When Are General Conditions and General Requirements Covered by Builder's Risk
December 18, 2022 —
Michael V. Pepe & Grace V. Hebbel - Saxe Doernberger & VitaGeneral conditions and general requirements are terms of art in the construction industry that describe the indirect costs necessary to complete a construction project. After physical loss or damage to a project, the following question often arises: Are “general conditions” and “general requirements” covered under a builder’s risk policy?
General Conditions vs. General Requirements
General conditions are usually described as the cost of managing a construction project. Examples include salaries for personnel like project managers, supervisors, engineers, field office staff, as well as the cost of field trailers, office equipment and supplies, and anything necessary to support the staff.
General requirements are the non-management indirect costs of executing the project, including items such as pre-development costs, permits, security, dumpsters, fences, temporary lighting, worker amenities, and clean-up costs.
Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & Vita and
Grace V. Hebbel, Saxe Doernberger & Vita
Mr. Pepe may be contacted at MPepe@sdvlaw.com
Ms. Hebbel may be contacted at GHebbel@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Cyber Thieves Phish Away a $735K Payment to a Minnesota Contractor
May 06, 2024 —
Richard Korman - Engineering News-RecordThe contractor's project manager asked for money due, $735,000 under Payment Application 13, to be sent by the owner electronically. "Hi Rick," the project manager, whose first name is Jalen, wrote in an email dated Aug. 15. "Can we have payments remitted electronically as we currently have numerous uncleared checks on hold?"
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Recent Supreme Court Decision Could Have Substantial Impact on Builders
January 23, 2023 —
Cassidy Ingram - Ahlers Cressman & SleightOn October 27, 2022, the Washington State Supreme Court issued a decision which could have a substantial impact on the enforceability of contract clauses that require litigation to be commenced within a stated period of time from project completion. In Tadych v. Noble Ridge Construction, Inc.,the Supreme Court held that the contractual one-year statute of limitations for bringing claims against the contractor was substantively unconscionable and reversed the Court of Appeals.
In Tadych, plaintiff owners (the Tadychs) contracted with defendant contractor (Noble Ridge Construction, Inc., or NRC) for the construction of a custom home in 2012. The contract included a one-year claim limitations clause that required claims to be raised within a one year period from project completion and that any claims not raised during the one-year period would be waived. In December 2013, as the project neared completion, the Tadychs met with NRC to identify any outstanding project issues. The Tadychs noted several, including rainwater pools at the landing at the bottom of the stairs and several nicks and cracks on the stucco exterior walls.
The Tadychs moved into the home on April 8, 2014, and the City of Seattle Department of Planning and Development conducted its final site inspection on April 15 and approved the residence for occupancy on April 23. In January or February of 2015, the Tadychs began to notice a shift in their home. In February of 2015, the Tadychs engaged the Construction Dispute Resolution (CDR) to review NRC’s work. CDR raised concerns about the adequacy of the home’s construction and prepared a written report in March 2015 indicating several deviations from the architectural plans and building codes. The Tadychs sent this report to NRC, who assured the Tadychs that NRC’s work followed all requirements and rejected any claims that there were deviations from the plans. The Tadychs continued to notice issues with the home through October 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Cassidy Ingram, Ahlers Cressman & SleightMs. Ingram may be contacted at
cassidy.ingram@acslawyers.com
PFAS: From Happy Mistake to Ubiquity to Toxic Liability (But is there coverage?)
March 14, 2022 —
Michael S. Levine & Rachel E. Hudgins - Hunton Andrews KurthIn 1938, a DuPont chemist’s experiment yielded not—as he first thought—a lumpen, waxy mistake, but a new chemical with remarkable properties: heat-resistance, chemical stability, and low surface friction. Decades of continuing experimentation yielded a class of chemicals with the capacity to make non-stick, water-resistant coatings. In time, these chemicals, per- and polyfluoroalkyl substances (PFASs), would become a major component in thousands of consumer goods: food packaging, non-stick cookware, waterproof clothing, paint, stain-resistant carpets and furniture, and firefighting foams. The discovery of the toxicity of these remarkable chemicals lagged behind the widespread adoption, but eventually yielded a moniker that reflected PFAS’s stability and longevity: “Forever Chemicals.”
