Construction Defect Claims are on the Rise Due to Pandemic-Related Issues
April 25, 2022 —
Beverley BevenFlorez – CDJ StaffAccording to a recent
New York Times article, pandemic-related issues such as “stop-and-start construction, global supply chain issues, pressure from lenders and yo-yoing housing prices” has caused an increase in construction defect suits for new apartment developments: “Complaints and legal claims are already emerging, signaling that a confluence of all factors amid the Covid crisis could continue to be a problem for new construction — from entry-level studios to top-tier penthouses — for years to come, according to lawyers and development consultants.”
A Times analysis of Department of Buildings data by Marketproof demonstrated an increase in complaints beginning March 1st, 2020: “During the first year of the pandemic, new residential buildings recorded an average of five complaints per building, a 46 percent jump from the same period the previous year.”
Steven D. Sladkus, a partner at Schwartz Sladkus Reich Greenberg Atlas told the Times that his “'phone’s been ringing off the hook' with complaints from homeowners in new condo buildings” regarding “heating problems, poor sound insulation, fire safety issues and faulty elevators.”
Developers have faced a variety of pandemic-related challenges including a disrupted supply chain, shut downs, shipping delays, labor shortages, and increased material prices. In 2020, the lack of availability of vaccines caused some construction to halt: “Suddenly one guy calls in sick and the whole crew of electricians can’t show up,” Steven Zirinsky, co-chair of the building codes committee at the New York chapter of the American Institute of Architects told the Times.
Read the court decisionRead the full story...Reprinted courtesy of
When to Withhold Retention Payments on Private or Public Projects
August 29, 2018 —
Nicholas Karkazis - Gordon & Rees Construction Law BlogTo ensure that construction contractors and subcontractors receive timely progress and retention payments, the California Legislature enacted statutes that impose deadlines and penalties on owners and direct (general) contractors who delay payments. (Cal. Civ. Code, §§ 8800, 8802, 8812, 8814; Pub. Contract Code, §§ 7107, 10262.5; Bus. & Prof. Code, § 7108.5.) However, there is an exception to these deadlines and penalties on both private and public projects. The exception allows an owner or direct contractor to withhold payment1 when there is a good faith dispute between an owner and a direct contractor or between a direct contractor and a subcontractor. (Civ. Code, §§ 8800, subd. (b), 8802, subd. (b), 8812, subd. (c), 8814, subd. (c); Pub. Contract Code, §§ 7107, subds. (c), (e), 10262.5, subd. (a); Bus. & Prof. Code, § 7108.5, subd. (a).)
But the term “good faith dispute” has been a source of confusion where direct contractors owe subcontractors retention payments, but want to withhold the payment because of a dispute.2 California appellate courts were split, with one court finding that any type of bona fide dispute justified withholding, and another finding that only disputes related to the payment itself justified withholding. (Compare Martin Brothers Construction, Inc. v. Thompson Pacific Construction, Inc. (2009) 179 Cal.App.4th 1401 [any bona fide dispute could justify withholding] with East West Bank v. Rio School Dist. (2015) 235 Cal.App.4th 742 [disputes related to the payment itself may justify withholding].) In May 2018, the California Supreme Court clarified that for a direct contractor to withhold a retention payment on a private project, the good faith dispute must somehow relate to the payment itself. (United Riggers & Erectors, Inc. v. Coast Iron & Steel Co. (2018) 4 Cal.5th 1082, 1097-1098.)
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas Karkazis, Gordon & Rees Scully MansukhaniMr. Karkazis may be contacted at
nkarkazis@grsm.com
No Retrofit without Repurposing in Los Angeles
October 21, 2013 —
CDJ STAFFThe Los Angeles Times has continued its series on the seismic safety of buildings in downtown Los Angeles. According to the article, Los Angeles only requires seismic retrofits of buildings if their purpose is being changed. One investor, Izak Shomof, bought a residential hotel and kept it as one to avoid retrofitting the building. He converted an office building to upscale residences and so the building was strengthened.
His son, Eric Shomof, keeps an office in the unreinforced building. He said if more retrofitting were required, “you’d see a lot more vacant buildings down here,” describing the process as “not cheap.”
Depending on whether or when a building has changed its use, the concrete buildings of downtown Los Angeles may or may not be protected against failure in an earthquake.
Read the court decisionRead the full story...Reprinted courtesy of
The Proposed House Green New Deal Resolution
February 27, 2019 —
Anthony B. Cavender - Gravel2GavelA Resolution has been proposed to the House for consideration that would recognize the Federal Government’s duty “to create a Green New Deal.” It sets forth a very ambitious 10-year program to mobilize and transform every aspect of American life to combat the threats of climate change by transitioning to an economy based upon 100% clean and renewable energy.
In doing so, millions of new jobs would be created, and everyone who wants a job would be guaranteed a job. The sponsors’ talking points declare that there is no time to lose, that Americans love a challenge, and “this is our moonshot.” The obvious goal is to eliminate the generation and use of fossil fuel and nuclear energy—they are simply not part of the solution.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Comply with your Insurance Policy's Conditions Precedent (Post-Loss Obligations)
May 31, 2021 —
David Adelstein - Florida Construction Legal UpdatesI am of the opinion that if your property insurer requests a sworn proof of loss, furnish one with the assistance of counsel (preferably). Ignoring the insurer’s request or refusing to comply with insurer’s request is NOT value-added; it is simply placing you at a disadvantage based on the insurer’s argument that you, as the insured, materially breached the policy. I generally find no value having to confront this expected argument. Instead, I find value making an effort to comply with post-loss obligations including the insurer’s request to submit a sworn proof of loss. Working with counsel can help you comply with post-loss obligations (conditions precedent) while not weakening the value or merits of your claim.
