Force Majeure Under the Coronavirus (COVID-19) Pandemic
March 08, 2021 —
Lindsay T. Watkins - Ahlers Cressman & Sleight PLLCAs COVID-19 disrupts work and life as we know it, the question many contractors have is what protections are available against the inevitable project impacts and delays? Generally, construction contracts require a contractor to timely perform work until project completion or potentially face damages (liquidated or actual) and possible termination. When events occur, however, that are beyond our control (such as a national pandemic), it is important to review and understand what contract provisions or avenues are available for potential relief.
1.
Review Your Contract For A Force Majeure Provision.
A
“force majeure” contract provision is commonly included in construction contracts, service agreements, purchase orders, etc. It typically covers events or conditions that can be neither anticipated nor controlled. These provisions, however, will vary greatly from contract to contract and may not include the language “force majeure” but rather may be included in general delay or impact clauses. For example, some common provisions include:
- Washington State Department of Transportation Clause (2018 Standard Specifications for Road, Bridge and Municipal Construction): The Contractor shall rebuild, repair, restore, and make good all damages to any portion of the permanent or temporary Work occurring before the Physical Completion Date and shall bear all the expense to do so, except damage to the permanent Work caused by: (a) acts of God, such as earthquake, floods, or other cataclysmic phenomenon of nature, or (b) acts of the public enemy or of governmental authorities; or (c) slides in cases where Section 2-03.3(11) is applicable; Provided, however, that these exceptions shall not apply should damages result from the Contractor’s failure to take reasonable precautions or to exercise sound engineering and construction practices in conducting the Work.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay T. Watkins, Ahlers Cressman & Sleight PLLCMs. Watkins may be contacted at
Lindsay.Watkins@acslawyers.com
Congratulations to BWB&O’s 2023 Mountain States Super Lawyers Rising Stars!
August 07, 2023 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBWB&O is excited to announce Las Vegas Partners Devin Gifford and Madeline Arcellana have been selected in the 2023 Mountain States Super Lawyers list as Rising Stars for their work in Civil Litigation. To read Super Lawyers’ digital publication, please click
here.
SELECTED AS RISING STARS
Devin Gifford: 2023
Madeline Arcellana: 2023
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
A Court-Side Seat: Appeals and Agency Developments at the Close of 2020
December 29, 2020 —
Anthony B. Cavender - Gravel2GavelTHE FEDERAL APPELLATE COURTS
The U.S. Court of Appeals
On November 23, 2020, the court, in a 2-to-1 vote, rejected the plaintiff’s request for an emergency injunction pending appeal in the case of Manzanita Band of Kumeyaay Nation, et al. v. Wolf. The majority held the requirement for such relief did not meet the requirements set forth in Winter v. NRDC, 555 US 7 (2008). Here, the plaintiffs allege that that the government’s construction of a border wall violates several environmental laws that were illegally waived by the Secretary of the Interior. Judge Millett dissented in part because the plaintiffs demonstrated a likelihood of success on the merits. She pointed to the argument that the authority of the Secretary—or Acting Secretary—to take these actions has been successfully challenged in several federal district courts. An expedited pleading schedule was established by the court.
The U.S. Court of Appeals for the Fourth Circuit
On November 17, 2020, in Ergon-West ,Inc. v. EPA, the court again reversed the EPA’s decision denying regulatory relief to a small refinery seeking a waiver of the renewable fuels mandate of the Clean Air Act. Ergon is a small refinery and requested relief in the basis of the economic harm that compliance would entail. In 2018, the court ruled in Ergon’s favor and remanded the case back to the agency. After relief was again denied, the court held that “Ergon has come forward with sufficient evidence undermining one aspect” of the agency’s latest decision, and the ruling was returned to EPA for additional analysis. It appears that a complicated process has become even more complicated.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Eyerly may be contacted at
te@hawaiilawyer.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Defend Additional Insured Though Its Insured is a Non-Party
November 18, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe plaintiff insurer's motion for partial summary judgment seeking an order that defendant insurer was obligated to defend a non-party as an additional insured was granted. Am Empire Surplus Lines Ins. Co. v. Burlington Ins. Co., 2019 N. Y. Misc. LEXIS 4145 (N. Y. Sup. Ct. July 25, 2019).
