 558 pre-suit process is an “alternative dispute resolution proceeding” as included in the definition of “suit” in the policy by C&F to Altman, C&F had a duty to defend Altman during the chapter 558 process, prior to the filing of a formal lawsuit.
Chapter 558, titled “Construction Defects,” sets forth procedural requirements before a claimant may file a construction defect action. It requires a claimant to serve a written notice of claim on the applicable contractor, subcontractor, supplier, and/or design professional prior to filing a construction defect lawsuit. The legislature intended for Chapter 558 to be an alternative dispute resolution mechanism in certain construction defect matters allowing an opportunity to resolve the claim without further legal process.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Garcia, Gordon & Rees Scully MansukhaniMr. Garcia may be contacted at
daniel.garcia@grsm.com
Fannie-Freddie Elimination Model in Apartments: Mortgages
April 08, 2014 —
Sarah Mulholland – BloombergThe apartment-lending units of Fannie Mae (FNMA) and Freddie Mac were among their few money makers after the U.S. housing collapse. Now they should help transform the U.S. mortgage industry.
Lawmakers seeking to eliminate the two government lenders, which were seized by regulators during the 2008 credit crisis, see an antidote to the reckless lending that blew up the U.S. housing market in the structure of the firms’ multifamily operations, which share risks with lenders.
Senate Banking Committee Chairman Tim Johnson and Republican Mike Crapo are proposing legislation to create a new government-backed reinsurer of mortgage bonds that would require private investors to bear losses on the first 10 percent of capital. The model for the provision mirrors Fannie Mae and Freddie Mac (FMCC)’s multifamily lending operations, requiring lenders to shoulder some of the risk on loans they originate.
Read the court decisionRead the full story...Reprinted courtesy of