Oregon Courthouse Reopening after Four Years Repairing Defects
April 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Courthouse Square in Marion County, Oregon is due to reopen after four years and nearly $23 million of repair costs to fix structural defects, according to the Statesman Journal. The square includes a courthouse building and bus mall, and is jointly owned by the county and transit district.
Two years after the Courthouse Square had been built, cracks were observed “in the building’s walls” and “paving stones on the bus mall shifted and settled.” A construction defect suit was filed in 2006.
However, the situation worsened in July of 2010 when “engineers determined that the entire complex was dangerous,” according to the Statesman Journal. “Building safety officials gave Courthouse Square’s occupants 60 days to move out, forcing county and transit district operations into temporary leased space.”
Now that the structural repairs have been completed, Dave Clark, project manager with Structural Preservation Systems LLC (the company awarded the repair contract), stated that the building’s structure is now stronger than most buildings. “If there’s an earthquake, come to this building,” Clark said.
Read the court decisionRead the full story...Reprinted courtesy of
Mexico’s Construction Industry Posts First Expansion Since 2012
August 13, 2014 —
Brendan Case – BloombergMexico’s construction industry expanded in June for the first time in 19 months, adding to signs that the economy is rebounding after missing analyst estimates in seven of the last eight quarters.
Construction increased 2.2 percent from the year earlier, helping industrial production to expand 2 percent, according to data released today by the national statistics agency. The median estimate of 19 economists surveyed by Bloomberg was for industrial output to rise 2.1 percent.
“Industrial activity continued strengthening in June, very much in line with what the market expected,” Mario Correa, the chief Mexico economist at Bank of Nova Scotia, said in a note to clients today. “The construction industry finally showed a positive growth rate.”
Read the court decisionRead the full story...Reprinted courtesy of
Brendan Case, BloombergMr. Case may be contacted at
bcase4@bloomberg.net
Courthouse Reporter Series: The Bizarre Case That Required a 117-Year-Old Expert
December 04, 2023 —
Todd Heffner & Di'Vennci Lucas - The Dispute ResolverA recent decision by the Georgia Court of Appeals, Munro v. Georgia Department of Transportation, highlights how overly specific and inflexible rules of evidence can create peculiar results.
Munro involved a dispute over the design of a Georgia intersection. No. A23A0404, 2023 WL 4194716 (Ga. Ct. App. June 27, 2023). The plaintiff alleged that the defendant improperly designed the intersection, never corrected that improper design, and failed to properly maintain the intersection. These claims were dismissed for a very odd reason: the plaintiff’s expert witness wasn’t old enough.
The case arose from a car accident. A vehicle in which the plaintiff Munro was a passenger collided with a tractor trailer crossing an intersection. Munro sued the Georgia Department of Transportation (DOT) for negligently designing, maintaining, and inspecting the intersection. The DOT filed a motion to dismiss for lack of subject matter jurisdiction on the ground of sovereign immunity and a motion to exclude the testimony of the Munros’ expert witness, among other motions. The trial court dismissed the case in full on the sovereign immunity ground and denied the other motions as moot. The Munros appealed.
Reprinted courtesy of
Todd Heffner, Troutman Pepper and
Di'Vennci Lucas, Troutman Pepper Read the court decisionRead the full story...Reprinted courtesy of
Mr. Heffner may be contacted at
todd.heffner@troutman.com
Florida Federal Court to Examine Issues of Alleged Arbitrator Conflicts of Interests in Panama Canal Case
May 24, 2021 —
Sarah B. Biser & Philip Z. Langer - ConsensusDocsThe parties in a $238-million dispute over the construction of the third set of locks for the Panama Canal are raising issues concerning alleged conflicts of interest on the part of the International Chamber of Commerce (“ICC”) arbitrators in the United States District Court for the Southern District of Florida.[2] The case may address rarely litigated issues concerning whether arbitrators who sit on multiple arbitration panels together or who support appointment of each other to lead arbitration panels have disabling conflicts of interest.
The case pits Grupo Unidos por el Canal, S.A. (“Grupo”), a consortium of Spanish, Italian, Belgian, and Panamanian construction firms, against Autoridad del Canal de Panama (“ACP”), the Panamanian entity that operates the Panama Canal and that sponsored the multi-billion-dollar, decade-long project to expand the Canal’s capacity by building a new set of locks (the “Project”). The current dispute (the “Panama 1 Arbitration”), which centers on the suitability of the rock coming from the excavations to be used to produce concrete aggregates for the Project, was arbitrated before a three-member ICC Tribunal and resulted in a $238-million award to ACP and against Grupo. The ICC Tribunal reversed a decision of the dispute review board established in the parties’ contract.