Quality Building Construction, LLC was the contractor hired to work on exterior facade of a building owned by Central Park West Corporation. The underlying complaint alleged that Quality caused plastic spacers and pedestals used for the penthouse terrace to fall down the roof drain riser. A clog and rainwater backup resulted in water damage to apartment 8A. The resulting damage was allegedly due to the clogged roof drain riser.
Quality subcontracted the work to Mega State, Inc. The subcontract required Mega to indemnify and hold Quality harmless against claims in connection with Mega's work, as well as name Quality as an additional insured on a primary, non-contributory bases under Mega's CGL policy. Burlington issued a policy to Mega naming Quality as an additional insured. American Empire issued a CGL policy to Quality.
Quality was sued in the underlying action, but Mega was not. American Empire tendered a demand for coverage to Mega and Burlington, relying on the agreement between Quality and Mega. Burlington responded that Mega was not liable for the alleged damages. American Empire sued Burlington. Subsequently, Burlington accepted the tender to defend Quality in the underlying action, and reserved rights as to whether Burlington's policy was primary and on the question of indemnification. American Empire agreed to withdraw its suit if Burlington would modify its reservation of rights. Burlington refused.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Although Property Damage Arises From An Occurrence, Coverage Barred By Business Risk Exclusions
July 08, 2011 —
Tred R. Eyerly - Insurance Law HawaiiThe homeowners hired the insured to raise the structure of their home twenty-four inches above the flood zone. Lafayette Ins. Co. v. Peerboom, 2011 U.S. Dist. LEXIS 58985 (S.D. Miss. June 2, 2011). When the insured’s crew returned from lunch one day, they found the house had fallen from hydraulic jacks being used to raise the structure a few inches at a time. There was substantial damage to the entire structure.
The homeowners sued, asserting several claims, including negligence and breach of contract. The complaint alleged the homeowners entered a contract with the insured to raise their structure while maintaining its integrity. However, the insured failed to use proper equipment, which caused the house to fall and be completely destroyed.
The insured tendered the claim to its insurer, Lafayette Insurance Company. Lafayette defended under a reservation of rights and filed suit for a declaratory judgment. Lafayette’s subsequent motion for summary judgment contended there was no “occurrence” alleged in the underlying complaint and, even if there was, the business risk exclusions barred coverage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Counter the Rising Number of Occupational Fatalities in Construction
April 19, 2021 —
Joshua Jacobsen - Construction ExecutivePrior to the pandemic, the construction industry was experiencing mental and behavioral health stressors and increasing fatalities. The pandemic is contributing to these underlying conditions threatening the safety and wellbeing of the construction workforce:
- Workers in construction occupations experienced 1,066 fatalities, a 6.3% increase and the highest total since 2007. Across all industries slips, trips and falls resulted in 880 deaths, a 11.3% increase from the previous year;
- Increasing mental health challenges as evidenced by growing percentage of Americans starting therapy; and
- Rising risk of relapse to substance use disorders and especially opioid overdoses. Deaths from unintentional overdoses of non-medical drug or alcohol use while at work climbed slightly to 313, marking the seventh straight annual increase in this category.
Reprinted courtesy of
Joshua Jacobsen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Jacobsen may be contacted at
jjacobsen@holmesmurphy.com
Montrose III: Appeals Court Rejects “Elective Vertical Stacking,” but Declines to Find “Universal Horizontal Exhaustion” Absent Proof of Policy Wordings
September 14, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Montrose Chemical Corp. v. Superior Court (No. B272387; filed 8/31/17) (Montrose III), a California appeals court found that excess insurance is not triggered for continuous and progressive losses until there has been horizontal exhaustion of underlying insurance, but there is no “universal horizontal exhaustion” because the order or sequence in which excess policies may be accessed depends on the specific policy wording at issue.
The coverage lawsuit was initiated by Montrose in 1990, when it was named in environmental actions for continuous and progressive property damage emanating from its Torrance chemical plant since the 1960s. Montrose had varying levels of insurance coverage throughout, but the total limits and attachment points of differing levels of excess coverage in any given year had changed from year-to-year. The coverage action was stayed in 2006 due to concern of prejudice to the underlying defense, but the stay was lifted in 2014 with Montrose entering a consent decree in the CERCLA action.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of