Fifth Circuit Holds Insurer Owes Duty to Defend Latent Condition Claim That Caused Fire Damage to Property Years After Construction Work
September 21, 2020 —
Jeremy S. Macklin - Traub LiebermanMost general liability policies only provide coverage for “property damage” that occurs during the policy period. Thus, when analyzing coverage for a construction defect claim, it is important to ascertain the date on which damage occurred. Of course, the plaintiffs’ bar crafts pleadings to be purposefully vague as to the date (or period) of damage to property. A recent Fifth Circuit decision applying Texas law addresses this coverage issue in the context of allegations of a condition created by an insured during the policy period that caused damage after the policy expired.
In Gonzalez v. Mid-Continent Cas. Co., 969 F.3d 554 (5th Cir. 2020), Gilbert Gonzales (the insured) was a siding contractor. In 2013, the underlying plaintiff hired Gonzales to install new siding on his house. In 2016, the underlying plaintiff’s house was damaged in a fire. The underlying plaintiff sued Gilbert in Texas state court alleging that when Gonzalez installed the siding in 2013, he hammered nails through electrical wiring and created a dangerous condition that caused a fire three years later in 2016.
At the time Gilbert performed construction work, he was insured by Mid-Continent Casualty Company. Mid-Continent disclaimed coverage to Gonzales on the basis that the complaint unequivocally alleged that property was damaged in 2016 and there were no allegations that property damage occurred prior to 2016 or was continuing in nature.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy S. Macklin, Traub LiebermanMr. Macklin may be contacted at
jmacklin@tlsslaw.com
Flexible Seattle Off-Ramp Would Retain Shape in Quake
November 23, 2016 —
Tim Newcomb – Engineering News-RecordMoving from the lab to the field, a highway off-ramp bridge under construction in Seattle features memory-retaining metal rods and bendable concrete designed to provide the structure with flexibility sufficient to withstand a major seismic event.
Read the court decisionRead the full story...Reprinted courtesy of
Tim Newcomb, Engineering News-RecordEngineering News-Record may be contacted at
ENR.com@bnpmedia.com
Sacramento Water Works Recognized as a Historic Civil Engineering Landmark
October 03, 2022 —
The American Society of Civil EngineersRESTON, Va. – The American Society of Civil Engineers (ASCE) Sacramento Section today recognized the City of Sacramento Water Works a Historic Civil Engineering Landmark. The landmark, which was completed in 1854, was recognized at a dedication ceremony at the Sacramento History Museum led by ASCE's Sacramento Section, which is celebrating its centennial anniversary of the Section's founding. The section was joined by Ken Rosenfield, director, ASCE Region 9 and Chuck Spinks, chair, Region 9 History and Heritage Committee.
ASCE represents more than 150,000 members of the civil engineering profession worldwide. It is the oldest national engineering society in the United States. ASCE recognizes historically significant civil engineering projects, structures, and sites all over the world. More than 280 projects have earned the prestigious title for creativity and innovation, and almost all are executed under challenging conditions.
The City of Sacramento Water Works was the first municipal, city-owned water system west of the Mississippi River. This project was inspired by a disastrous fire in 1852 that destroyed 27 blocks in Sacramento and the city did not have a water system capable of putting out fires. The water works site was equipped with a distribution system with hydrants that could fight fires.
The City of Sacramento Water Works was nominated by the ASCE Sacramento Section Centennial Committee. For more information about ASCE's Historic Civil Engineering Landmark Program, go to https://www.asce.org/about-civil-engineering/history-and-heritage/historic-landmarks.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Design Firm Settles over Construction Defect Claim
July 31, 2013 —
CDJ STAFFA Pennsylvania township has announced that it has reached a settlement with the architectural firm that designed its administration building. Cee Jay Frederick Associates will be paying than $1.05 million to settle claims of defects in the design of the building.
West Whiteland’s administration building was completed in July 2007. The first leaks were noticed in November and December 2008. In response, the township stopped payments to the contractor, Magnum, Inc. Magnum sued, claiming that their work was not to blame for the leaks. Magnum joined the township in suing the design firm.
Although Cee Jay Frederick Associates will be paying the township to settle the claim, West Whiteland will be paying $75,000 of that back to the firm to settle outstanding bills that had been withheld during litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Newmeyer Dillion Announces Jason Moberly Caruso As Its Newest Partner
February 01, 2021 —
Newmeyer DillionProminent business and real estate law firm Newmeyer Dillion is pleased to announce that Newport Beach attorney
Jason Moberly Caruso has been elected to partnership.
"Jason has continually shown himself to be a gifted attorney, both in his ability to expand the firm's offerings in land use, environmental law, and the firm's growing appellate practice, as well as in his exceptional approach to client service," said the firm's Managing Partner, Paul Tetzloff. "His positive presence is felt wherever he goes, and we're honored to have him join the firm's partnership."
