Court’s Ruling on SB800 “Surprising to Some”
October 16, 2013 —
CDJ STAFFDescribing it as “surprising to many in the residential home building industry,” Jay Drake of Reuben, Junius & Rose LLP has a piece discussing the recent California Court of Appeals decision that SB800 is not a homeowner’s only remedy for construction defects. The court found, according to Mr. Drake that “the primary purpose of the Act was to provide a property owner with remedies for repair of construction defects before the defects caused actual damages.” In the case before the court, the construction defects had already lead to further damages.
Mr. Drake notes that the legislative history of SB800 puts the bill in response to an earlier California court case in which the courts determined that without actual damage to property, a homeowner could not file a construction defect lawsuit. The court concluded that SB800 was not intended to limit the homeowner’s rights after a construction defect situation has lead to damage.
Read the court decisionRead the full story...Reprinted courtesy of
Third Circuit Holds That Duty to Indemnify "Follows" Duty to Defend
December 27, 2021 —
Jeffrey J. Vita - Saxe Doernberger & Vita, P.C.In a win for policyholders, the Third Circuit Court of Appeals recently affirmed a District Court’s 2018 ruling, which held that the duty to indemnify follows the duty to defend where a settlement precludes a determination on the facts of the case relative to liability and apportionment.
In Liberty Mutual Insurance Co. v. Penn National Mutual Casualty Insurance Co.,1 a large concrete panel collapsed and killed a construction worker at a construction site in New Kensington, Pennsylvania. Cost Company (“Cost”), Liberty Mutual’s insured, was a masonry subcontractor on the project and had further subcontracted with Pittsburgh Flexicore Co. (“Flexicore”), Penn National’s insured, for the concrete panels. Cost’s subcontract agreement required Flexicore to name Cost as an additional insured under its general liability policy issued by Penn National.
When the construction worker’s widow filed a wrongful death lawsuit against Cost and Flexicore, Cost demanded that Penn National defend and indemnify it as an additional insured under the policy. Penn National refused, arguing that any additional insured status had terminated at the conclusion of Flexicore’s work for Cost. As a result, Liberty Mutual defended Cost in the lawsuit, which was ultimately settled.
Read the court decisionRead the full story...Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C.Mr. Vita may be contacted at
JVita@sdvlaw.com
Nebraska Joins the Ranks—No CGL Coverage for Faulty Work
September 17, 2014 —
Craig Martin – Construction Contractor AdvisorThe Nebraska Court of Appeals has ruled that a home builder that fails to adequately compact the soil does not have insurance coverage to repair damages to the home caused by the settling soil. In “insurance speak”, there was no occurrence to trigger coverage.
In this case, Cizek Homes, Inc. v Columbia National Insurance Company, a home builder contracted with a buyer to build a house. A lot was selected and the home was built. After the buyer moved in, the house started to settle, causing damage to the house. The buyer told the builder about these problems and the builder agreed to fix the problems. The builder also contacted its insurance company and requested coverage for the buyer’s claim. The insurer rejected the claim, determining that the buyer’s claim was not covered by the builder’s Commercial General Liability (CGL) insurance.
The insurer then filed suit asking the court to interpret the insurance policy and to determine whether the CGL insurance covered the claim. The court looked to the buyer’s allegations that the builder failed to construct the home in accordance with accepted construction and industry standards and that the builder was negligent in designing and constructing the home. The builder admitted that it was obligated to pay for the costs of repairs, but denied that it was negligent in constructing the home.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
The Colorado Supreme Court holds that loans made to a construction company are not subject to the Mechanic’s Lien Trust Fund Statute
February 21, 2013 —
W. Berkeley Mann, Jr. — Higgins, Hopkins, McLain & Roswell, LLCIn a prior blog post, we summarized the Court of Appeals decision in the case of AC Excavating, Inc. v. Yale, ___ P. 3d. ___, 2010 WL 3432219 (Colo. App. Sept. 2, 2010) which provided an interpretation of the Colorado Mechanic’s Lien Trust Fund Statute, C.R.S. § 38-22-127 (hereafter “the Trust Fund Statute”). A divided Court of Appeals reversed the trial court, and held that capital loans infused into a limited liability company which performed construction could be subject to the provisions of the Trust Fund Statute.
The Court of Appeals reasoned that this determination was necessary because the statute was considered applicable to “all funds disbursed on a construction project.” Additionally, the Court of Appeals held that the intent of the provider of funds was not relevant, and that the statute applied “irrespective of the [originator of the funds]’s intended use of the funds.”
This decision was reviewed by the Colorado Supreme Court in an opinion released on February 4, 2013, and it reversed the Court of Appeals’ decision. See, Yale v. AC Excavating, Inc., ___ P. 3d. ___, 2013 WL 441895 (Colo. Feb. 4, 2013). The Supreme Court strongly disagreed that loaned or infused capital funds which were obtained by the general contractor entity were “funds disbursed on a construction project,” simply because some of the infused monies were used for operational purposes to pay down specific project obligations.