In October 2021, the Biden administration announced
a plan to address, among other concerns, PFAS’s migration to drinking water sources. EPA Administrator Michael S. Regan debuted the plan in Raleigh, North Carolina alongside Governor Roy Cooper.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Rachel E. Hudgins, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Upholds Denial of Collapse Coverage Where Building Still Stands
October 02, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe Michigan Court of Appeals affirmed the trial court's decision finding the policy's collapse coverage did not apply. Cmty. Garage v. Auto-Owners Ins. Co., 2018 Mich. App. LEXIS 2680 (Mich. Ct. App. June 19, 2018).
The insured operated a truck repair business. In June 2016, the insured's place of business sustained damage due to failure of several trusses providing structural support to the building's roof. The failure was due to latent construction defects leading to an insufficient load bearing capacity. The roof began to sag while one of the walls bulged outward due to the sudden pressure overload. The insured hired a construction firm to install temporary shoring to support the roof and prevent further damage. All of the building's walls remained standing and, although the roof sagged, it also remained intact. However, the building could not be safely occupied until repairs were completed.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Should a Subcontractor provide bonds to a GC who is not himself bonded? (Bonding Agent Perspective)
May 03, 2017 —
Christopher G. Hill - Construction Law MusingsGuest Post Friday is back, and for this week, Construction Law Musings welcomes Steve Moore. Steve has been the Construction & Surety Manager for Towne Insurance Agency-Invincia, in Chesterfield, VA since 2010. Steve’s experience in the Virginia surety bonding marketplace started in 1985 with USF&G. His underwriting travels took him from USF&G to starting National Grange Mutual’s mid-Atlantic bond department over Virginia, Maryland, Delaware, North & South Carolina, to being Reliance Surety’s “Firemark” bond manager in Virginia. Reliance was purchased by Travelers, where Steve continued to grow the surety book of business and build expertise and relationships. Experience with Travelers and Zurich had Steve handling surety bonds for some of Virginia’s largest and best-of-class contractors. Recently, he was contracted by the Commonwealth’s Attorney’s office to serve as a contract surety expert witness on behalf of the state. He is a 1985 graduate of Virginia Tech with double-major B.S. degrees in Finance and Marketing.
Today, Steve has business and relationships with Travelers, The Hartford, Westfield, CNA, CBIC, Selective, Liberty Mutual, Ohio Casualty, Cincinnati, and many other companies. Steve’s strong foundation of insurance knowledge and in bonding principles and practices allow him to serve as a great resource for his clients.
An old Aesop fable comes to mind when I am asked whether a Sub should bond to an unbonded GC:
"A woodsman entered the forest and asked the trees to give him a handle made of the best wood. After giving the woodsman a stave of hickory, the forest watched the woodsman fashion an axe onto the handle. In a flash, the woodsman began to chop down the various oaks and maples in the forest. The oak then said to a pine, “It serves us right, since we gave our adversary the very thing that contributes to our doom…"
When a subcontractor client of mine asks about bonding to an un-bonded general contractor, a number of questions immediately come to mind. Why isn’t the GC bonded? What is the existing relationship between the GC and Sub? How well is the job financed? While wanting to help my subcontractor procure work, and surely enjoying the commissions from writing a bond, I also want to help my sub client manage unforeseen risk. What are the risks to a sub, when posting a bond to an unbonded GC?
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
NYC Design Firm Executives Plead Guilty in Pay-to-Play Scheme
June 18, 2019 —
Engineering News-RecordTwo former top executives of New York City-based engineer HAKS pleaded guilty in city court May 13 to bribe charges related to efforts to gain municipal water infrastructure contracts, according to court filings, an attorney for its ex-chief financial officer and plea agreements provided to ENR by the Manhattan district attorney's office.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
City Potentially Liable for Cost Overrun on Not-to-Exceed Public Works Contract
June 29, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPOn a public works construction project, a contractor incurred additional costs and asserted a claim against the city. The city denied the claim because the contract had a not-to-exceed price, and the city council and mayor did not approve contract modifications to exceed that amount. City ordinances require approval for contract modifications and change orders exceeding ten percent of the original not-to-exceed amount.
But the contractor argued that the ordinance did not apply because the excess costs did not result from a contract modification or change order. In addition, the contractor argued that, in refusing to approve an increase in the not-to-exceed amount, the city breached the implied duty of good faith and fair dealing. The court concluded that these questions were factual issues for the jury to decide.
Read the court decisionRead the full story...Reprinted courtesy of