The U.S. Flooded One of Houston’s Richest Neighborhoods to Save Everyone Else
December 01, 2017 —
Shannon Sims - Bloomberg“Next contestant, come on down.” On Oct. 6, in a bright courtroom in downtown Houston, Susan Braden, chief justice of the U.S. Court of Federal Claims, opens a preliminary hearing with a joke, beckoning a lawyer forward. Braden has flown in from Washington to oversee disputes involving the homes and businesses flooded in West Houston after Hurricane Harvey made landfall over Texas in late August. She has summoned attorneys interested in suing, to get their thoughts on how the proceedings should unfold.
Almost 100 lawyers are present, combed and buzzing in anticipation of what promises to be some of the most complex and expensive litigation ever brought against the federal government. Observers speculate that thousands of plaintiffs could eventually join in, and that the total damages claimed could reach $10 billion or more, especially if the big energy and oil companies—whose presence in one section of West Houston gave it the nickname the Energy Corridor—sue over their flooded headquarters. Eighty suits, 11 of which are seeking class-action status, have been filed by homeowners against the federal government, though many of the Energy Corridor’s approximately 9,500 residents are still weighing their options, speed-dating lawyers by phone and at community meetings.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon Sims, Bloomberg
Boston Contractor Faces More OSHA Penalties
February 21, 2022 —
Scott Van Voorhis - Engineering News-RecordThe head of a Boston-based construction company that lost two workers in a
fatal accident at a downtown Boston worksite last year now faces nearly $2 million in total fines after safety violations on a new project.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
A Reminder to Get Your Contractor’s License in Virginia
April 25, 2023 —
Christopher G. Hill - Construction Law MusingsHow are ducks and contractors alike? A question I get often, particularly from construction contractors outside of Virginia is whether they need to get a Virginia contractor’s license. The answer is almost invariably “yes.” The next question is why? The answer is almost always “Because state law says so.” With some minor exceptions for material suppliers and the like, Virginia law requires that all of those that perform construction for others carry the proper license and specialization for the work performed. There is no exception for the proverbial “paper contractor” that takes money from an owner and subcontracts all of the actual physical work. It does not matter if you use a different term for what you do for the owner. If it walks like a duck and quacks like a duck. . .its a duck. If you take money to perform construction, you’re a contractor.
Some of the consequences of contracting without a license (aside from possible criminal charges) include among other things, the inability to perfect a mechanic’s lien under Va. Code 43-3(D) and, with minor exceptions, the ability to enforce a contract (meaning it really hurts your ability to get paid).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Texas covered versus uncovered allocation and “legally obligated to pay.”
April 27, 2011 —
CDCoverage.comIn Markel American Ins. Co. v. Lennar Corp., No. 14-10-00008-CV (Tex. Ct. App. April 19, 2011), insured homebuilder Lennar filed suit against its insurer Markel seeking recovery of costs incurred by Lennar to repair water damage to homes resulting from defective EIFS siding. Following a jury trial, judgment was entered in favor of Lennar and against Markel. On appeal, the intermediate appellate court reversed. Applying Texas law, the court first held that Lennar failed to satisfy its burden of allocating damages between covered and uncovered. In a prior decision, the court had held that, while the costs incurred by Lennar for the repair of the resulting water damage
Read the full story…
Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
Specification Challenge; Excusable Delay; Type I Differing Site Condition; Superior Knowledge
January 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesAn Armed Services Board of Contract Appeals dispute, Appeal of L.S. Black-Loeffel Civil Constructors JV, ASBCA No. 62402, 2023 WL 5827241 (ASBCA 2023), involved which party bore liability for delay—the federal government or the prime contractor–based on various legal theories. Without detailing the factual details, a number of interesting legal issues were raised in this dispute including (1) a defective specification challenge, (2) excusable delay, (3) Type I differing site condition, and (4) superior knowledge. These legal issues are discussed below.
1. Specification Challenge (Defective Specifications)
The contractor claimed that the government’s specifications were defective in regard to a thermal control plan. The government countered that the specifications were not design specifications but performance specifications. The specifications were performance based because they did not tell the contractor how to achieve the performance-based criteria.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Failure to Comply with Sprinkler Endorsement Bars Coverage for Fire Damage
July 31, 2013 —
Tred Eyerly, Insurance Law HawaiiDespite its application stating otherwise, the insured's failure to install a sprinkler system in its building barred coverage for extensive damage caused by fire.American Way Cellular, Inc. v. Travelers Prop. Cas. Co. of Am., 2013 Cal. App. LEXIS 425 (Cal. Ct. App. May 30, 2013).
American Way contacted a broker, A&J, regarding liability and property coverage. A&J sent American Way an application for a policy with Travelers. The application indicated American Way had a sprinkler system and fire detectors in its building.
Travelers issued a policy with a Protective Safeguards Endorsement For Sprinkler Locations and Restaurants. The endorsement stated that as a condition of the insurance, the insured was required to maintain a sprinkler system. An exclusions section said the insurer would not pay for loss caused by fire if there was no sprinkler system.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Court finds subcontractor responsible for defending claim
May 18, 2011 —
CDJ STAFFIn an unpublished decision, the California Fourth Appellate District Court has reversed the judgment of Judge Linda B. Quinn of the Superior Court of San Diego. In the case Inland California, Inc. v. G.A. Abell, Inland, a general contractor had subcontracted with Apache Construction and Precision Electric Company (G.A. Abell).
Apache alleged that extra demolition and drywall work was needed due to Precision’s electrical work. Inland tendered a defense of Apache’s claims. However, Precision did not provide any defense. Inland withheld payment from Precision.
At trial, Inland “conceded Precision earned the $98,000 in progress payments Inland withheld.†They were obligated to additionally pay Precision’s costs and attorney fees.
The Fourth Appellate District court has overturned this and remanded the case back to the lower court. The judges determined that Precision was obligated to defend itself against the claims raised by Apache and therefore vacated the judgment against Inland.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
“Time Is Money!” In Construction and This Is Why There Is a Liquidated Damages Provision
February 01, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn construction, the adage “Time is Money!” rings true for all parties involved on a project. This includes an owner of a project that wants a project completed on time, i.e., by a substantial completion date. While substantial completion is often defined as when an owner can use a project for its intended purpose, this intended purpose typically equates to beneficial occupancy (in new construction) and other factors as identified in the contract.
The best mechanism for an owner to reinforce time and the substantial completion date is through a liquidated damages provision (also known as an LD provision) that includes a daily monetary rate for each day of delay to the substantial completion date.
A liquidated damages provision is not designed, and should NEVER be designed, to serve as a penalty because then it would be unenforceable. Instead, it should be designed to reasonably compensate an owner for delay to the substantial completion date that cannot be ascertained with any reasonable degree of certainty at the time the contract is being negotiated and executed. (Liquidated damages are MUCH easier to prove than actual damages an owner may incur down the road.) As an owner, you don’t really want to assess liquidated damages because that means the project is not substantially completed on time. And, in reality, a timely completed and performing project should always be better and more profitable than a late and underperforming project. However, without the liquidated damages provision, there isn’t a great way to hold a contractor’s feet to the fire with respect to the substantial completion date.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com