Reprinted courtesy of
Sarah B. Biser, Fox Rothschild LLP and
Philip Z. Langer, Fox Rothschild LLP
Ms. Biser may be contacted at sbiser@foxrothschild.com
Mr. Langer may be contacted at planger@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of
Certificates as Evidence of Additional Insured Coverage Are All the Rage, But You Deserve Better
August 30, 2021 —
Joseph L. Cohen, W. Mason & Sean Milani-nia - ConsensusDocsConsider the following scenario: the construction project is ready to proceed. The deal is done. The agreements have all been carefully crafted, with detailed provisions on insurance dedicated to reducing risk. Those provisions require the downstream trade contractors to furnish certificates of insurance listing the owner and prime contractor as additional insureds on the downstream contractor’s policies of insurance. A provision in the prime contract further requires the prime contractor to provide the owner with a certificate of insurance showing the owner as an additional insured on the prime contractor’s policies. At the ceremonial ground-breaking and right before work commences, the downstream contractors deliver their insurance certificates to the prime contractor and the prime contractor delivers its certificate plus the downstream certificates to the owner. From there, each insurance certificate will begin its final destination to the project file (either electronic or physical) where, with any luck, it will serve the regular stint before being discarded after the project’s successful conclusion. Otherwise, it will be retrieved under much stress and heavy scrutiny. The acceptance of insurance certificates is often viewed as standard industry practice, but should it be?
The answer is a resounding “no.” There are many form development and construction agreements in circulation that deem insurance certificates to be acceptable evidence of insurance. But, a certificate of insurance should not be relied upon because it does not mean that insurance has been placed. You deserve real evidence that the requisite additional insured coverage is in place (in the form of a policy endorsement), and here is why.
Reprinted courtesy of
Joseph L. Cohen, Fox Rothschild,
W. Mason, Fox Rothschild and
Sean Milani-nia, Fox Rothschild
Mr. Cohen may be contacted at jlcohen@foxrothschild.com
Mr. Mason may be contacted at wmason@foxrothschild.com
Mr. Milani-nia may be contacted at smilani@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of
New Hampshire’s Statute of Repose for Improvements to Real Property Does Not Apply to Product Manufacturers
April 22, 2019 —
Gus Sara - The Subrogation StrategistIn United Services Automobile Association v. Broan-Nutone, LLC, No. 218 2017 CV 01113, [1] the Superior Court of Rockingham County, New Hampshire recently considered whether the eight-year statute of repose for improvements to real property applied to the manufacturer of a ceiling ventilation fan that was installed in the property during its original construction. The court held that New Hampshire’s statute of repose did not apply to the manufacturer because it was not involved in incorporating its product into the property.
In 2012, Chad St. Francis purchased a home in Northwood, New Hampshire. The home was originally constructed in 2008, at which time a Broan-Nutone ceiling ventilation fan was installed in the first-floor bathroom. In 2016, a fire occurred at the home. United Services Automobile Association (USAA) provided property casualty insurance for the home and paid Mr. St. Francis for the damage. In 2017, USAA filed a subrogation lawsuit against Broan-Nutone, alleging that its ceiling fan caused the fire due to a design defect within the product. Broan-Nutone filed a motion for summary judgment on grounds that USAA’s action was barred by New Hampshire’s statute of repose for improvements to real property.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com
Experts: Best Bet in $300M Osage Nation Wind Farm Dispute Is Negotiation
March 11, 2024 —
Daniel Tyson - Engineering News-RecordNearly two months after a federal judge ruled that renewables developer Enel Green Power North America must deconstruct 84 land-based wind turbines because it did not secure mineral rights on Osage Nation land in northern Oklahoma, two energy sector attorneys say the unit of an Italy-based company must negotiate with the tribe.
Reprinted courtesy of
Daniel Tyson, Engineering News-Record
Mr. Tyson may be contacted at tysond@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court of New Jersey Reviews Statutes of Limitation and the Discovery Rule in Construction Defect Cases
July 18, 2018 —
David Suggs – Bert L. Howe & Associates, Inc.Robert Neff Jr. of Wilson Elser analyzed the recent case, Palisades at Fort Lee Condo. Ass’n v. 100 Old Palisade, LLC, 2017 N.J. Lexis 845, 169 A.3d 473 (Supreme Court of New Jersey, September 14, 2017), and states that this ruling “gives defendants the ability to defend against the assertion that the statute of limitations was tolled until the most recent owner (and plaintiff) discovered the cause of action.”
Neff concludes that a statute of limitations test needs to be conducted at the beginning of each case: “In Palisades, the motions to dismiss based on the statute of limitations were filed at the conclusion of all discovery. While an initial analysis might yield the conclusion that certain discovery will be needed to ascertain the appropriate accrual date (or dates, in the case of multiple defendants), counsel will then know what discovery to seek during the discovery period.”