Be Careful How You Terminate: Terminating for Convenience May Limit Your Future Rights
January 19, 2017 —
Brett M. Hill - Ahlers & Cressman, PLLC BlogMany construction contracts contain a termination clause that allows a contractor to be terminated either for convenience or for cause. Termination for convenience and termination for cause clauses have been discussed previously on the blog
here,
here and
here. The distinction between a termination for convenience or for cause is an important one.
If a contractor is terminated for convenience, the rights of the party who has terminated the contractor for convenience could be limited in the future. This is specifically true as to any defects in the terminated contractor’s work that are discovered after the termination for convenience.
This issue was addressed in an Oregon Court of Appeals case where a general contractor attempted to recover costs incurred in correcting a terminated subcontractor’s work after the subcontractor was terminated for convenience. Shelter Prods. v. Steel Wood Constr., Inc., 257 Or. App 382 (2013). In that case, the subcontractor sued the general contractor for its termination expenses. The general contractor asserted an offset/backcharge claim for damages incurred by the general contractor in correcting the subcontractor’s defective work. The general contractor had incurred the costs after it had terminated the subcontractor. The general contractor did not notify the subcontractor that its work was defective and did not give the subcontractor an opportunity to cure before the repairs were completed.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers & Cressman, PLLCMr. Hill may be contacted at
bhill@ac-lawyers.com
Waiving The Right to Arbitrate Under Federal Law
November 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesIf there is an arbitration provision in your contract that you want to enforce, you do not want to take action inconsistent with those rights as this could give rise to a waiver argument, i.e., that you waived your rights to arbitrate, particularly if the other party has been prejudiced.
Under federal policy and law, establishing waiver requires the party arguing waiver to “bear a heavy burden of proof.” U.S. f/u/b/o John Wayne Construction, G.S.A. Division, LLC v. Federal Ins. Co., 2021 WL 4526727 (M.D.Fla. 2021) quoting Stone v. E.F. Hutton & Co., 898 F.2d 1542, 1543 (11th Cir. 1990).
“To determine whether the right to arbitrate has been waived, courts apply a two part test: i) whether, “‘under the totality of the circumstances,’ the party ‘has acted inconsistently with the arbitration right’”; and ii) “whether, by doing so, that party ‘has in some way prejudiced the other party.’” Id. quoting Ivax Corp. V. B. Braun of Am., Inc., 286 F.3d 1309, 1315-16 (11th Cir. 2002). Substantial participation in litigation prior to invoking the right to arbitrate supports a party acting inconsistent with the right to arbitrate. Id. And, “‘[p]rejudice has been found in situations where the party seeking arbitration allows the opposing party to undergo the types of litigation expenses that arbitration was designed to alleviate.’” Id. quoting Morewitz v. W. of Eng. Ship Owners Mut. Prot. & Indem. Ass’n (Luxembourg), 62 F.3d 1356, 1366 (11th Cir. 1995).
Hence the heavy burden for a party to support to prove waiver– establishing both substantial participation in litigation that is inconsistent with the right to arbitrate AND prejudice.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Changes To Commercial Item Contracting
May 29, 2023 —
Marcos R. Gonzalez - ConsensusDocsThe FAR Council has recently published two changes to commercial item contracting that clarify the definition of commercial services and simplify commercial item determinations (“CIDs”) for contracting officers (“COs”). Since the 1990s, the federal government has encouraged the purchase of commercial items to ease the regulatory burden on vendors who have not previously conducted federal business, encourage innovation, and lower prices[
1]. These different objectives (cost savings, broadening markets, innovation) often have corollary policies; for example, vendors who are not accustomed to the regulatory burdens of government business are encouraged to enter the market by being exempted from a slew of regulations (found in standard commercial items clause FAR 52.212-4). As a result, the regulations applicable to commercial item contracting are those required by statute and executive orders in addition to generic commercial terms that may be tailored due to potential variation in commercial terms.[
2]
Commercial Products v. Commercial Services
The first change, in effect since November 2021 pursuant to the 2019 National Defense Authorization (“NDAA”), split the old definition of “commercial item” into two separate definitions: “commercial product” and “commercial service.”[
3] We are now blessed with the following definitions of commercial products and services, respectively:
Commercial product means—
(1) A product, other than real property, that is of a type customarily used by the general public or by nongovernmental entities for purposes other than governmental purposes, and–
(i) Has been sold, leased, or licensed to the general public; or
(ii) Has been offered for sale, lease, or license to the general public;
Reprinted courtesy of
Marcos R. Gonzalez, Peckar & Abramson, P.C.
Mr. Gonzalez may be contacted at mgonzalez@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Substantial Completion Explained: What Contractors & Owners Should Know
January 17, 2022 —
Travis Colburn - Ahlers Cressman & SleightA project’s Substantial Completion date is a critical construction milestone for contractors and owners. Depending on the contract, the date of Substantial Completion has project-specific contractual and statutory consequences.
