Subcontractor Not Liable for Defending Contractor in Construction Defect Case
February 10, 2012 —
CDJ STAFFThe California Court of Appeals has ruled on January 9, 2012 in Hensel Phelps Construction Company v. Urata & Sons Cement, upholding the judgment of the lower court.
Hensel Phelps was the general contractor for a high-rise in Sacramento. They were sued by the owners of the building after problems were discovered in the concrete slabs of the building’s parking garage. Instead of welded steel wire mesh, the slabs had been constructed with fiber mesh. Hensel Phelps filed a cross-complaint against Urata Cement, the subcontractor that had performed the cement work. Urata refused to defend Hensel Phelps. The owners’ case was subsequently dismissed due to the statute of limitations.
Although the original case was over, Hensel Phelps continued in their claims against Urata. “Urata argued that a handwritten interlineation required Hensel Phelps to prove Urata was at fault for the injury alleged in the building owners’ complaint before Urata was obliged to defend Hensel Phelps in that action.”
The lower court concluded that Urata would have been obligated to defend Hensel Phelps if the owners’ lawsuit had alleged that the damage was due to the subcontractor’s work or if evidence at trial established this. The lower court found neither of these true. Instead, the use of the fiber mesh was a design issue and “that decision was outside the scope of the subcontractor’s work.”
During the trial, Hensel Phelps conceded that Urata was not at fault. The appeals court could find no reading of the contract that would cause Urata to be obligated to defend Hensel Phelps, calling Hensel Phelps’s reading of the contact as “grammatically infeasible.”
Judges Nicholson, Raye, and Butz upheld the decision of the lower court and awarded costs on appeal to Urata.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Largest Dam Removal Program in US History Reaches Milestone
December 11, 2023 —
Mary K. Miller - Engineering News-RecordAll work associated with removal of the first of four hydroelectric dams slated for demolition on the Klamath River completed in early November, according to the dam owner, Klamath River Renewal Corp. Demolition of the four dams on the Klamath River that flows through parts of Oregon and California is the largest dam removal project in U.S. history.
Reprinted courtesy of
Mary K. Miller, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Idaho Federal Court Rules Against Sacketts After SCOTUS Decided Judicial Review of an EPA Compliance Order was Permissible
May 13, 2019 —
Anthony B. Cavender - Gravel2GavelIn a decision released on March 31, in Sackett v. EPA, the U.S. District Court for Idaho held, without benefit of oral argument, that the Environmental Protection Agency’s (EPA) motion for summary judgment should be granted, and accordingly, the Sacketts had violated the Clean Water Act (CWA) by making improvements to 0.63 acres of land they owned without a required CWA permit when the land qualified as a “wetlands.”
The EPA had determined the Sacketts’ “property is subject to the CWA because it contains wetlands adjacent to Priest Lake, a traditionally ‘navigable water,’ and, additionally, their property is wetland adjacent to a tributary and similarly situated to other wetlands and has a significant nexus to Priest Lake.” The District Court rejected the Sacketts’ arguments that their property was not a “wetlands” subject to the CWA.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Wine without Cheese? (Why a construction contract needs an order of precedence clause)(Law Note)
August 11, 2011 —
Melissa Brumback, Construction Law in North CarolinaFor today’s law note, I’m addressing a comment that came to me last week from Dave O’Hern of Miller O’Hern Construction. Dave writes:
I am a general contractor doing a fuel tank replacement project for our county. In the specifications there is a spec for a UL 142 tank, on the plans the spec references UL 2085 ? a much more expensive tank. My subcontractor bid the UL 142 tank. The specifications state that the specs and plans are on the same level of precedence.
The county wants me to furnish the more expensive tank without compensation citing the clause that states the plans and specs are complementary and what is called for by one is binding as if called by all and the most stringent requirement will apply.
Read the full story…
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
The Oregon Tort Claims Act (“OTCA”) Applies When a Duty Arises from Statute or Common Law and is Independent from The Terms of a Specific Contract. (OR)
February 25, 2014 —
Natasha Khachatourians – Scheer & Zehnder LLP Liability NewsletterCase: Jenkins v. Portland Housing Authority, 260 Or.App. 26, 316 P.3d 369 (2013).
Issue: Do tort claims arising from a rental agreement fall within the exemption from the definition of a tort under the OTCA? NO.
Facts: Plaintiff rented an apartment in a public housing complex operated by the Portland Housing Authority (“PHA”). While walking in the hallway of the building, Plaintiff slipped on a puddle of water that had leaked from a broken washing machine in a nearby laundry room. Plaintiff fell and was injured. The trial court granted summary judgment to PHA, finding that the PHA was considered a public body under the OTCA and, as a result, enjoyed discretionary immunity from liability.
