Developer’s Failure to Plead Amount of Damages in Cross-Complaint Fatal to Direct Action Against Subcontractor’s Insurers Based on Default Judgment
January 21, 2019 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel LLPIn Yu v. Liberty Surplus Ins. Corp. (No. G054522, filed 12/11/18), a California appeals court held that a developer’s failure to allege the amounts of damages sought in its cross-complaint rendered default judgments against a subcontractor void and, therefore, unenforceable against the subcontractor’s insurers in a direct action under Insurance Code section 11580(b)(2).
Yu, the owner, hired ATMI to develop a hotel. ATMI subcontracted with Fitch to perform stucco and paint work. Yu sued ATMI for construction defects and the developer cross-complained against its subcontractors, including Fitch, for breach of contract; warranty; indemnity, etc. Yu’s operative complaint prayed for damages “in an amount not less than $10,000,000, according to proof.” ATMI’s cross-complaint stated that it incorporated the allegations of Yu’s complaint “for identification and informational purposes only,” but “does not admit the truth of any allegations contained therein.” The cross-complaint also prayed for damages with respect to the various causes of action “in an amount according to proof.”
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Terminating the Notice of Commencement (with a Notice of Termination)
July 19, 2017 —
David Adelstein - Florida Construction Legal UpdatesThe notice of commencement is important for purposes of construction lien priority. Stock Bldg. Supply of Florida, Inc. v. Soares Da Costa Const. Services, LLC, 76 So.3d 313, 317 (Fla. 3d DCA 2011) (“[A] notice of commencement serves to determine the priority of liens under the Construction Lien Law.”). A lien relates back in time to the date the notice of commencement was recorded assuming the notice of commencement is still in effect when the lien is recorded (or an amended noticed of commencement is recorded). Lien priority is very important and the reason why a contractor should always want to ensure there is an effective notice of commencement in place rather than an expired notice of commencement.
For the same reasons why a contractor wants to ensure there is an effective notice of commencement, there are times an owner wants to terminate a notice of commencement. An owner may want to terminate the potential priority of a construction lien. For instance, say the owner is refinancing or obtaining a construction loan in the midst of construction. A lender will want to ensure its mortgage maintains first priority and certainly priority over a potential construction lien. Otherwise, why would a lender finance the construction if it does not maintain first priority. It generally will not. Thus, an owner needs to terminate the notice of commencement so that the closing occurs on the loan and the mortgage recorded before a new notice of commencement is recorded and construction continues.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Final Rule Regarding Project Labor Agreement Requirements for Large-Scale Federal Construction Projects
January 29, 2024 —
Aaron C. Schlesinger & Julia Loudenburg - Peckar & Abramson, P.C.Beginning on January 22, 2024, in compliance with President Biden’s February 4, 2022 Executive Order, 14603, federal construction projects with a total estimated cost of $35 million are required to utilize a project labor agreement (“PLA”) unless the contracting agency grants an exception. The Federal Register estimates that this rule will impact approximately 119 IDIQ contracts each year; these contracts have an average award value of about $114 million.
The White House claims the PLAs will improve projects by:
- Eliminating project delays from labor unrest, such as strikes;
- Creating dispute resolution procedures and cooperation for labor-management disputes, such as those over safety;
- Including provisions “to support workers from underserved communities and small businesses”;
- Helping to create a steady pipeline of workers for federal projects; and
- Promoting competition on government contracts so that all builders, even those who are non-union, can bid on jobs that require a PLA.
Read the court decisionRead the full story...Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson, P.C.Mr. Schlesinger may be contacted at
aschlesinger@pecklaw.com
Wall Street’s Favorite Suburban Housing Bet Is Getting Crowded
February 15, 2021 —
Patrick Clark - BloombergWall Street’s zest for a corner of suburban real estate long left to small landlords is reaching new heights, attracting institutional investors, homebuilders and apartment managers during a pandemic that has ignited demand for larger homes.
The pension manager for the Canadian Mounties is the latest investor in single-family rentals, joining JPMorgan Chase & Co.’s asset-management arm and Nuveen Real Estate in a bet that there are lots of Americans who want spare bedrooms and backyards, but don’t have cash for down payments.
