Builder Must Respond To Homeowner’s Notice Of Claim Within 14 Days Even If Construction Defect Claim Is Not Alleged With The “Reasonable Detail”
June 05, 2017 —
Richard H. Glucksman & David A. Napper - CGDRB News & PublicationsOn February 10, 2017, California’s Fourth District Court of Appeal held that if a builder fails to acknowledge receipt of a homeowner’s Notice of Claim within 14 days, as required by the Right to Repair Act (“SB800”), specifically California Civil Code §913, the homeowner is released from the requirements of SB800 and may proceed with the filing of a lawsuit.
In Blanchette v. Superior Court, Blanchette owned 1 of 28 homes constructed by GHA Enterprises, Inc. (“GHA”). On February 2, 2016, Blanchette served GHA with notice of a claim, setting forth the alleged defects in all 28 homes. On February 23, 2016, GHA responded that the construction defects were not alleged with sufficient “reasonable detail” as required by Civil Code §910. In response, Blanchette asserted that GHA’s response was untimely and thus excused him and the other homeowners from any obligations under SB800. The trial court found for the builder, GHA, holding that Blanchette’s Notice of Claim lacked detail sufficient to trigger GHA’s obligations under SB800. Blanchette appealed the ruling.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean Roeb & Barger and
David A. Napper, Chapman Glucksman Dean Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Chimney Collapses at South African Utility’s Unfinished $13 Billion Power Plant
November 21, 2022 —
Paul Burkhardt - BloombergSouth Africa’s newest coal-fired power plant, which has been under construction since 2008 and will cost an estimated 232 billion rand ($12.7 billion), shut one of its six generating units after a duct collapsed.
The unit at the Kusile plant could remain offline “for a few months” although a clearer estimate will be known over coming weeks, state-owned utility Eskom Holdings SOC Ltd. said in a statement late Wednesday. The outage comes as the country endures record blackouts -- locally known as loadshedding.
The duct appeared to have sheared off from the unit’s main structure, a photo posted on Twitter by Anton Eberhard, a professor at the University of Cape Town’s Graduate School of Business, showed.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Burkhardt, Bloomberg
Filling Out the Contractor’s Final Payment Affidavit
February 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen preparing a contractor’s final payment affidavit, I always suggest for a contractor (or anyone in privity of contract with the owner) to identify the undisputed amounts their accounting reflects is owed to ALL subcontractors, etc., regardless of whether that entity preserved their lien rights. If the contractor provided a payment bond, I footnote this simply to support that none of the lower-tiered subcontractors have lien rights or are the traditional “lienor.” (Thus, there is no prejudice to the owner if an entity is inadvertently omitted from the affidavit.)
There are times, however, where a contractor does not identify a subcontractor that did not serve a notice to owner and, therefore, has no valid lien rights. Or, a contractor omits a lienor that actually did serve a notice to owner and preserve its lien rights; this happens.
There was an older First District Court of Appeals case that harshly (and, quite, unfairly) held that the contractor must identify everyone in the final payment affidavit regardless of whether that entity timely served a notice to owner or their lien is invalid. This case, however, predated, a 1998 statutory change to Florida’s Lien Law.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Insurer Prohibited from Bringing Separate Contribution Action in Subrogation to Rights of Suspended Insured
January 15, 2019 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel LLPIn Travelers Property Casualty Co. of Amer. v. Engel Insulation, Inc. (No. C085753, filed 11/30/18), a California appeals court held that an insurer may not file its own action to assert claims solely as a subrogee of a suspended corporation, where the corporation could not otherwise assert the claims on its own behalf.
In Engel, a homeowners association filed a construction defect action against the developer, Westlake. Travelers defended Westlake as an additional insured on the policy of a subcontractor. After the case settled, Travelers brought a subrogation action against another subcontractor for contribution to the defense costs. However, Westlake had its corporate status suspended for failure to pay taxes, and the subcontractor moved for judgment on the pleadings, which was granted.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Emergency Paid Sick Leave and FMLA Leave Updates in Response to COVID-19
April 06, 2020 —
Yvette Davis & Kyle R. DiNicola - Haight Brown & BonesteelThe Families First Coronavirus Response Act (“FFCRA”) was signed by the President on March 18, 2020 and will become effective no later than April 2, 2020. The law contains numerous updates to the country’s employment regulations in response to the Coronavirus pandemic of which employers should be familiar.