Caruso focuses his practice on various aspects of "contaminated sites" environmental legal work, complex litigation, and appellate matters. He counsels and represents current and former facility owners and operators in state and federal proceedings, administrative actions, cost recovery cases, and non-litigation site remediation situations. The litigated matters frequently involve the federal Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and its parallel California Hazardous Substances Account Act (HSSA). When clients must go to court, Caruso applies his significant experience in complex state and federal litigation over a broad range of substantive areas, including environmental, business, real estate, construction, and products liability. His experience extends from pre-litigation through trial and post-trial proceedings.
Caruso's practice also includes a special emphasis on appellate matters. Caruso has briefed and argued multiple appeals in the state and federal courts, obtaining victories for clients in general appellate and extraordinary writ proceedings. Caruso has prosecuted and defended appeals involving the firm's existing cases and clients, but has also been engaged by outside clients after the conclusion of trial court proceedings.
An active member of the community, Caruso serves as a mock trial attorney coach for University High School through the Constitutional Rights Foundation Orange County (CRF-OC) and as a member of CRF-OC's Board of Directors. He also serves as a member and secretary of the Orange County Bar Association's Professionalism & Ethics Committee, and is a member of the executive committee of the William P. Gray Legion Lex Inn of Court. Caruso is also committed to pro bono work, endeavoring always to be representing at least one pro bono client via Orange County's Public Law Center.
Caruso earned his B.A., cum laude, from the University of Southern California, and his J.D., cum laude, from the University of California, Hastings College of Law.
About Newmeyer Dillion
For 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that achieve client objectives in diverse industries. With over 65 attorneys working as a cohesive team to represent clients in all aspects of business, employment, real estate, environmental/land use, privacy & data security and insurance law, Newmeyer Dillion delivers holistic and integrated legal services tailored to propel each client's operations, growth, and profits. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of
Mega-Consulate Ties U.S. to Convicted Billionaire in Nigeria
May 30, 2022 —
Neil Munshi & William Clowes - BloombergOn March 31, billionaire Gilbert Chagoury stood atop the plot of land he’d dredged from the sea around Lagos, beaming in the sweltering heat alongside U.S. Consul-General to Nigeria Claire Pierangelo, as they broke ground for America’s largest consulate in the world.
As a cool spring rain fell on Washington that day, Republican Congressman Jeff Fortenberry, of Nebraska, resigned from the House of Representatives after a conviction announced a week earlier. His crime: lying to the Federal Bureau of Investigation about illegal campaign contributions he’d received from Chagoury.
The pageantry in Lagos obscured the uncomfortable fact that by placing its $537 million consulate on Chagoury’s Eko Atlantic development, the U.S. government was becoming the anchor tenant for a project run by a man who was once convicted of laundering money for a Nigerian dictator and who’s admitted to making illegal campaign contributions in the U.S. Ethics groups and Nigeria experts aren’t pleased with the choice.
Reprinted courtesy of
Neil Munshi, Bloomberg and
William Clowes, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Heatup of Giant DOE Nuclear Waste Melter Succeeds After 2022 Halt
August 21, 2023 —
Tim Newcomb - Engineering News-RecordBefore 56 million gallons of long-stored radioactive waste at the federal Hanford nuclear waste site in Washington state can be turned into vitrified glass for disposal beginning in 2024, crews from the U.S. Energy Dept and Bechtel National that built and are commissioning the site's giant waste vitrification plant need to heat up its two 300-ton melters, the world's largest, to 2,100° F.
Reprinted courtesy of
Tim Newcomb, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Contractor’s Burden When It Comes to Delay
October 26, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen a contractor is challenging the assessment of liquidated damages, or arguing that it is entitled to extended general conditions, the contractor bears a burden of proof to establish there were excusable delays that impacted the critical path and, in certain scenarios, the delays were not concurrent with contractor-caused delay:
When delays are excusable, a contractor is entitled to a time extension, such that the government may not assess liquidated damages for those delays. The government bears the initial burden of proving that the contractor failed to meet the contract completion date, and that the period of time for which the government assessed liquidated damages was correct. If the government makes such a showing, the burden shifts to the contractor to show that its failure to timely complete the work was excusable. To show an excusable delay, a contractor must show that the delay resulted from “unforeseeable causes beyond the control and without the fault or negligence of the Contractor.” “In addition, the unforeseeable cause must delay the overall contract completion; i.e., it must affect the critical path of performance.” Further, the contractor must show that there was no concurrent delay.
Ken Laster Co., ASBCA No. 61292, 2020 WL 5270322 (ASBCA 2020) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of