Substantial Completion is an “event” – there is no universal definition of the term. It is generally understood to be (1) a point in time (2) when work performed by the contractor is sufficiently complete (3) where it can be used or occupied for the owner’s intended purpose. The date of Substantial Completion is generally established at the time of contract formation (either as a negotiated or a contract set date), and that date may be adjusted over the course of a project to account for excusable delays.
As a construction professional, your attorney should review and tailor any written agreement to your project-specific needs and risk tolerances prior to execution. Savvy construction professionals often start with standard form agreements promulgated by the American Institute of Architects (“AIA”), the Design-Build Institute of America (“DBIA”), or the Engineers Joint Contract Document Committee (“EJCDC”) as the basis for their construction contracts. The AIA, DBIA, and EJCDC standard forms each contains contract provisions relating to when and what happens once Substantial Completion has occurred, subject to any agreed-to, project-specific deviations.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
Alabama Court Upholds Late Notice Disclaimer
August 20, 2018 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Evanston Ins. Co. v. Yeager Painting, LLC, 2018 U.S. Dist. LEXIS 130316 (N.D. Ala. Aug. 3, 2018), the United States District Court for the Northern District of Alabama had occasion to consider an insured’s reporting obligations under a general liability policy.
Evanston’s insured, Yeager, was hired to sandblast water tanks, and in turn, subcontracted out the work to a third party. On May 19, 2012, an employee of the subcontractor was severely injured in connection with a work-site accident. It is not entirely clear when Yeager provided notice of occurrence to Evanston, although Evanston advised by letter dated January 30, 2013 that it would be further investigating the matter subject to a reservation of rights. Evanston subsequently denied coverage by letter dated April 10, 2013, the disclaimer based on a subcontractor exclusion on the policy. Notably, Evanston’s letter advised that Yeager should immediately contact Evanston if any facts changed or if it had any additional information concerning the matter.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub Lieberman Straus & Shrewsberry LLPMr. Margolies may be contacted at
bmargolies@tlsslaw.com
Coverage Established for Property Damage Caused by Added Product
April 28, 2014 —
Tred R. Eyerly – Insurance Law HawaiiApplying Minnesota law, the federal district court determined the supplier of contaminated dried milk had coverage. The Netherlands Ins. Co. v. Main Street Ingredients, LLC, 2014 WL 1012793 (8th Cir. March 18, 2014).
In 2007, Plainview Milk Products sold dried milk to Main Street Ingredients, LLC, who then sold the dried milk to Malt-O-Meal. The dried milk was used by Malt-O-Meal in its instant oatmeal products.
In June 2009, the FDA found Salmonella bacteria at Plainview's plant. The FDA also observed thirteen instances of insanitary conditions in the plant. Plainview issued a product recall notice announcing a "voluntary recall" of dried milk, stating its dried milk had "the potential to be contaminated with Salmonella."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pensacola Bridge Repair Plan Grows as Inspectors Uncover More Damage
September 28, 2020 —
Jim Parsons - Engineering News-RecordWith a still-growing list of repairs needed to restore the barge-damaged Pensacola Bay Bridge, the Florida Dept. of Transportation has yet to determine a timeline for completing repairs. But assessments by the agency’s inspectors indicate that impacts from several Skanska-owned construction barges that unmoored during Hurricane Sally not only resulted in five irreparable spans, as previously reported, but at least two more that will require partial replacement.
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Three Key Takeaways from Recent Hotel Website ADA Litigation
April 26, 2021 —
Shane Singh & Grace Mehta - Lewis BrisboisDespite the COVID-19 pandemic and its chill on the hospitality industry, ADA-related digital lawsuits increased by approximately 23% in 2020. Many of these lawsuits are filed against hotels. The complaints allege that a hotel’s online reservation system failed to provide enough detail for individuals with disabilities to decide if the hotel meets their accessibility needs.
These plaintiffs will often claim that it is insufficient to describe an aspect of a hotel or room as “accessible” because the term is an opinion or conclusion. Plaintiffs argue that a hotel’s reservation system must report specific information, such as the dimensions of space under accessible desks and sinks, the slopes of surfaces, doorway clearance, and numerous other technical requirements under the ADA.
Many hotels are fighting back, arguing that the detail provided is sufficient and in compliance with the ADA. So far this year, in February 2021, two judges in the U.S. District Court for the Central District of California, Judge Percy Anderson and Judge Cormac Carney, agreed with the defendants, dismissing three cases with prejudice.
Reprinted courtesy of
Shane Singh, Lewis Brisbois and
Grace Mehta, Lewis Brisbois
Mr. Singh may be contacted at Shane.Singh@lewisbrisbois.com
Ms. Mehta may be contacted at Grace.Mehta@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of