Of particular note, the FFCRA makes limited amendments to the Family and Medical Leave Act. Now, pursuant to the Emergency Family and Medical Leave Expansion Act (“EFMLEA”) employees may take up to 12 weeks of family and medical leave after having worked with the employer for 30 calendar days if the employee is unable to work (or telework) due to the employee’s need to care for a son or daughter under 18 years of age due to the child’s school closure or unavailability of a childcare provider due to a public health emergency, i.e., COVID-19. Unlike the FMLA, which does not apply to many small employers, this requirement applies to any employers with 500 or fewer employees. No mileage radius requirement exists under the EFMLEA.
When an employee utilizes leave pursuant to EFMLEA, the first 10 days of that leave may consist of unpaid leave, but the employee may elect to substitute any accrued paid vacation leave, personal leave, or medical or sick leave, including the Emergency Paid Sick Leave provided for by the Act and described below). All subsequent days of leave taken by the employee after the tenth day must be paid by the employer at a rate of not less than two thirds of the employee’s regular rate of pay and the number of hours the employee would otherwise normally be scheduled to work. The cap is $200 per day or $10,000 in the aggregate.
Reprinted courtesy of
Yvette Davis, Haight Brown & Bonesteel and
Kyle R. DiNicola, Haight Brown & Bonesteel
Ms. Davis may be contacted at ydavis@hbblaw.com
Mr. DiNicola may be contacted at kdinicola@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Appellate Court Breaks New Ground on Policy Exhaustion
April 26, 2021 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsThe Connecticut Appellate Court recently issued a wide-ranging opinion, Continental Casualty Co. v. Rohr, Inc.,[1] which significantly extended the current restrictive view on when a general liability policy can be considered exhausted so as to trigger overlying excess coverage. The case marks a further step away from Judge Augustus Hand’s almost-century-old ruling in Zeig v. Massachusetts Bonding & Ins. Co.,[2] which held that an underlying policy could be “exhausted” by a below-limits settlement as long as the insured was willing to “fill the gap” between the settlement amount and the limits of the policy.[3]
In recent years, courts in California and elsewhere have increasingly walked back Zeig’s broad ruling – holding in Qualcomm v. Certain Underwriters,[4] for example, that an insured’s below-limits settlement with primary carriers does not exhaust the limits of primary coverage, or allow the insured to access overlying excess coverage.[5]
Reprinted courtesy of
Eric B. Hermanson, White and Williams and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
American Arbitration Association Revises Construction Industry Rules and Mediation Procedures
April 08, 2024 —
Dennis Cavanaugh & Larry Grijalva - Construction Law ZoneThe American Arbitration Association (AAA), one of the longest-standing and experienced alternative dispute resolution (ADR) administrators, has unveiled a significant update to its Construction Industry Rules and Mediation procedures. This update, last revised in 2015, became effective March 1, 2024. Changes to the AAA Construction Industry Rules are significant as these rules are incorporated by default in American Institute of Architects standard construction forms, which are widely used in the industry.
Advancements in remote access technology drive a substantial number of new changes. Others are designed to streamline the arbitrator appointment process and certain prehearing procedures and to make arbitration more cost-efficient by enhancing the arbitrator’s case management authority. Some of the more notable changes are:
Fast Track
F-1: The limit for cases eligible for AAA’s Fast Track Procedures has been increased from $100,000 to $150,000 so long as no claim or counterclaim exceeds that amount.
Reprinted courtesy of
Dennis Cavanaugh, Robinson & Cole and
Larry Grijalva, Robinson & Cole
Mr. Cavanaugh may be contacted at dcavanaugh@rc.com
Mr. Grijalva may be contacted at lgrijalva@rc.com
Read the court decisionRead the full story...Reprinted courtesy of
One More Thing Moving From California to Texas: Wildfire Risk
June 19, 2023 —
Patrick Sisson - BloombergIn early January, Keith Elwell was doing one of the things he does best, swinging chainsaws to help save forests from wildfire. Amid groves of junipers and white oak trees, Elwell led a team of a half-dozen volunteers, clearing brush and dead limbs in Twin Springs Preserve in Williamson County, Texas, a 170-acre county preserve a 40-minute drive north of downtown Austin.
Set on the northeastern edge of Hill Country, a rolling, rocky landscape of natural springs and wild grasses, it’s also adjacent to Georgetown, the fastest-growing city in the United States according to US Census Bureau data. Once a small farming town, it’s now an Austin suburb of more than 75,000 people with 60 subdivisions under construction.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Sisson, Bloomberg