“It’s really an inflection point in SFR,” said Michael Carey, a senior director for Altus Group, an advisory firm. “It used to be an alternative asset class. Now people look at it as a solution.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg
Sanctions of $1.6 Million Plus Imposed on Contractor for Fabricating Evidence
March 16, 2017 —
Paul R. Cressman, Jr.King County Superior Court issued sanctions of $1,641,721 in favor of Gefco and against Cascade Drilling, Inc. and its President, Bruce Niermeyer, composed of $1,394,435 in attorneys’ fees and $247,286 in expert fees. [i]
Cascade Drilling is a contractor. Gefco manufactures and sells large drilling machinery. The dispute centered around a project that began in 2008. Cascade was hired to drill a water well at a housing development in Wheeler Canyon, California. Cascade used a 50K drilling rig purchased from Gefco. The pump drive shafts on the drilling rig failed four times. After each failure, Cascade ordered a replacement pump drive shaft from Gefco.
In September 2008, Cascade ordered drilling equipment for an unrelated drilling rig from Gefco, but did not pay Gefco. Gefco then sued to collect. Cascade admitted not paying, but asserted counterclaims alleging that Gefco was indebted to Cascade for non-conforming and defective goods, including the replacement pump drive shafts purchased from Gefco for the Wheeler Canyon project.
Read the court decisionRead the full story...Reprinted courtesy of
Paul R. Cressman, Jr., Ahlers & Cressman PLLCMr. Cressman may be contacted at
pcressman@ah-lawyers.com
How Artificial Intelligence Can Transform Construction
February 22, 2021 —
Jeff Rubenstone - Engineering News-RecordArtificial intelligence and machine-learning algorithms have struggled to make sense of chaotic construction jobsites, but recent years have seen industry firms build the vast data lakes and analytics systems necessary for these machines to provide useful advice on how to plan, schedule and execute projects. In some cases, these AI advisors have become a standard part of some firms’ project delivery methods. But it’s still a challenge to convince construction professionals to listen to these AI advisors, and there are emerging questions of how risk will be allocated once algorithm-driven decisions start to steer projects.
Reprinted courtesy of
Jeff Rubenstone, Engineering News-Record
Mr. Rubenstone may be contacted at rubenstonej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
A Relatively Small Exception to Fraud and Contract Don’t Mix
April 06, 2016 —
Christopher G. Hill – Construction Law MusingsRemember all of my posts about how fraud and contract claims don’t usually play well in litigation? Well, as always with the law, there are exceptions. For instance, a well plead Virginia Consumer Protection Act claim will survive a dismissal challenge.
A recent opinion out of the Alexandria division of the U. S. District Court for the Eastern District of Virginia sets out another exception, namely so called fraudulent inducement. In XL Specialty Ins. Co. v. Truland et al, the Court considered the question of whether both a tort and contract claim can coexist in the same lawsuit when the tort claim is based upon the information provided to the plaintiff when that information proves false.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Construction Law MusingsMr. Hill may be contacted at
chrisghill@constructionlawva.com
Not Remotely Law as Usual: Don’t Settle for Delays – Settle at Remote Mediation
May 25, 2020 —
Victor J. Zarrilli, Robert G. Devine & Michael W. Horner - White and Williams LLPThe emergence and rapid spread of COVID-19 has created extraordinary circumstances that have significantly impacted how we go about living, working and interacting with one another. The practice of law is no exception.
While most cases have been postponed and some extended indefinitely, the issues and disputes that first triggered the litigation remain. In fact, the burdens created by social distancing and other responses to the COVID-19 outbreak have served to only increase these disputes and create an urgent need in some for quick resolution.
In our previous article, we summarized some of the best practices that should be applied when taking and defending depositions in a remote, virtual setting. That technology can also offer the same benefits for alternative dispute resolutions. If planned properly, the use of technology allows remote mediations to be conducted as seamlessly as in-person mediations and, in some circumstances, affords additional benefits that can achieve the best possible resolution for all sides.
This article summarizes the opportunities technology has created by which parties can attempt to resolve their disputes through alternative dispute resolution methods, even in a time of social distancing.
Reprinted courtesy of White and Williams LLP attorneys
Victor J. Zarrilli,
Robert G. Devine and
Michael W. Horner
Mr. Zarrilli may be contacted at zarrilliv@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Horner may be contacted at hornerm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of