Read the court decisionRead the full story...Reprinted courtesy of
W. Berkeley Mann, Jr.mann@hlmrlaw.com
Washington Court Tunnels Deeper Into the Discovery Rule
July 09, 2019 —
Lian Skaf - The Subrogation StrategistOften times, properly analyzing when a statute of limitations begins to run – not just how long it runs – is crucial to timely pleading. In Dep’t of Transp. v. Seattle Tunnel Partners, 2019 Wash.App. LEXIS 281 (Was. Ct. App. Feb. 5, 2019), Division Two of the Court of Appeals of Washington addressed when the discovery rule starts the statute of limitations clock on a negligence cause of action. The court held that the statute of limitations begins to run when the plaintiff knows that the factual elements of the claim against the defendant exist. The clock starts to run even if the plaintiff wants to investigate the possibility of other contributing factors or the defendant identifies opposing viewpoints on the theory of the claim.
In this matter, the Washington State Department of Transportation (WSDOT) contracted with an engineering firm, WSP USA, Inc. (WSP), for an evaluation of the Alaskan Way Viaduct in 2001. As part of this project, WSP retained the services of Shannon and Wilson (S&W), another engineering firm, to conduct geological profile logs, groundwater-pumping tests, and prepare technical memoranda. In 2002, WSP and S&W installed a pumping well with an eight-inch steel casing (TW-2). In 2009, apparently based on the work done by WSP and S&W, WSDOT determined that a bored underground tunnel was the best option for replacing the viaduct.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Renovate or Demolish Milwaukee’s Historic City Hall?
July 02, 2014 —
Beverley BevenFlorez-CDJ STAFFMilwaukee, Wisconsin’s City Hall, which according to the New York Times is “one the largest of its kind in the country,” is “slowly sinking.” However, residents are debating whether it is worth the millions to renovate—especially considering that despite $76 million spent in 2006 to restore the building’s exterior, a terra cotta urn fell into the street in 2011 resulting in a lawsuit against the contractor.
The main problem with the building is that “old wooden pilings that support the base of City Hall, timbers anchored deep into the marshy soil more than a hundred years ago, are decaying,” the New York Times reported. “So far, the northeast corner of the aging structure has ‘settled’ 2.16 inches over the past three decades — a small change, but serious enough to raise concerns about the possibility of more structural problems.”
However, proponents of renovation mention the building’s rich history. In 1895 when the City Hall was built, it was “the third-tallest structure in the country at the time, behind the Philadelphia City Hall and the Washington Monument.” The German Renaissance Revival building features a 400-foot clock tower, which “is most fondly remembered for its role in the opening credits of the sitcom ‘Laverne & Shirley.’”
“Buildings like this are salvageable,” Dennis Barthenheier, a contractor who has used concrete to reinforce the pilings of nearly two dozen sinking structures in downtown Milwaukee, told the New York Times. “But it’s not a cheap date.”
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law- Where Pragmatism and Law Collide
January 06, 2020 —
Christopher G. Hill - Construction Law MusingsIf there is one “theme” to Construction Law Musings, those that read regularly hopefully see that I take my role as counselor to construction companies seriously. Aside from the fact that litigation and arbitration are both expensive and not a great way for any business, particularly a construction business, to make money, I have found construction professionals to be a pragmatic group of people that would rather solve a problem than go to court.
I have also discussed the need for a good foundation for the project in the form of a well drafted and properly negotiated contract. This contract sets out the rights of the parties and essentially makes the “law” for your construction project. Virginia courts will not renegotiate the terms for you and while this can lead to problems where parties either don’t understand the terms or don’t work to level the terms, it does mean that the parties know what the expectations are where the expectations are properly set, preferably with the help of your friendly neighborhood construction attorney and counselor at law. Practical considerations such as your feel for the other party and which terms are worth forgoing the work for should drive your considerations almost as much as the legal implications.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Effective July 1, 2022, Contractors Will be Liable for their Subcontractor’s Failure to Pay its Employees’ Wages and Benefits
July 25, 2022 —
Edward O. Pacer & David J. Scriven-Young - Peckar & AbramsonOn June 10, 2022, Illinois Governor J.B. Pritzker signed two House Bills that amend the Illinois Wage Payment & Collections Act, 820 ILCS 115 et. seq. (“Wage Act”), to provide greater protection for individuals working in the construction trades against wage theft in a defined class of projects. Pursuant to this new law, every general contractor, construction manager, or “primary contractor,” working on the projects included in the Bill’s purview will be liable for wages that have not been paid by a subcontractor or lower-tier subcontractor on any contract entered into after July 1, 2022, together with unpaid fringe benefits plus to attorneys’ fees and costs that are incurred by the employee in bringing an action under the Wage Act.
These amendments to the Wage Act apply to a primary contractor engaged in “erection, construction, alteration, or repair of a building structure, or other private work.” However, there are important limitations to the amendment’s applicability. The amendment does not apply to projects under contract with state or local government, or to general contractors that are parties to a collective bargaining agreement on a project where the work is being performed. Additionally, the amendment does not apply to primary contractors who are doing work with a value of less than $20,000, or work that involves only the altering or repairing of an existing single-family dwelling or single residential unit in a multi-unit building.
Reprinted courtesy of
Edward O. Pacer, Peckar & Abramson and
David J. Scriven-Young, Peckar & Abramson
Mr. Pacer may be contacted at epacer@pecklaw.com
Mr. Scriven-Young may be contacted at dscriven-young@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of