The issue before the court was whether the OTCA applied to a claim under the Oregon Residential Landlord Tenant Act (“ORLTA”) since an ORLTA claim generally arises out of a rental agreement. Plaintiff did not plead breach of a specific provision of the rental agreement, and she conceded that she had alleged a breach of a legal duty resulting in injuries. Plaintiff argued, however, that her claim involved a duty arising from the rental agreement. As such, she contended her claim fell within the exception of the definition of a “tort” under OTCA, and thus the OTCA should not apply to give PHA discretionary immunity.
Read the court decisionRead the full story...Reprinted courtesy of
Natasha Khachatourians, Scheer & Zehnder LLP Ms. Khachatourians may be contacted at
natashak@scheerlaw.com
Drafting or Negotiating A Subcontract–Questions To Consider
June 21, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to drafting and negotiating a subcontract, there are provisions that should be important to you from a risk assessment standpoint. From the subcontractor’s standpoint, below are questions you should ask, or issues you should consider, as you go through the subcontract. These are the same questions and issues that are also important to a contractor as the contractor will want to ensure these issues are included in the subcontract. By asking yourself these questions, you can check to see how the subcontract addresses these issues, and how the risk should be negotiated. Hopefully, you are working with counsel to make sure you understand what risk you are assuming and those provisions you want to try to push back on. Asking yourself these questions, or considering these questions, will help you go through the subcontract with a purpose based on the risk profile of the project and certain risk you don’t want to assume.
- Prime Contract –> Does the subcontract incorporate the prime contract? Make sure to request the prime contract since the subcontract will identify the prime contract as part of the Subcontract Documents and will require you to assume towards the contractor the same obligations the contractor is required to assume towards the owner.
- Scope of Work –> What is the scope of work? Is it clear. Make sure the scope is clear and you understand the scope.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Contractors with Ties to Trustees Reaped Benefits from LA Community College Modernization Program
March 03, 2011 —
Gale Holland, Michael Finnegan and Doug Smith, Los Angeles TimesIn the latest installment of the “Billions To Spend” series of investigative reports focused on construction defects, management, and cost issues relevant to LACC’s Community College Modernization Projects, the LA Times examines the costs associated with the various layers of construction management and benefits that accrued to contractors with ties to LACC trustees.
The reporting by the Times is seemingly critical of the project’s utilization of “body shops” an industry term for companies that function as employers of record. The article segment published today cites a number of circumstances wherein their utilization appears to have escalated costs substantially.
“To gauge the cost of the staffing system, The Times reviewed thousands of pages of financial records from April 2007, when URS began managing the program, to July 2010. Reporters identified two dozen contractors serving as conduits for pay and benefits for employees they did not supervise.
At least 230 people were employed in this manner, at a total cost of about $40 million, the records show.
Approximately $18 million of the total was paid to the employees, according to the Times analysis. The remaining $22 million went to profit and overhead for contractors, the records indicate.
For employees on its own payroll, the district says that medical and other benefits increase compensation costs 40% above base salaries. So if the district had employed its construction staff directly, the total cost for the period studied would have been $25 million instead of $40 million, a savings of $15 million, The Times calculated.”
Read Full Story...
Read the court decisionRead the full story...Reprinted courtesy of
New FAR Rule Mandates the Use of PLAs on Large Construction Projects
October 10, 2022 —
Reggie Jones - ConsensusDocsThe Federal Acquisition Regulatory Council recently published a proposed ruled that, once implemented, will require the use of project labor agreements (PLAs) on federal construction projects with a contract value of $35 million or greater. The proposed rule revokes President Obama’s Executive Order 13502 and implements an Executive Order 14063 (E.O. 14063) issued on February 9, 2022. E.O. 14063 addresses the use of PLAs in the government contracts. Under the current Federal Acquisition Regulation (FAR), the use of PLAs on “large-scale construction projects” is discretionary. The new rule proposed by the Department of Defense (DOD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA) revises the FAR contract clauses making the use of PLAs mandatory.
Under the proposed rule, contractors performing “large-scale construction projects” will be required to “negotiate or become a party to a [PLA] with one or more appropriate labor organizations.” FAR 52.222-33. A PLA is in essence a collective bargaining agreement between a local trade union and contractor that governs employment terms, including wages and benefits, for union and non-union workers. Although the PLA mandate only applies to large-scale construction projects with the contract value of $35 million and more, under the proposed rule, agencies have the option to include the PLA requirement for construction projects that are under the $35 million threshold. The proposed rule also sets out a flow-down requirement, which means that subcontractors working on a large-scale project must likewise be familiar with and comply with terms of the PLA negotiated by a prime contractor.
Read the court decisionRead the full story...Reprinted courtesy of