By way of example, in Edwards v. Safepoint Ins. Co., 46 Fla. L. Weekly D1086a (Fla. 4th DCA 2021), the insured did not provide its property insurer with the requested sworn proof of loss. The insurer moved for summary judgment that the insured’s failure to submit the sworn proof of loss was a material breach of the policy that rendered the policy ineffective. The trial court agreed and granted summary judgment. The Fourth District Court of Appeal affirmed explaining “[a] total failure to comply with policy provisions made a prerequisite to suit under the policy may constitute a breach precluding recovery from the insurer as a matter of law. If, however, the insured cooperates to some degree or provides an explanation for its noncompliance, a fact question is presented for resolution by a jury.” Edwards, supra, quoting Haiman v. Federal Ins. Co., 798 So.2d 811, 812 (Fla. 4th DCA 2001).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Do Hurricane-Prone Coastal States Need to Update their Building Codes?
April 15, 2015 —
Beverley BevenFlorez-CDJ STAFFProperty Casualty 360 reported that “a number of coastal states took no action to improve their building code systems since 2012, and a few have weaker systems in place, according to the Insurance Institute for Business & Home Safety (IBHS).”
The IBHS released their “Rating the States” report that published the results of their study of “the 18 most hurricane-prone states located along the Gulf of Mexico and the Atlantic Coast on their building regulations.” States can receive up to 100 points, with a higher score reflecting better state building requirements.
Delaware scored lowest with a mere 17 points—the same score it received in 2012. Virginia, the highest scored state, earned 95 points.
Read the court decisionRead the full story...Reprinted courtesy of
Contractor Sues License Board
June 30, 2011 —
CDJ STAFFJudge Kendall J. Newman of the US District Court handed down a decision on June 24 on the case of Kent v California Department of Consumer Affairs. Mr. Kent, appearing as his own counsel, had brought the suit against the California Department of Consumer Affairs and the Contractors State Licensing Board after he was arrested in a sting operation and, as the plaintiff put it, “was absurdly arrested and uncooperatively detained for a time longer than necessary or allowed by law under the false pretense of contracting with out a license.” Mr. Kent’s alleged that Rick Lopez, one of the defendants, formed him to read allow from the California Business and Professions Code. He said he was later handcuffed and placed in an uncomfortable chair, “enduring physical pain and emotional agony.”
Although Kent was given a Notice to Appear, he alleged that a further defendant, Stuart Rind, “closed the plaintiff’s case marked citation A7773 without giving written notice to anyone.” As a result, the Placer County District Attorney’s Office had no record of his Notice to Appear.
Kent alleged that subsequently his firm was essentially shut down for two years and that he was prevented from “legally contracting or selling services for any other contractor or qualifying for any other licensed capacity governed by the CSLB.” After this, the CSLB suspended the license for his firm, DSI Construction. He was assessed a $1,500 fine, after which he claims he sent a letter to the CSLB demanding money damages. The judge noted that the letter was not included in the plaintiff’s Ninth Amended Complaint.
Judge Kendall recommended that the plaintiff’s Complaints be dismissed, although he did allow that sixth, and perhaps the eighth and ninth, could be amended with a tenth amended complaint.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
The Court of Appeals Holds That Indifference to Safety Satisfies the Standard for a Willful Violation Under WISHA
May 16, 2022 —
Cameron Sheldon - Ahlers Cressman & Sleight PLLCIn March 2022, the Washington State Court of Appeals, Division One, issued Marpac Constr., LLC v. Dep’t of Lab. & Indus., No. 82200-4-I, 2022 WL 896850, at *1 (Wash. Ct. App. Mar. 28, 2022) holding Marpac Construction, LLC (“Marpac”) liable for three willful Washington Industrial Safety and Health Act of 1973 (WISHA) violations pertaining to safe crane operation near energized power lines.
Marpac was the general contractor on an apartment complex construction project in West Seattle. The worksite had high voltage power lines running throughout the site. Seattle City Light had flagged some with a 10-foot offset, but none of the other power lines were flagged. Marpac’s superintendent assumed that the lines were between 26 kilovolts (kV) and 50 kV based on their connection to the lines flagged by Seattle City Light. The superintendent never called Seattle City Light to check the voltage of the lines and the lines remained above ground.
In September 2016, a subcontractor began work on the project’s structural foundation. The subcontractor expressed concerns about working around the power lines, but Marpac promised it was working on mitigation of the power line hazard and directed the subcontractor continue working. At one point, the subcontractor’s employees had to move the crane and concrete forms away from the power lines to allow a cement truck to park in its place. The crane’s line contacted the power lines, causing serious injuries to two of the subcontractor’s employees.
Read the court decisionRead the full story...Reprinted courtesy of
Cameron Sheldon, Ahlers Cressman & Sleight PLLCMs. Sheldon may be contacted at